2016-09-06 S&O Committee - Attachment 1 to Item 2 - Asset Management Roadmap

of 60

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Task   Task Description        Sub-   Sub-task Description                     Linked        Resources   Council Leads      Approx.    Delivery   Deliverable / Outcome
No.                            Task                                            RoadMap                                      Duration   Timing
                               No.                                             Tasks
24     Asset Information       1      Review existing asset hierarchy                         Council     Asset Planning    3 months   Short      Revised asset hierarchy
       Improvement: Asset                                                                                  Coordinator,
       Information                                                                                           Director
       Improvement: Asset                                                                                   Corporate
       Management Process                                                                                    Services
       Mapping and Data
       Analysis                2      Develop or revise data standards         24.1, 24.2     Council     Asset Planning    2 months   Short      Agreed asset information data
                                                                                                           Coordinator,                           Standards
                                                                                                              Asset
                                                                                                          Management
                                                                                                             Working
                                                                                                            Group(s),
                               3      Develop information improvement          23.2, 24.1,    Council     Asset Planning    3 months   Short      Comprehensive and high-quality
                                      program                                  24.2, 24.3                  Coordinator,                           asset data to support the Asset
                                                                                                             Director                             Management System
                                                                                                            Corporate
                                                                                                          Services, Asset
                                                                                                           Management
                                                                                                             Working
                                                                                                          Group(s), Asset
                                                                                                           Management
                                                                                                          Steering Team
25     Asset Management        1      Determine asset management                              Council     Asset Planning    1 month    Short /    AMS document control needs
       Document Control               document control requirements                                        Coordinator,                Medium     understood.
                                                                                                              Asset
                                                                                                           Management
                                                                                                          Steering Team,
                               2      Incorporate procedures developed            25.1        Council     Asset Planning    1 month    Medium     Revised document control
                                      into existing corporate governance /                                 Coordinator,                           procedures aligned to AMS
                                      document control procedures                                             Asset                               requirements
                                                                                                           Management
                                                                                                          Steering Team,
                                                                                                              Asset
                                                                                                           Management
                                                                                                         Working Group(s)
26     Asset Management Plan   1      Document the workflow from Asset            14.2        Council     Asset Planning    2 months   Medium     Documented AMP to Budget
       to Budget Workflow             Management Plan to approved                                          Coordinator,                           workflow.
                                      Budget.                                                                Director
                                                                                                            Corporate
                                                                                                          Services, Asset
                                                                                                           Management
                                                                                                          Steering Team
27     Management of Change    1      Identify possible changes and their         19.3       Council      Asset Planning    3 months   Medium     Comprehensive list of possible
                                      influencing factors, by asset class.                                 Coordinator,                           changes, by asset class.
                                                                                                              Asset
                                                                                                           Management
                                                                                                          Steering Team,
                                                                                                              Asset
                                                                                                           Management
                                                                                                         Working Group(s)
                               2      Develop measures to mitigate the risks      13.1       Council      Asset Planning    2 months   Medium     Identified measures to mitigate
                                      of changes identified.                                               Coordinator,                           risks of change.
                                                                                                             Human
                                                                                                            Resources
                                                                                                          Manager, Asset
                                                                                                           Management
                                                                                                          Steering Team
28     Control of Outsourced   1      Develop an Asset Management                 3.2         Council    Noosa Leadership   2 months   Medium     AM Strategic Sourcing Strategy
       Activities                     Strategic Sourcing Strategy                                             Team,
                                                                                                           Governance
                                                                                                             Advisor,
                                                                                                         Procurement and
                                                                                                          Fleet Manager
29     Quality Management      1      Investigate integration of AMS              10.2        Council     Asset Planning    2 months   Medium     Required amendments to existing
       Plan                           performance management                                               Coordinator,                           Plans or functions.
                                      requirements in existing Council                                     Governance
                                      quality management and audit                                        Advisor, Asset
                                      functions                                                           Management
                                                                                                          Steering Team
                               2      Develop Asset Management System          29.1, 24.3,    Council     Asset Planning    2 months   Medium     Asset Management System Quality
                                      Quality Management Plan                     25.2                     Coordinator,                           Management Plan
                                                                                                           Governance
                                                                                                          Advisor, Asset
                                                                                                          Management
                                                                                                          Steering Team
Log in to download the original file

2016-09-06 S&O Committee - Attachment 1 to Item 2 - Asset Management Roadmap(PDF, 2MB).pdf · 2.1 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