Subdivision Decision Notice · OPW16/0051

Attached to the e-mail OPW16/0051 - Operational Works Application (REC15/0023).

of 8

Text shows just the words. Original shows the document exactly as it was published.

                                                                                                     REC15/0023


                      8.      All easements must be created and granted at no cost to the Grantee.
                      9.      All works must be kept clear of any existing or proposed easements on the subject
                              land, unless agreed otherwise in writing by the Grantee.
                              Water and Sewer Connections
                      10.     An underground connection to reticulated water and sewerage must be provided to
                              each lot in accordance with the standards and requirements of Northern SEQ
                              Distributor–Retailer Authority (Unitywater).
                      11.     Prior to the endorsement of the Plan of Survey by Council a written confirmation
                              from Unitywater must be provided to Council to confirm that the proposed lots are
                              provided with their own separate connection to the sewer system and in
                              compliance with the requirements of Unitywater.
                      12.     A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
                              (Unitywater) must be submitted to Council that certifies an underground connection
                              to reticulated water and sewerage has been provided to each lot.
                              Frontage Reinstatement Works
                      13.     Any redundant driveway must be removed, and the kerb line and the verge area
                              reinstated and landscaped to match the existing kerb and/or verge treatments.
                              Grassed verge areas to be reinstated must be provided with 100 mm topsoil and
                              turf, and must be maintained by the developer until established. The driveway
                              layback must be saw-cut and removed to allow for a smooth and neat finish with
                              the adjoining kerb. A Development Permit for Operational shall be required.
                      14.     Prior to the endorsement of the Plan of Survey by Council, any trees within the
                              road grassed verge that are damaged or removed due to the development works
                              must be replaced with similar tress or as agreed to by Council.
                      15.     Any badly damaged kerb and/or channel along the frontage of the site must be
                              repaired to the reasonable satisfaction of Council’s representative.

                              Electricity and Telecommunication Services
                      16.     Prior to the endorsement of the Plan of Survey by Council a written confirmation
                              must be provided to Council from the relevant services providers to confirm that
                              the proposed lots are provided with their own separate connections to the
                              electricity and telecommunication services and in compliance with the relevant
                              legislation and guidelines at the time of construction, the development must be
                              provided with all necessary conduits, pits and pipes to accommodate the future
                              connection of optic fibre technology telecommunications.

                              Bonds
                      17.     The applicant is advised that the development works for this permit require
                              payment of a compliance bond of $5,000 and an on-maintenance bond in
                              accordance with Council’s policies. The payment of the compliance/performance
                              bond will be required prior the prestart meeting for the Operation Works.

                      5.     REFERRAL AGENCIES

                      Nil.




                                                                                                          Page 3 of 7


Document Set ID: 20006723
Version: 1, Version Date: 07/01/2016                                                              Print Date: 7 January 2016, 2:28 PM

Used in these records

About this file

File size
582 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Subdivision Decision Notice.pdf · 582 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.