Minor Change Existing Approval 51987 2949 6 · 51987.2949.6
4. ASSESSMENT MANAGER CONDITIONS
1. Compliance with all relevant provisions of the Town Planning Scheme, Chapter XLIV (Town
Planning) and other Council Policies
2. The site shall be developed substantially in accordance with the plans forming part of and
approved with this application.
3. In accordance with Section 33 (16D) of the Local Government Act 1936, Council's approval
is valid for a period of two (2) years at the expiration of which period the Council may take
action to revoke its approval, if in the opinion of the Council substantial progress has not
been made in erecting the building or other structure the subject of the Consent Permit; or
the land, subject to the Consent Permit, is not being used substantially in accordance with
the purposes for which consent was granted
4. To ensure compliance with any and all conditions of this approval Council will require that
you enter into a Bank Guarantee of $100,000 to secure performance. The guarantee shall
be lodged with Council prior to the issue of a Building Permit. Any costs incidental thereto
will be borne by the Developer.
5. The conditions of this approval are to be completed prior to the occupancy of the building
and if this is not done, Council reserves the right to call on the bank guarantee lodged to
carry out the works involved.
6. Contributions shall be Water supply and Sewerage within fourteen (14) days paid in
accordance with Council's Policy on Headworks. Such contributions shall be paid of
building approval. Contributions shall be payable at the following rate: -
Water Supply - $40,452
Sewerage $16,382
(Plus P.I. index rises from April, 1987).
7. Payment of any outstanding rates owing on the property.
8. This consent approval does not imply Building Approval. Working drawings shall be
submitted in compliance with the Building Act 1975 as amended and shall be
substantially in accordance with the plans the subject of this consent. (Substantial
variations will require separate Council approval).
9. The approval herein is for Town Planning Consent only and does not imply that Council
approval will be granted to an application under the Building Units and Group Titles Act.
10. Permanent covered car parking is to be provided on site for 36 vehicles. Of these spaces at
least 25 must be covered and at least 6 must be available for use by visitors to the premises.
11. All internal roadworks (including parking areas) and access from the existing frontage
road to connect to the internal roadworks shall be provide with a sealed pavement, which
shall be designed, drained, constructed and maintained in accordance with the
standards and requirements of the Shire Engineer.
Plans and specifications for the above works shall be submitted to the Shire Engineer
for approval prior to the issue of a Building Permit.
12. The Developer shall bear the cost of alteration of any public utility or facilities necessitated
by the development of the land or associated development external to the site.
13. Connection to Council’s existing water supply reticulation at the Developer’s expense to the
standards and requirements of Council’s Building Surveyor.
14. Connection to Council’s existing sewerage reticulation system at the Developer’s expense
to the standards and requirements of Council’s building Surveyor.
15. Filling levels and floor levels of all buildings, other structuresand car park area levels
shall be established to the requirements of the Shire Engineer. Such levels shall be
provided upon application to the Engineering Department.
Page 2 of 10
Document Set ID: 22418280
Version: 3, Version Date: 08/05/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Minor Change Existing Approval 51987 2949 6.pdfRelated documentApplication case desk ↗
About this file
- File size
- 210 KB (small file)
- File type
No other editions are linked here.