AMENDED ADVICE - Energex - Approved subject to conditions Taylor
2
Drainage Work, Stormwater, Earthworks &
Landscaping, Reconfiguring a Lot - Community Title
Subdivision (1 Lot into 54 Lots)
Referral Trigger ☒ Schedule 10, Part 9, Division 2, Table 1, Item 1
(10.9.2.1.1) – Reconfiguring a lot subject to an easement
for the benefit of a distribution entity under the Electricity
Act for a supply network; or part of the lot is within 100m
of a substation site
☒ Schedule 10, Part 9, Division 2, Table 2, Item 1
(10.9.2.2.1) – Material Change of use of premises within
100m of a substation site or subject to an easement for
the benefit of a distribution entity under the Electricity Act
and the easement is for a supply network
☒ Schedule 10, Part 9, Division 2, Table 3, Item 1
(10.9.2.3.1) - Operational Work on premises subject to
an easement for the benefit of a distribution entity under
the Electricity Act for a supply network; or part of the lot
is within 10m of a substation site
Impacted Electrical Easement AA on SP316697
Infrastructure
Energex provides the following response to the application in accordance with Section
56(1) of the Planning Act 2016:
Component of Advice Agency direction
Development
MCU/ ROL/ OPW ☒ S56(1)(b)(i) – approval subject to stated development
conditions
In accordance with Section 56(1) should the Assessment Manager decide to approve
the proposed Development Application, as an Advice Agency, Energex requires that
the assessment manager impose the below conditions. These conditions have been
imposed in response to the matters prescribed under Section 55 (2) of the Planning Act
2016.
Table 1
Plans forming part of this Approval
Title Plan No. Issue Date
SITE / FLOOR PLAN LEVEL 1- 2025-68 I 29.05.26
OPT 05
Overall Development Layout Plan C010 B 08.05.26
Landscape Plan 2025-68 I 29.05.26
Sheet 30
Table 2
Condition Timing Purpose/Reason
1 Carry out the approved development At all times To ensure the
generally in accordance with the approved development is
carried out generally
Have you seen our fact sheets?
See the ‘considerations when developing around electricity infrastructure’ section of our website
www.energex.com.au/referralagency