SECTION 4 - INVESTIGATION RESULTS
4.1 Results
The subsurface conditions encountered in the bores are given on Bore Report Sheets included in Appendix A,
using classification and descriptive terms defined in the accompanying notes. Laboratory test report sheets are
included in Appendix B.
4.2 Subsurface Conditions
For a description of the stratigraphy encountered in the bores, the Bore Report sheets should be consulted.
However, in broad summary, the subsurface conditions encountered in the bores generally comprised a surface
layer of either fill material (in Bores 1 to 4) that varied up to a maximum depth of 0.8m, or silty sand (in Bores 5
and 6) to a maximum depth of 0.4m. In Bores 1 and 2 only, the fill was underlain by natural, dark grey-brown
si clays that were underlain in turn by silty sands that were indurated below 2m depth. In Bores 3 to 6, the
surface fill or silty sand layer was underlain by san s.
4.3 Groundwater
Free groundwater was encountered during the drilling of four of the six bores at the depths/RLs given in Table 1.
It should be noted that groundwater levels can vary seasonally and with prevailing weather conditions.
r
Table 1: Observed Groundwater Depths/Reduced Levels During Drilling
Groundwater Observations
B ore
Depth Reduced Level
1 0.8 C RL 2.3m
2 1 0.8 RL 2.3m
3 1.5 RL6.Om
4 Not encounte re
5 1.6 RL5..9m
6 Not encountered
4.4 Laboratory Testing
4.4.1 Screening Tests
Screening tests were undertaken on all soil samples collected from all bores. The screening tests comprised
two small sub-samples of soil; one mixed with approximately 20 mL of distilled water, and the other mixed with
approximately 20 mL of hydrogen peroxide, buffered to a pH of 5.0 with sodium hydroxide.
Slurry pH was measured with a calibrated pH meter. The pH of the distilled water/soil slurry (pHF) was
measured approximately one hour after mixing, whilst the pH of the hydrogen peroxidelsoil slurry (pHrox) was
measured approximately one to two hours after mixing.
Residential Development Page 5 of 10
215-219 David Low Way. Peregian Beach
Project No. 07160 16 June 2007
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Development Application Part 2 - Environmental & Stormwater Management PlansRelated documentApplication case desk ↗
About this file
- File size
- 49.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.