PLANNING & ENVIRONMENT COMMITTEE MEETING MINUTES 11 MAY 2021
5 REPORTS FOR CONSIDERATION OF THE COMMITTEE
1 OPW20/0114 PLANNING & ENVIRONMENT COURT APPEAL NO. D209 OF 2020 -
REFUSAL OF AN APPLICATION FOR OPERATIONAL WORKS - JETTY AT 1/4
PORTSIDE CT, NOOSAVILLE
Committee Recommendation
Moved: Cr Wegener
Seconded: Cr Stewart
That Council note the report by the Manager Development Assessment to the Planning
& Environment Committee Meeting dated 11 May 2021 regarding Planning &
Environment Court Appeal No. D209 of 2020 and agree to settle the appeal generally in
accordance with the following conditions:
Approved Plans
1. Development undertaken in accordance with this approval must generally comply
with the approved plans of development. The approved plans are listed in the
following table unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
20.046 Sheet 1 of 2 E Site Plan prepared by Kunkel 6 August 2020
Sheets Building Design
20.046 Sheet 2 of 2 E Floor Plan, Floor Framing Plan & 6 August 2020
Sheets Typical Section prepared by Kunkel
Building Design
Currency Period
2. The development approval lapses if the works have not been completed and all
conditions of approval been complied with by 20 May 2023, unless an application
to extend the currency period is approved by Council.
Site Specific Conditions
3. The approved plans must be certified by a suitably qualified Registered
Professional Engineer of Queensland (RPEQ) as being suitable for the intended
use prior to the commencement of construction. A copy of the certified plans must
be submitted to Council for records purposes.
4. The Registered Professional Engineer of Queensland (RPEQ) bears full
responsibility for all structural aspects of the jetty.
General Conditions
5. All structures must be designed and constructed such that they are free standing
within the waterway and are not connected to or behind the revetment wall.
6. All structures must have no detrimental effects on stormwater drains and/or
easements.
7. Jetties must have a level-walking surface of R.L 1.000 A.H.D or be level with the
top of the revetment wall.
8. A rigid handrail must be fitted on one side of the walkway.
9. No posts or vertical supports of the proposed jetty are to extend vertically from the
structure unless they provide necessary support for the handrail.
10. No boatlifting devices are to be attached or moored at the jetty structure for the
purpose of elevating a vessel above the water without Council approval.
Page 3 of 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.