               4.     ASSESSMENT MANAGER CONDITIONS

               1.     Compliance with all relevant provisions of the Town Planning Scheme, Chapter XLIV (Town
                      Planning) and other Council Policies
               2.     The site shall be developed substantially in accordance with the plans forming part of and
                      approved with this application.
               3.     In accordance with Section 33 (16D) of the Local Government Act 1936, Council's approval
                      is valid for a period of two (2) years at the expiration of which period the Council may take
                      action to revoke its approval, if in the opinion of the Council substantial progress has not
                      been made in erecting the building or other structure the subject of the Consent Permit; or
                      the land, subject to the Consent Permit, is not being used substantially in accordance with
                      the purposes for which consent was granted
               4.     To ensure compliance with any and all conditions of this approval Council will require that
                      you enter into a Bank Guarantee of $100,000 to secure performance. The guarantee shall
                      be lodged with Council prior to the issue of a Building Permit. Any costs incidental thereto
                      will be borne by the Developer.
               5.     The conditions of this approval are to be completed prior to the occupancy of the building
                      and if this is not done, Council reserves the right to call on the bank guarantee lodged to
                      carry out the works involved.
               6.     Contributions shall be Water supply and Sewerage within fourteen (14) days paid in
                      accordance with Council's Policy on Headworks. Such contributions shall be paid of
                      building approval. Contributions shall be payable at the following rate: -
                      Water Supply - $40,452
                      Sewerage         $16,382
                      (Plus P.I. index rises from April, 1987).
               7.     Payment of any outstanding rates owing on the property.
               8.     This consent approval does not imply Building Approval. Working drawings shall be
                      submitted in compliance with the Building Act 1975 as amended and shall be
                      substantially in accordance with the plans the subject of this consent. (Substantial
                      variations will require separate Council approval).
               9.     The approval herein is for Town Planning Consent only and does not imply that Council
                      approval will be granted to an application under the Building Units and Group Titles Act.
               10.    Permanent covered car parking is to be provided on site for 36 vehicles. Of these spaces at
                      least 25 must be covered and at least 6 must be available for use by visitors to the premises.
               11.    All internal roadworks (including parking areas) and access from the existing frontage
                      road to connect to the internal roadworks shall be provide with a sealed pavement, which
                      shall be designed, drained, constructed and maintained in accordance with the
                      standards and requirements of the Shire Engineer.
                      Plans and specifications for the above works shall be submitted to the Shire Engineer
                      for approval prior to the issue of a Building Permit.
               12.    The Developer shall bear the cost of alteration of any public utility or facilities necessitated
                      by the development of the land or associated development external to the site.
               13.    Connection to Council’s existing water supply reticulation at the Developer’s expense to the
                      standards and requirements of Council’s Building Surveyor.
               14.    Connection to Council’s existing sewerage reticulation system at the Developer’s expense
                      to the standards and requirements of Council’s building Surveyor.
               15.    Filling levels and floor levels of all buildings, other structuresand car park area levels
                      shall be established to the requirements of the Shire Engineer. Such levels shall be
                      provided upon application to the Engineering Department.


                                                                                                       Page 2 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023

Used in these records

About this file

File size
210 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval 51987 2949 6.pdf · 210 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.