                                                                                 Officer:            Jada Lyons
                                                                                 Direct Telephone:   07 53296527
                                                                                 Our Reference:      51987.2949.6
                                                                                 Your Reference:     n/a

               8 May 2023


               GM Collinson
               C/- Brennan Planning Pty Ltd
               44 Maple St
               COOROY QLD 4563
               [email protected]



               Dear Sir/Madam,
                                            Decision Notice – Minor Change
                                                           Planning Act 2016

               I refer to your application received on 24 March 2023, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              51987.2949.6

                   Street address:              Number 1 19/1 Morwong Dr Noosa Heads Qld 4567

                   Real property description:   BUP 9411, Lot 19 BUP 9411 BUP 9411

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 15 September 1987
               •       Town Planning Consent TPC 1920 for 24 Multiple Dwelling Units.
               In relation to the request to make a minor change to the existing approval, Council on 3 May 2023,
               decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Amend condition 56.
               C.      Include additional condition: 59.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.




               ABN 97.969.214.121                                                              PO Box 141
               noosa.qld.gov.au                                                         Tewantin QLD 4565
               [email protected]                                                         07 5329 6500
                                                                                                       Page 1 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023
Full text of the other 9 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               1.     Compliance with all relevant provisions of the Town Planning Scheme, Chapter XLIV (Town
                      Planning) and other Council Policies
               2.     The site shall be developed substantially in accordance with the plans forming part of and
                      approved with this application.
               3.     In accordance with Section 33 (16D) of the Local Government Act 1936, Council's approval
                      is valid for a period of two (2) years at the expiration of which period the Council may take
                      action to revoke its approval, if in the opinion of the Council substantial progress has not
                      been made in erecting the building or other structure the subject of the Consent Permit; or
                      the land, subject to the Consent Permit, is not being used substantially in accordance with
                      the purposes for which consent was granted
               4.     To ensure compliance with any and all conditions of this approval Council will require that
                      you enter into a Bank Guarantee of $100,000 to secure performance. The guarantee shall
                      be lodged with Council prior to the issue of a Building Permit. Any costs incidental thereto
                      will be borne by the Developer.
               5.     The conditions of this approval are to be completed prior to the occupancy of the building
                      and if this is not done, Council reserves the right to call on the bank guarantee lodged to
                      carry out the works involved.
               6.     Contributions shall be Water supply and Sewerage within fourteen (14) days paid in
                      accordance with Council's Policy on Headworks. Such contributions shall be paid of
                      building approval. Contributions shall be payable at the following rate: -
                      Water Supply - $40,452
                      Sewerage         $16,382
                      (Plus P.I. index rises from April, 1987).
               7.     Payment of any outstanding rates owing on the property.
               8.     This consent approval does not imply Building Approval. Working drawings shall be
                      submitted in compliance with the Building Act 1975 as amended and shall be
                      substantially in accordance with the plans the subject of this consent. (Substantial
                      variations will require separate Council approval).
               9.     The approval herein is for Town Planning Consent only and does not imply that Council
                      approval will be granted to an application under the Building Units and Group Titles Act.
               10.    Permanent covered car parking is to be provided on site for 36 vehicles. Of these spaces at
                      least 25 must be covered and at least 6 must be available for use by visitors to the premises.
               11.    All internal roadworks (including parking areas) and access from the existing frontage
                      road to connect to the internal roadworks shall be provide with a sealed pavement, which
                      shall be designed, drained, constructed and maintained in accordance with the
                      standards and requirements of the Shire Engineer.
                      Plans and specifications for the above works shall be submitted to the Shire Engineer
                      for approval prior to the issue of a Building Permit.
               12.    The Developer shall bear the cost of alteration of any public utility or facilities necessitated
                      by the development of the land or associated development external to the site.
               13.    Connection to Council’s existing water supply reticulation at the Developer’s expense to the
                      standards and requirements of Council’s Building Surveyor.
               14.    Connection to Council’s existing sewerage reticulation system at the Developer’s expense
                      to the standards and requirements of Council’s building Surveyor.
               15.    Filling levels and floor levels of all buildings, other structuresand car park area levels
                      shall be established to the requirements of the Shire Engineer. Such levels shall be
                      provided upon application to the Engineering Department.


