2022-11-14 General Committee Meeting Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 14 NOVEMBER 2022
1. 2022-2023 OPERATIONAL PLAN
The Operational Plan contains details of the specific projects that were adopted by Council as part
of its budget process. The reporting format for the FY 2022-23 operational plan contains
operational initiatives based on the key focus areas of the Corporate Plan whereas the “business
as usual” activities are included in Branch Plans.
Details of each Operational Plan Initiative are set out in Attachment 1 with a progress update of
each item using the following status criteria of
completed
on track
behind schedule
not started
Additional comments on each item are also provided by the responsible officers for completeness.
It is important to note that this report is for the first quarter of 22/23 Financial year and reflects the
progress as at 30 September 2022.
There are over 90 operational and sub operational initiatives (it should be noted this is an increase
of 16% on the previous FY) grouped under and answerable to the 5 key themes of the adopted
Corporate Plan of:
Noosa Environment
Noosa Community
Noosa Economy
Long Term Planning for Noosa Shire
Excellence as a Council
The current overall status of these initiatives is:
Status Quarter 1 Quarter 2 Quarter 3 Quarter 4
(July – Sept 2022) (Oct – Dec 2022) (Jan – Mar 2023) (Mar – June 2023)
Not started 5
Behind Schedule 15
On Track 67
Completed 2
In addition to the Council Officer comments at attachment 1, the following analysis can be provided
for behind schedule, not started or projects requiring further commentary:
1.3 – It is noted that there is concern by Councillors in relation to the Zero Emissions Strategy.
Council Officers that deliverables of the strategy are on track as at 30 September, however
there is significant work to be undertaken during the rest of the financial year.
1.4 – The implementation of the Waste Strategy is behind schedule, this will return to being on
track at the completion of the Corporate Plan.
1.5 – Internal resourcing has impacted delivery during the 1st quarter.
1.7 – SEMP is being monitored for delivery in 2023.
1.7 – This has not commenced due to resourcing and will be implemented as an action from the
Waste Strategy.
2.3 – Delay is due to awaiting vehicle delivery, once delivered this project is completed.
2.8 – Behind schedule as at Q1, both items will return to on track at Q2.
3.2 – It is noted that the DMP project is behind schedule.
4.1 – Behind schedule as at Q1, both items will return to on track at Q2.
Page 51 of 62
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.