2016-09-06 S&O Committee - Attachment 1 to Item 2 - Asset Management Roadmap
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
The first two procedures will need to be developed in collaboration with Council staff to ensure the
outcomes of these procedures serve both financial and operational objectives.
Council Lead(s)
Asset Planning Co-ordinator, Infrastructure Planning & Design Manager, Financial Services Manager,
Co-ordinator Engineering, Project Officer Planning & Infrastructure
Interfaces with existing Council Initiatives:
Project Delivery Toolkit Initiative
As Constructed Process Mapping
Dependencies with other Road-Map Initiatives:
Asset Management Process Mapping and Data Analysis: The process steps and/or workflows
developed under this initiative will be incorporated into the end-to-end process mapping
under this initiative.
ISO 55001 Reference:
8.1 Operational Planning and Control: The organisation shall plan, implement and
control the processes needed to meet requirements...
Potential Benefits:
The benefits of including asset management considerations within the current Project Delivery
Toolkit initiative are that capture of asset data at hand-over is streamlined and Council is not left
with an administrative or operational liability post-handover.
The development of procedures for the capitalisation of assets that meet both financial and
operational requirements of the business will not only standardise the capitalisation process, but
improve operational efficiency. Providing a “single point of truth” of capitalised asset data eliminates
data ambiguities and reduces data administration overheads. A common source of this information
for both financial and operational purposes provides the opportunity for Council staff to provide
inputs on asset modifications (i.e. maintenance, renewal or upgrade) that would not otherwise
accurately be reflected in Council’s financial systems.
Scope of Work:
Task Task Description Resources Approx. Delivery Deliverable /
No. Duration Timeframe Outcome
1 Ensure capture of asset management Council 2 months Short PD Toolkit
requirements in existing PD Toolkit developed meets
initiative. asset
management
requirements.
2 Document procedures for realisation and Council 4 months Short Consistent
capitalisation of handed-over assets approach to asset
capitalisation
that meets
financial and
operational
requirements.
34 ASSET MANAGEMENT ROAD-MAP REPORT
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.