                                                                                                       Page 2 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 3

               16.    Filling, other development works or the erection of any buildings or other structures shall
                      be carried out so as not to cause any ponding of water on adjoining land or any blockage
                      or interference with natural watercourse or in any other way unduly affect adjoining
                      property.
               17.    No earthworks or filling shall be carried out on site until the issue of a Building Permit.
               18.    An identification survey of the subject site is to be carried out by a Licensed Surveyor and
                      is to be submitted to council at the time of foundation inspection by Council's Building
                      Surveyor or immediately thereafter. Such survey shall set out the boundaries of the site
                      and the position of the buildings on the site.
               19.    The applicant shall cause minimum disturbance to natural flora and shall only remove
                      that vegetation which would impede building operations. Where practicable,
                      revegetation of the site is to be carried out following completion of building activity.
               20.    Landscaping shall be established and maintained in accordance with a landscaping plan
                      approved by Council. Such plan shall be prepared in accordance with the provisions of
                      the Noosa Design Manual.
               21.    No signage is approved as part of this consent. Further application to Council is required
                      for signage prior to erection and regard shall be given to the Noosa Design Manual in
                      preparing such anapplication.
               22.    Deleted.
               23.    Location points for mail delivery shall be to the requirements of Australia Post.
               24.    The swimming pool shall be licensed annually with the Council’s Health Department in
                      accordance with the provisions of Chapter 42 of Councils Bylaws
               25.    Any flat, unit, intended to be let out for a fee or reward shall be licensed annually with
                      Council’s health Department in accordance with the provisions of Chapter 43d of Council’s
                      bylaws prior to such letting.
               26.    Adequate facilities shall be provided in accordance with the provisions of the Refuse
                      Management Regulations 1983 for the storage and collection of refuse to the satisfaction
                      of Council's Health surveyor.
               27.    Provide an imperviously paved area suitably drained t the satisfaction of the Local Authority
                      upon which to stand all refuse containers and a suitable hose cock and hose in the vicinity
                      of such stand or such paved area with a suitable enclosure to enclose the refuse container
                      areas to the satisfaction of the Health Surveyor.
               28.    Canopies and Porches external to the building shall beconstructed with glazed or other
                      clear roofing.
               29.    Rooftop recreation areas shall comply with the design requirementsof the Noosa Design
                      Manual.
               30.    Porches only are permitted to" intrude into the 6 metre setback from Morwong Drive
                      Roadworks
               31.    The developer shall construct roadworks, drainage and footpath improvements across the
                      full Morwong Drive frontage of the development up to and including the intersection with
                      Hastings Street to the requirements of the Shire Engineer. Such works shall involve the
                      construction in Morwong Drive of kerb and channel on the eastern side, a 5.0 m. wide
                      bitumen pavement with a 1.0 m. gravel shoulder to terminate at a 6.5 m. minimum radius cul-
                      de-sac including associated drainage to a suitable discharge point in Hastings Street, and
                      footpath upgrading Works.
                      The design of such works shall be prepared and shall be submitted for Shire Engineer's
                      approval, by a Registered Civil Engineer prior to construction commencing. The Registered
                      Civil Engineer shall certify that the works have been constructed in accordance with the
                      approved plans.


