               4.     ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                           Plan No.              Rev.    Plan/Document Name                            Date

                           S23-112-C02           A       Civil Works Plan – As annotated by Council 25/09/2023

                           S23-112-C03           A       Typical Details                               25/09/2023

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 29 November 2025, unless an application to extend the currency
                      period is approved by Council.
               GENERAL CONDITIONS
                      Engineering
               3.     A revised Construction Management Plan (CMP) must be submitted to Council prior to the
                      pre-start meeting. Note that due to the location of the site Council is unlikely to support
                      excessive construction vehicles parking along Seaview Terrace. The revised CMP must
                      specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction.
                              ii.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased. Note that pedestrian
                                       access along Seaview Terrace including but not limited to the public beach
                                       access must be maintained at all times.
                              iii.     Proposed fencing to the site during the construction phase of the development.
                              iv.      Adequate parking arrangements for construction workers. Note that public and
                                       emergency vehicle access along Seaview Terrace must be maintained at
                                       all times. Construction vehicles are to abide by parking rules and
                                       regulations and are not to block resident’s driveways or park on yellow line
                                       marking under any circumstances. The revised CMP must provide an
                                       alternative carpark location and transportation for construction vehicles
                                       should public carparks be occupied.
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off.
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures.
                      c.      Works programme identifying key components of the works and their respective
                              durations.
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues.




                                                                                                           Page 2 of 7
Document Set ID: 22733163
Version: 3, Version Date: 15/12/2023

Used in these records

About this file

File size
163 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - OPW23 0175 [As Published].pdf · 163 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.