1909-13367 SRA referral response approved docs

Attached to the e-mail SARA Referral agency response – with conditions - MCU19/0114 & RAL19/0027.

of 146

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (31.2 MB): the original may take a few minutes to open or download. The page text below is quick to read.

The proposed site will have four major sub-catchments. The proposed treatment train will consist of
four bioretention basins, one for each sub-catchment.

Table 7 outlines the developed catchment details and the relevant treatment device.
The model layout is presented in Figure 3 below.

Table 8 – Catchment Summary / Treatment Details

                                                         Catchment
Sub-Catchment
                       BioBasin               BioBasin              BioBasin               BioBasin
                      Catchment 1            Catchment 4           Catchment 2            Catchment 3

      Area              56,980m2               2,750m2               18,140m2               29,450m2


 % impervious         87% approx.            100% approx.          87% approx.            87% approx.


                   Bioretention Basin 1                         Bioretention Basin 2   Bioretention Basin 3
                   Filter Area = 550m2    Bioretention Basin    Filter Area = 500m2    Filter Area = 500m2
                        minimum                   4                  minimum                 minimum
                   Extended Detention     Filter Area = 40m2    Extended Detention     Extended Detention
  Treatment                                    minimum
                      Depth = 0.3m                                 Depth = 0.3m           Depth = 0.3m
 device details
                    Area at the top of    Extended Detention     Area at the top of     Area at the top of
                   Extended Detention        Depth = 0.3m       Extended Detention     Extended Detention
                     Depth = 650m2        Filter Depth = 0.5m     Depth = 600m2          Depth = 600m2
                   Filter Depth = 0.5m                          Filter Depth = 0.5m    Filter Depth = 0.5m

  Flow Route                        LPOD 1                            LPOD 2                 LPOD 3



Figure 3 outlines the treatment train’s effectiveness and the pollutant load reductions achieved from
MUSIC stormwater modelling program. A larger image is provided in Appendix AB.




                         Figure 3 – MUSIC Model & Pollutant load reductions

Table 8 outlines the treatment trains effectiveness.



                                      Stormwater Management Report                                       14
S19-007                                 122 & 144 Myall St, Cooroy
Log in to download the original file

1909-13367 SRA referral response approved docs.pdf · 31.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.