Haulage activity and amenity No solution provided RO7. Haul routes from trucks used to transport spoil
O7 and material to and from the site will only use
Haulage of material to and from a site major roads as required. Alternatively if there is
ensures— no major road route to the site, haul trucks will
a) minimal disturbance to neighbouring properties use minor roads with the shortest, most direct
and properties along the haulage route; and route that will have the least amount of
b) Council’s road infrastructure including pavements is environmental impact. This will be clearly
not adversely affected. documented in the Construction Management
Plan.
O8 S8.1 All earthworks, including cut and fill batters, RO8.1 All earthworks will be contained within the
Extent of earthworks retaining walls etc are contained within the subject site. Any minor earthworks
subject site. undertaken external to the site will only be
Earthworks are contained within the subject property. undertaken after all approvals and/or consent
is obtained from Council and neighbouring
property owners.
Sloping sites S9.1 Cut or fill is less than 2m in depth relative to RO9 Acknowledged.
O9 the natural ground surface.
On sloping sites, excavation or filling are designed to
maximise the use of natural slope and minimise the
need for cut and fill.
Environmental protection No solution provided. RO10 An Erosion and Sediment Control Plan will be
O10 prepared by Morgan Consulting Engineers
Earthworks minimise any adverse impact upon and will be kept on site for the duration of the
groundwater, watercourses, drainage lines, wetlands, construction phase for the management of
and native vegetation. sediment laden stormwater runoff.
Dams S11.1 W here the site is in the Rural RO11.1 The construction of a dam is not planned for
O11 Zone— this development.
Dam location and construction does not impact upon a) the land has a slope of less than 25%
neighbouring properties in terms of— (1:4); and
a) hydrology; b) the earthworks including cut and fill batters
b) alteration of existing overland flowpaths and and retaining walls are setback a minimum of
patterns; 50m from the property boundary; and
c) landslide or failure of dam wall; and c) the size of the lot is greater than 5
d) effluent disposal areas. Hectares;
AND
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.