                                                                                                          Page 3 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 4

                      (Note that Council staff may negotiate an alternative to the above roadworks requirements
                      subject to further detailed design).
                      Drainage
               32.    All stormwater runoff, including that from roofed and paved areas shall be piped to discharge
                      into Council's existing system in Hastings Street to the satisfaction of the Shire Engineer.
                      The stormwater design is to include an assessment of the hydraulic adequacy of the existing
                      system downstream from the point of connection and the Developer shall bear the full cost
                      of any upgrading works required to the existing system (or the construction of an alternate
                      system in accordance with Council's master drainage plan if required) to accommodate the
                      additional stormwater.
               33.    Noiselevels emitted from any mechanical device, including inclinators, air conditioners and
                      the like are not to exceed 5 dba above the background noise level.
               34.    The B.U.P. plan shall not be named No. 1 Hastings Street and the development shall not be
                      advertised or marketed as being No. 1 Hastings Street.
               35.    Access, carparking layout and manoeuvring areas are to be designed in accordance with
                      Council’s Policies and to the satisfaction of the Shire Engineer.
               36.    The applicant shall contribute $8,000 to Council towards the upgrading of the Park
                      Road/Morwong Drive/Hastings Street intersection. Such payment shall be made within 14
                      days of the issue of a Building Permit.
               37.    The Developer shall provide for the erection of ‘No Stopping” signs along the Morwong Drive
                      frontage.
               38.    The proposed pathway within the Hastings Street road reserve is to be constructed to the
                      standards and requirements of the Shire Engineer. Prior to commencement of any works
                      associated with the pathway, a detailed design is to be submitted to Council for approval.
                      Particular attention is to be given to minimising damage to the existing vegetation. Any scour
                      prevention measures, including revegetation of disturbed areas, are to be undertaken by the
                      Developer as considered appropriate by the Shire Engineer.
               39.    Prior to the issue of a Building Permit, the applicant's Geotechnical Consultant shall prepare
                      a report and at the applicant's expense, submit it to Council's nominated Geotechnical
                      Consultant for his perusal.
                      Such report shall specifically address the following
                              i.       The effect of the proposed earthworks on the stability of the site and the
                                       adjoining sites,
                              ii.      proposed construction methods,
                              iii.     full extent of excavations and detailed proposed retaining structures to minimise
                                       the risk of land slip.
               Additional conditions – 28 March 2003
                      Land Use
               40.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are numbered 116A, 117, 118, 120,
                      201 A, 202 A, 205 dated 13/1/03 and numbered 119 A dated 12/02/03 prepared by Goodwin
                      & Southwell Architects and as may be amended by these conditions
               41.    The development must be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
                      lighting nuisance or other emissions.
               42.    Existing trees on the site and within road reserves are to be retained, except where required
                      to be removed due to building operations or the conduct of the approved use.



                                                                                                          Page 4 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 5

               43.    The proposed pool deck extension shall not extend further to the Morwong Drive frontage
                      than the existing northern stair landing (approximately 3.8 metres).
               44.    Additional landscaping shall be undertaken at the northern end of Morwong Drive frontage
                      to completely screen the undercroft of the proposed pool deck extension. The landscaping
                      shall comprise species taken from Planning Scheme Policy No. 1 - Landscaping Guidelines
                      densely planted to create a screening effect.
               45.    This Development Permit for a material change of use of premises lapses if:-
                      a.      the use or erection of a building or other structure associated with the use, has not
                              been commenced by 28 March 2007, unless application is made and approved by
                              Council for an extension; or
                      b.      6.2. the use of any premises pursuant to the Development Permit ceases.
                      Land Development
               46.    The development shall be carried out in accordance with Engineering drawings Nos. 119A
                      dated 12th February 2003 and 201A dated 13th January 2003 or otherwise modified herein.
               47.    The car park layout shall comply with AS 2890.1 - 1993.
                      Further Development Permits Required
               48.    Prior to the commencement of development, the following Development Permits must be
                      obtained:-
                      a.      Development Permit for building works;
               Additional conditions - 15 February 2011
               49.    Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table and may
                      be amended by these conditions and annotations on the plans.

                        Plan No.           Iss.     Plan Name – Prepared by                       Date

                        CD 1.01            P4       Existing Floor Plan – Middap Ditchfield       13 April 2010

                        CD 1.02            P3       Existing Section AA – Middap Ditchfield       13 April 2010

                        CD 1.03            P3       Existing Section BB – Middap Ditchfield       13 April 2010

                        CD 1.04            P3       Existing Section CC – Middap Ditchfield       13 April 2010

                        CD 2.01            P4       Proposed Floor Plan – Middap Ditchfield       13 April 2010

                        CD 2.02            P4       Proposed Roof Plan – Middap Ditchfield        13 April 2010

                        CD 3.01            P4       Proposed Section AA – Middap Ditchfield       13 April 2010

                        CD 3.02            P4       Proposed Section BB – Middap Ditchfield       13 April 2010

                        CD 3.03            P4       Proposed Section CC – Middap Ditchfield       13 April 2010

               50.    A small garden shall be retained to the side of the southern walkway. The garden shall have
                      a minimum width of 0.5m and shall be of similar length to that existing.
               51.    The development shall be undertaken and operated in a manner that causes no detrimental
                      effect upon the amenity of the neighbourhood due to the creation of excessive noise, lighting
                      nuisance, or other emissions.




