SPECIAL MEETING AGENDA 30 NOVEMBER 2022
Finance
It was identified prior to the invitation to quote process that the approved budget was not enough to
complete the entire scope of the project. Council invited quotes on a schedule of rates basis to
facilitate a scope reduction to fit within the budget. The scope will be confirmed with Durack Civil Pty
Ltd on award.
The funding sources for the project are detailed in the table below.
Funding Source Amount (GST excl.)
Local Roads and Community Infrastructure – Phase 3 Fund $1,292,692
Council Capital $0,000,000
Total Funding $1,292,692
Risks & Opportunities
Finance Risks Mitigation
Budget Overrun Council will engage contractor under schedule of
rates contract and work with contractor to ensure the
project scope fits within approved budget. Further
project scope increase will be mitigated through
ongoing and stringent monitoring and controls by the
project working group and the Capital Works Project
Control Group and in regular reports to Capital
Works Executive meetings.
In defining the detailed scope of works, contingency
will be allowed to address unforeseen risks.
Material price increases Council will engage contractor under schedule of
rates contract with locked in material rates not
subject to rise and fall. A relatively short contract
period is expected which mitigates this risk.
Contractor becomes insolvent Council has carried out a financial viability check on
the preferred contractor which proved acceptable.
The contractor appears to be a well-established
contractor.
Program Risks Mitigation
Delays due to wet weather. Extensions of time over and above those provided in
the quote are assessed by the Superintendent. The
project is commencing in a traditionally wet period
and the risk is considered medium-high.
Contingency will be included in finalising the scope
of work to make reasonable allowance for inclement
weather.
Resource risk The contractor has nominated a capable and
experienced project team to undertake construction.
Council’s resources to the project will be monitored
by the Project Control Group and Capital Works
Executive due to the high volume of work in the
capital works program.
Construction takes longer than allowed for The contractor is well resourced and has the
available resources to deliver this project
successfully. The risk is mitigated through the
contract, and will be closely monitored by the Project
Officer
Page 6 of 14