' 4 Frontage Works
1. Introduction
i The frontage works for this development will include the following,
e Retaining walls to the street frontage
i e Retaining walls to the driveway up to the garage
© Storm water connection to the street
® Sediment and erosion control of the street frontage
i ® Landscaping
2. Retaining walls
i The retaining walls to be built will be maximum 1.0 metre high they will be constructed as per the
engineers drawings, using Gympie quarry rock similar to what has been used on the existing retaining
i wall, the only difference will be the rock selected will be of a more uniform, regular shape, with flatter
faces, this will achieve a more architectural! form
i 3. Storm water
The storm water connection to the street will be completed as per the engineer's drawings, a pit will be
installed to reduce/control the flow of water onto park Rd. All water collected will be diverted to a
rainwater collection tank, excess water will be dispersed via the pit at boundary curb adapters will be
used to connect the pipe work to the street
Prior to construction sand bags will be placed in the gutters to prevent sand entering the storm water
i system
i 4, Sediment and Erosion control
Sediment and erosion control will be completed as per the engineer's drawings.
Sediment flow from rain water over the site has made the existing retaining wall to park Rd unable to
i hold back the sand and mulch behind the wall, it is proposed to raise/ replace the left side of the
retaining wall, to build it up to a suitable level. All measures will be in place prior to commencement of
! construction
5.0 landscaping
i Landscaping will be undertaken by Greenscapes nursery and design [Richard Leathers] who currently
maintain number 12 Park Rd, the design of the landscape will be in accordance with council guidelines a
pre start meeting with council will be held no works to the street frontage will be undertaken without
permission from the relevant council officer
It is proposed that the undergrowth will be cleared and re landscaped to improve the site lines of
vehicles leaving the siteSee the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
001A7F25.001.pdfRelated documentPublic source context ↗
09/0578 - Operational Works - Landscaping, Carparking, Access, Frontage Works, Stormwater Drainage, Site Civil Works, Sewer & Water Reticulation [As Published]Related documentApplication case desk ↗
About this file
- File size
- 6.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.