SUPERSEDED - 06/1101 Negotiated Decision Notice [As Published] · 142006.1101

of 8

Text shows just the words. Original shows the document exactly as it was published.

NOOSA COUNCIL IDAS Development Application Decision Notice                                                  5 of 8


      In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
      Applicant, such cost being paid prior to the commencement of the use.

30.   The development of the site shall be carried out in such a manner as to prevent dust and/or sand
      nuisance to residents and/or tenants in the vicinity of the development.

31.   Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
      pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
      hours are approved by the Manager-Land Development or his nominee.

32.   All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
      Traffic Control Devices and Traffic Infrastructure (Roads) Act.

33.   Safe pedestrian access on Weyba Street shall be maintained at all times. Should footpath / road closures
      be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410 512 505)
      must be notified prior to the proposed closure.

34.   Sediment and erosion control measures must be in place prior to works commencing. If such measures
      are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
      sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
      natural waterways. Although the sediment and erosion control measures have been approved on drawing
      No 16078-OW1B dated 4 July 2007 by SCG Consulting Engineers, Council’s Manager – Land
      Development may request further controls to be installed should approved measures be inefficient.

35.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
      on construction works during the maintenance period, which is a minimum period of 12 months duration.
      Such bond must be lodged by, and shall only be accepted from the Developer for the works. Should the
      applicant choose to make a contribution towards Council’s pathways in lieu of construction the bond shall
      not apply.

36.   The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
      completed.

37.   These works are also to be in compliance with the relevant conditions of Development Permit No.
      2006/138.

38.   Notwithstanding that Council has checked the plans with due care, where it is found during construction
      that variations from Council's standards exist, then Council standards shall apply




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@4007a506\@[email protected]

Used in these records

About this file

File size
40 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED - 06_1101 Negotiated Decision Notice [As Published].pdf · 40 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.