SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 6 JUNE 2017
The table and graph below provide a breakdown of expenditure as at 30 April 2017.
YTD Actual Expenditure $10,293,702
Committed Expenditure $ 8,346,117
Remaining Capital Expenditure $ 5,953,656
Full Year Budgeted Expenditure $24,593,475
Current Capital Works Program Expenditure as of 30/04/2017
Remaining Capital
Expenditure
24.21%
YTD Actual
Expenditure
41.86%
Committed
Expenditure
33.94%
Previous Council Consideration
Ordinary Meeting, 17 November 2016, Item 5, Page 8
That Council note the report by the Asset Planning Coordinator to the Services & Organisation
Committee Meeting dated 8 November 2016 providing an update on the status of the projects
currently being delivered in the 2016/17 Capital Works Programme and:
A. Note that Council has achieved 36% of actuals and commitments compared to total budget
as at 28 October 2016,
B. Endorse the establishment of a Project Control Group to assist in the coordination of the
delivery of the Capital Works Programme; and
C. Nominate Crs. Pardon & Glasgow as members of the Project Control Group.
Finance & Risk
Nil.
Page 15 of 94
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.