PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 2 FEBRUARY 2016
Page 67 of 81
QUALITY SERVICE DELIVERY
No. Project Responsibility Update St)
1 Development of Pomona Disaster Management Plan Director Planning & Infrastructure A draft Pomona Disaster Management Plan was considered by the Noosa Local On track @
Disaster Management Group at its meeting on 26 November 2015. Further
details were requested to be included and reported back in February 2016.
2 Review of options for Council customer service reception area Executive Manager Concept brief drafted and Building Section consulted. Request for quote to be On [email protected] Adoption and implementation of Waste Management Strategy Manager Waste & Environmental Health Draft strategy to be finalised by March 2016. On track @
4 Develop tender for next Waste Services Contract Manager Waste & Environmental Health Manager Waste and Environmental Health to go offline from February 2016 to On track @
focus on developing tender for consideration by Council in June 2016.
5 Undertaking kerbside bulk waste collection service Manager Waste & Environmental Health Kerbside collection completed October 2015 and outcomes reported to Council. Completed @
6 Community engagement focus Executive Manager Project and media support provided to 'Have Your Say ‘site and to developing On track @
comunications plans for major projects including the ‘Zero Waste' campaign.
LOOKING AFTER COMMUNITY ASSETS
No. Project Responsibility Update BS) cL t0 Es
1 Refurbishment of Munna Point Bridge Project Manager Contractors are onsite, progress is to schedule. On track for completion in April Ontrack (%
2 Replacement of bus shelters to meet disability access standards Designer - Capital Works Contractors are have commenced civil works and program on track for On track @
completion by end of May.
3 Construction of Dr Pages Road and Kinmond Creek Road Infrastructure Planning & Design Manager Contractors are onsite, progress is to schedule. On track for completion in April. On track @
4 Finalisation of high level Asset Management Plans Asset Planning Coordinator Completed and endorsed by Council at its Ordinary Meeting on 22 October [email protected] Delivery of Capital Works Program on time and on budget Director Planning & Infrastructure All projects are on track to be delivered as scheduled by 30 June 2016. On track @
6 Resolving Noosa North Shore land tenure issues Executive Officer Council resolution 17 December 2015 provides direction. Implementation On track @
commenced but it will take a number of years to complete due to complexity of
processes to change tenure and the range of State agencies involved.
Page 67 of 81See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.