Subdivision Decision Notice · OPW16/0051
Attached to the e-mail OPW16/0051 - Operational Works Application (REC15/0023).
REC15/0023
8. All easements must be created and granted at no cost to the Grantee.
9. All works must be kept clear of any existing or proposed easements on the subject
land, unless agreed otherwise in writing by the Grantee.
Water and Sewer Connections
10. An underground connection to reticulated water and sewerage must be provided to
each lot in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
11. Prior to the endorsement of the Plan of Survey by Council a written confirmation
from Unitywater must be provided to Council to confirm that the proposed lots are
provided with their own separate connection to the sewer system and in
compliance with the requirements of Unitywater.
12. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection
to reticulated water and sewerage has been provided to each lot.
Frontage Reinstatement Works
13. Any redundant driveway must be removed, and the kerb line and the verge area
reinstated and landscaped to match the existing kerb and/or verge treatments.
Grassed verge areas to be reinstated must be provided with 100 mm topsoil and
turf, and must be maintained by the developer until established. The driveway
layback must be saw-cut and removed to allow for a smooth and neat finish with
the adjoining kerb. A Development Permit for Operational shall be required.
14. Prior to the endorsement of the Plan of Survey by Council, any trees within the
road grassed verge that are damaged or removed due to the development works
must be replaced with similar tress or as agreed to by Council.
15. Any badly damaged kerb and/or channel along the frontage of the site must be
repaired to the reasonable satisfaction of Council’s representative.
Electricity and Telecommunication Services
16. Prior to the endorsement of the Plan of Survey by Council a written confirmation
must be provided to Council from the relevant services providers to confirm that
the proposed lots are provided with their own separate connections to the
electricity and telecommunication services and in compliance with the relevant
legislation and guidelines at the time of construction, the development must be
provided with all necessary conduits, pits and pipes to accommodate the future
connection of optic fibre technology telecommunications.
Bonds
17. The applicant is advised that the development works for this permit require
payment of a compliance bond of $5,000 and an on-maintenance bond in
accordance with Council’s policies. The payment of the compliance/performance
bond will be required prior the prestart meeting for the Operation Works.
5. REFERRAL AGENCIES
Nil.
Page 3 of 7
Document Set ID: 20006723
Version: 1, Version Date: 07/01/2016 Print Date: 7 January 2016, 2:28 PM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Subdivision Decision Notice.pdfRelated documentApplication case desk ↗
Subdivision Decision Notice.pdfRelated documentApplication case desk ↗
About this file
- File size
- 582 KB (small file)
- File type
No other editions are linked here.