SEDIMENT CONTROL
on your building site
A combination of sediment control measures is often needed on an individual site. Sediment controls
usually consist of a sediment barrier installed along the lower side of the soil disturbance, and a stabilised
entry/exit pad (rumble pad).
Where possible, manage the entry/exit point of the site so that sediment is not tracked off the site.
Where practical, restrict the entry/exit point to one stabilised location, not necessarily at the location
of the permanent driveway (refer Figure 4.1).
Stabilised Entry/Exit Pad - Building Sites Building Site
Entry/exit pod extends .•° °:: "'"'
I
in:;arp,rate d mto the pad
from kerb to budding slob
when .• ^t . rxrt pod .4
where practical I'a
yM,,, to a ' ):•.. CPO of the.
!r !xjrh )Om (,
nrn /. SC, 1 ,
2OOmn, (m n); ) Runoff
.. diversion
r
I'f ;4r, Iran. bank
Width 20m (mm)
5rdimentfence
Runoff from pa d A
directed to
Footpath
sediment trop N A ,' " , ° n ^ , pedestrian
Geote.otile filter cloth 40-7f)mm .AOke safe tr fflc
(as directed or when crushed rock for pedestrior:
working on clayey soils) nwff c Figure 4 1 Figure 4.2 nr/ Road f
7
Stabilised entry/exit detail Entry/exit bond detail
A rumble pad may be used to stabilise the entry/exit point. These pads should be at least 2 metres wide
consisting of minimum 40 mm crushed rock placed 150-200 mm thick over geotextile filter cloth. Where
possible, the rumble pad should extend from the kerb to the building slab or a minimum length of 10m.
Where practical, the rumble pad should extend from the kerb to the building slab. Where necessary, 20 mm
aggregate or blue metal should be placed
over the crushed rock between the
property boundary and the road kerb to
make the entry/exit point (rumble pad)
safe for pedestrian traffic.
Where the entry/exit point (rumble pad)
slopes toward the road, install a minimum
200mm high flow diversion bund across
the pad to deflect stormwater run-off into
the main sediment control zone or into
a separate U-shaped sediment fence.
(refer Fiqure 4.2).
Stabilised entry/exit point (rumble pad)
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.