Example Job Safety Analysis (JSA)/Work Method Statement (WMS)
The following JSA/WMS is a guide only. It is the responsibility of the cleaning contractor or asset owner to develop their own JSA/WMS in
line with their own WHS requirements and constraints. It also assumes that there will be no entry into the unit during maintenance.
Project/ Address: Date:
Job: Clean out of HumeCeptor® unit Operator:
Risk Level: 1 - Extreme 2 - High 3 - Medium 4 – Low 5 - Negligible
Consequence: Likely to cause very Clear potential for Similar to risk of driving Little likelihood of any Virtually Harmless
serious harm serious harm a car harm
Response: STOP THE JOB STOP and Reassess to Control and ensure Monitor to ensure risk Continue work
find better way controls work remains low
INITIAL PERSON END
PROCEDURE POSSIBLE HAZARDS CONTROLS
RISK RESPONSIBLE RISK
1. Preliminaries: Nil - Refer to relevant manuals Operator -
• Confirm unit locations and types
• Familiarise with the technical manual
2. Plan the Job: • Climbing in/out/around of truck 3 • Refer to safety plan on moving around Operator 4
• Room to access and work on the unit vehicles
without impacting other property or • All units have a high risk of 4 • Wear PPE and never reach into or lift 5
vehicles containing syringes accumulated matter with hands. If a needle
• Consider water flows and if excessive stick injury occurs, wash the affected area
note and move onto next job with soap and water and report the incident
• Condition and status of unit to the branch and seek medical attention
• Identify water fill point ASAP.
• Identify waste dump point
3.Establish Job Site: • Traffic 2 • Devise a relevant Traffic Management WMS Operator 5
• Over 60 km/hr will require traffic • Pedestrians • Ensure barriers and signs redirect
management • Overhead power lines pedestrians
• Within 6.4m of overhead power lines • Ensure spotter is present
will require spotter
4. Assemble Cleaning Equipment • Infection 3 • Personal hygiene (wash hands prior to Operator 5
• Position vacuum hose to remove debris • Sharp edges smoking/eating)
from the unit • Manual handling • Wear gloves & remove sharp edges/burrs on
• Falling equipment equipment
• High pressure water • Follow a manual handling WMS
• Store equipment securely on vehicle
• Inspect vacuum hose fittings firmly secured
• Inspect hose daily 7 ensure it has been
tested (6 monthly)
• Never cap jetting hose
• Inspect jetting hose for damage
• Never adjust pump pressures or regulators
• Maximum reducer on 1” hose is ¾”
• No reducers on ½” hose
• Fittings to be firmly secured using a spanner
5. Open the GPT Cover • Manual Handling 3 • Refer to a SWP for manual handling Operator 5
• Remove lid using the manhole lifting • Open Manholes • Refer to a SWP for manhole lifting
procedure
• If lid is mass concrete and exceeds safe
lifting limits, use mechanical lifting
device
6. Start Cleaning • Manual handling 3 • Follow a SMP for manual handling Operator 5
• Check for oil using a dipstick, tube or • Eye injury from flying debris • Wear eye protection
sampling device • Noise • Wear hearing protection
• Remove and store any free oil separately • People inside exclusion zone • Stop operation until area clear. Only
using a small portable pump • Confined Space Entry (If essential personnel within exclusion zone
• If there is any requirement to enter the required) • Ensuring minimum slack in hose to prevent
pit for any reason, confined Space Entry whipping
Procedure is to be followed • Refer to confined space manuals and SWPs
• Decant the relatively clean water from
the central zone to either sewer or
upstream (approvals from authorities
required to discharge to sewer)
(OPTIONAL)
• Vacuum all material out of the sump
until empty clear
• Clean the interior of the pit using water
jet
7. Finish Cleaning • Manual handling 3 • Follow a SMP for manual handling Operator 5
• Replace lid ensuring it is fimly &
securely in place
• Ensure all waste is vacuumed and site is
clean prior to packing up
• Complete the CWS recording all details
and any problems
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.