Approved Plans
3. Development authorised by this approval must be undertaken generally in accordance with
the Approved Plans listed in the table below.
Plan No. Rev. Plan/Document Name Date
WD.2.01 I Site Plan, prepared by Garland Design 27/02/2025
Annotated by Council
WD.2.02 I Demolition Plan, prepared by Garland 27/02/2025
Design
WD.2.03A I Ground Floor Plan, prepared by Garland 27/02/2025
Design
WD.2.04 I Level 1 Floor Plan, prepared by Garland 27/02/2025
Design
WD.2.07 I Roof Plan, prepared by Garland Design 27/02/2025
WD.3.01 I Elevations, prepared by Garland Design 27/02/2025
WD.3.02 I Elevations, prepared by Garland Design 27/02/2025
Noosa Waters Setback
4. The area within 4.5 metres of the centre line of the top of the concrete revetment wall must
be developed in accordance with the following:
(a) A minimum of 25% of the area must be planted with shrubs and small trees with a
mature height of 3m or less.
(b) A maximum of 25% of the area may be impervious, with the balance area soft
landscaping (i.e. grass, ground covers, shrubs and small trees).
(c) The ground surface within 1 metre of the revetment wall must be grass or ground cover
and must not include shrubs or hard pavement.
(d) Any side boundary fencing must taper down to a maximum height of 1.2 metres at the
revetment wall and have a height not exceeding 1.5 metres at a distance of 2.25 metres
from the revetment wall.
(e) Any retaining structures, planter boxes or the like must be finished with natural
materials such as timber or rock rather than manufactured materials.
5. No shore side anchor points are permitted within 4.5m of the revetment wall.
Bonds
6. A site compliance bond of $5,000 is to be submitted to Council prior to the commencement
of works. The commencement of works can only commence once Council's Construction
Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with
these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
7. Bonds must:
a. Meet the requirements of council’s relevant Planning Scheme Policy for performance
and uncompleted works;
b. Be lodged with Council and accompanied by the Bond Administration Fee/s; and
Page 2 of 7
Document Set ID: 23690366
Version: 4, Version Date: 16/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original