                              PROPOSED UNIT DEVELOPMENT
                              3 HENDERSON STREET, SUNSHINE BEACH

1.0      INTRODUCTION
This report details the results of a geotechnical investigation undertaken for a proposed residential unit
development at 3 Henderson Street, Sunshine Beach. The investigation was performed by Tectonic at the
request of the HR Design Group, generally in accordance with Proposal P22302-Rev0, dated 17 May 2022.

The investigation comprised drilling of boreholes at two locations across accessible areas of the
development footprint, together with in-situ soil strength testing. This report summarises the results of the
investigation and provides geotechnical recommendations regarding slope stability, earthworks and footings,
together with advice regarding temporary and permanent basement retention. In summary, subject to the
implementation of the recommendations made herein, it is assessed that there would be a Low Risk of slope
instability affecting the proposed development in accordance with the Australian Geomechanics Society
Guidelines for Landslide Risk Management, dated March 2007 (AGS 2007).

2.0      PROPOSED DEVELOPMENT
Preliminary architectural drawings were supplied to Tectonic (Ref. Chris Clout Design, Sheet Nos. C0.0 to
C4.1, Issue Preliminary Concept, dated 4 May 2022). These plans indicate that the development will
comprise a four-storey building, over a single level inground basement. Construction will likely include a
combination of masonry and lightweight materials (e.g. weatherboard cladding to walls etc.), and
suspended concrete floors.
No earthworks details were provided at the time of reporting; however, the sections provided to Tectonic
indicate that excavations for the lower ground floor would likely be in the order of about 4 m deep to the
rear, with minimal fill (<0.5 m high) anticipated to form final levels and for landscaping. Excavations will
extend close to the site boundaries and, therefore, some form of temporary retention will be required during
construction. Isolated deeper excavations may be required for underground services and other elements.
Text Figure 1 below presents the proposed layout plan and a cross-sectional view of the proposed
development.




Text Figure 1: Proposed layout plan (LHS) and a cross-sectional view (RHS), courtesy Chris Clout Design




29 June 2022
Report No. 22227-001-Rev0                                 1

Used in these records

About this file

File size
5.1 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

geotech and slope stability.pdf · 5.1 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.