                                                                                                     Page 5 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 6

               Additional conditions – 11 October 2013
               52.    Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans. The approved plans are listed in the following table and may be
                      amended by these conditions and annotations on the plans

                        11 October 2013

                        Plan No.             Iss.     Plan Name – Prepared by                       Date

                        DA1001 A                      Site Plan, prepared by Peter Hull             12 July 2013

                                                      Plans – Floor Plans – Existing, prepared by
                        DA1002 A                                                                  12 July 2013
                                                      Peter Hull

                                                      Plans – Floor Plans – New Level 9 proposed
                        DA1003 B             A        alteration, Existing Level, prepared by Peter 4 Oct 13
                                                      Hull

                                                      Sections – S/01 Section 1, prepared by Peter
                        DA2001 A                                                                   12 July 2013
                                                      Hull

                        DA3001 A                      Elevations, prepared by Peter Hull            12 July 2013

                        DA3002 A                      Elevations – Layout, prepared by Peter Hull   12 July 2013

                                                                                                    Plot
                        DA3003 A                      Elevations – Layout, prepared by Peter Hull
                                                                                                    Date:18/07/13

                      Acoustic Amenity
               53.    Any fixed plant and equipment* that causes either tonal (Leq) sound (e.g. from basement
                      car-park exhaust, air conditioning unit or pool filtration unit), or impulse (Lmax) sound,
                      must be enclosed, shielded and/or positioned to ensure that sound pressure does not
                      exceed the following levels for habitable rooms within dwellings:
                      53.1.       40 dB(A) Leq for living and work areas
                      53.2.       35 dB(A) Leq for sleeping areas
                      53.3.       45 dB(A) Lmax for all areas
                      Note: Measurement o f sound pressure levels ( adjusted for tonality and impulse)
                      must be in accordance with Australian Standard AS1055.1 “Acoustics – Description
                      and measurement of environmental noise – General procedures”.
                      *(Refer to Advisory Note)
               54.    Certification must be submitted to Council from a qualified person* which certifies that
                      operational noise from any fixed plant and equipment complies with the requirements of this
                      Decision Notice.
                      *(Refer to Advisory Note)
                      Built Form
               55.    The additions must have an external finish consistent with the existing development.
               Additional conditions – 18 May 2020
               56.    Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans. The approved plans are listed in the following table and may be
                      amended by these conditions and annotations on the plans:



                                                                                                      Page 6 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 7

                        Plan No.         Rev Plan Name                                               Date

                                               Minor   Change      Application  to   Existing
                        D-02426-04-A     -     Development Approval TPC1920, prepared by 21/12/2022
                                               Martoo Consulting (as annotated by Council)

                        D-02426-05-A           Minor   Change      Application  to   Existing
                                         -     Development Approval TPC1920, prepared by 21/12/2022
                                               Martoo Consulting (as annotated by Council)

                        D-02426-06-A           Minor   Change      Application  to   Existing
                                         -     Development Approval TPC1920, prepared by 21/12/2022
                                               Martoo Consulting (as annotated by Council)

                        CD.3             -     Proposed Floor Plan, prepared by Design to Detail 12/08/2022

                        CD.5             -     Proposed Section, prepared by Design to Detail        12/08/2022

                      Caretaker’s car park
               57.    Deleted.
               Additional conditions – 19 April 2023
               58.    All building works associated with the minor change for Lot 2 on BUP9411 & Common
                      Property in CTS5904 is to be completed within two years of the issuing of minor change
                      approval 51987.2949.5.
               Additional conditions – 3 May 2023
               59.    The terrace of Unit 19 is to remain unenclosed and is not to be further reduced in size other
                      than that approved by 51987.2949.6.
               5.     REASONS FOR APPROVAL

