Decision Notice - OPW23 0175 [As Published] · OPW23/0175
e. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
f. Include signage in prominent locations on the boundaries of the site advising of the
proposed development, the expected time frames and the site contact details.
g. identification of complaint management procedures including:
i. Contact details for the on-site manager
ii. Dispute resolution procedures
h. For haulage operations involving significant volumes of fill material or excavated
material being transported onto or off the site: details on the location of external fill
sites/sources, the haulage route, type of vehicle to be utilised during filling operations
and frequency of usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense.
4. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting.
5. The principal contractor must have all the appropriate insurance and public liability
documentation to carry out the works. The principal contractor is also responsible to ensure
that any subcontractors also have the appropriate insurance and public liability
documentation. Certificates demonstrating currency of public liability insurance and works
insurance covering the works must be submitted to Council prior to the prestart meeting.
6. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is (07) 5329 6500.
The pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
7. Prior to the commencement of municipal works associated with this development, Council
requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum
of $5000) of the value of the municipal works. See Advisory Notes for details of the return of
bond monies.
8. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
9. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
10. This approval shall comply with all the conditions of related approval as stipulated in the
Development Tribunal’s Decision Notice dated 17 April 2023 referenced as Appeal 23-005
(Council Reference MCU21/0212).
DURING CONSTRUCTION
Engineering
11. The integrity and condition of any existing public or Council infrastructure and services
(above ground and/or underground) must not be adversely affected by the proposed works
12. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
13. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
Page 3 of 7
Document Set ID: 22733163
Version: 3, Version Date: 15/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - OPW23 0175 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 163 KB (small file)
- File type
No other editions are linked here.