               The following reasons are given in support of Council’s decision to vary the Scheme
               requirements:-
               1.     The site is constrained by slope such that a larger building is necessary to enable a viable
                      construction.
               2.     The site was previously zoned Residential 1 B 1 which permitted larger developments up to
                      three storeys. The subject proposal is three storeys in part only.
               3.     A previous approval provided for 44 X 2 bedroom units.
               The following are grounds to support the proposal approved 18 May 2020 despite the conflict with
               The Noosa Plan:
               1.     The proposal does not adversely impact on the amenity of the residents of the development
                      or the surrounding area
               2.     The proposal does not result in a significant increase in the scale, bulk or density of the
                      development and will not be visible from outside the site.
               3.     The proposal is consistent with the existing design elements of the building
               4.     Sufficient additional car parking has been provided
               6.     REFERRAL AGENCIES

               Not applicable.




                                                                                                     Page 7 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 8

               7.       ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                        Qualified Person
               1.       For the purpose of certifying acoustic treatments for the development, a qualified person is
                        considered to be either:
                        b.    Registered Professional Engineer of Queensland;
                        c.    an environmental consultant with a minimum of 3 years current experience in the field
                              of acoustics.
                        Noise
               2.       The applicant is advised to ensure that during the detailed building design and construction
                        phase, including the design, selection and installation of fixed plant and equipment, A/C units
                        and refrigeration plant, mechanical exhausts, acoustic enclosures/plant rooms and the like,
                        that the ongoing advice and design input of a qualified acoustic consultant is sought and
                        implemented to ensure that the operation of such plant and equipment complies with statutory
                        and planning noise limits. Mechanical plant and equipment must be provided with appropriate
                        acoustic enclosures/screening and located away from adjacent noise sensitive premises.
               Infrastructure Charges
               3.       All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                        made pursuant to the planning legislation and regulations current at the time of issue.
               Infrastructure Charges
               4.       All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                        made pursuant to the planning legislation and regulations current at the time of issue. For
                        further information, please refer to https://www.noosa.qld.gov.au/planning-
                        development/development-tools-guidelines/infrastructure-charges
               8.       PROPERTY NOTES

               Not applicable.
               9.       VARIATION APPROVAL DETAILS

               Not applicable.
               10.      FURTHER DEVELOPMENT PERMITS REQUIRED

               Development Approved 28 March 2003
                    •   Development Permit for Building Works
               Development Approved 18 May 2020

                Type of Development Permit Required                Subject of the required Development Permit

                Development Permit for Building Works              All building works

               11.      SUBMISSIONS

               Not applicable.
               12.      RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.


                                                                                                         Page 8 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 9

               13.      OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.




               Yours faithfully,




               Jada Lyons
               Assistant Development Planner



               Enc:     Appeal Rights
                        Approved Plans/Documents


               cc.      Unitywater




               DECISION NOTICE HISTORY
               •     Original Decision Notice –21 July 1987 – 51987.2949 (TPC 1920)
               •     Negotiated Decision Notice – TPC 1920 – 15 September 1987, with an amendment to conditions 10 and delete conditions 22.

               •     Decision Notice - Change - TPC1920 28 March 2003, with additional conditions 40, 42, 43, 44, 45, 46, 47 & 48.

               •     Decision Notice – Change – 51987.2949.2 – 15 February 2011, include additional conditions 49, 50 & 51.

               •     Decision Notice – Change – 51987.2949.3 – 11 October 2013, include additional conditions 52, 53, 54 & 55.

               •     Decision Notice – Minor Change – 51987.2949.4 – 18 May 2020, include additional conditions 56 & 57.

               •     Decision Notice – Minor Change – 51987.2949.5 – 19 April 2023, with an amendment to description of the permit, amendment to
                     condition 56, include additional conditions 58 and delete conditions 57.

               •     Decision Notice – Minor Change – 51987.2949.6 – 3 May 2023, with an amendment to description of the permit, amendment to
                     condition 56, include additional conditions 59.




                                                                                                                                     Page 9 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Page 10

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 10 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Used in these records

About this file

File size
210 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51987 2949 6.pdf · 210 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.