With respect to loss of floodplain storage it is stated in the Flood Study that the loss of flood storage within
the site is minor when compared to the surrounding floodplain and Lake Weyba. The cumulative
impact of all sites within the Noosa River and Lake Weyba floodplain being developed with a loss of
floodplain storage has however not been considered. In such a large catchment area it is the cumulative
impact rather than site specific impact of lost floodplain storage which is of concern. In addressing this issue a
revised Flood Study considering the cumulative impact of loss of floodplain storage on other sites is not the
intention because continued loss of floodplain storage is not the Strategic Plan for either the former Noosa or
Maroochy Council areas.
Information Required
88 Provide revised plans for the development which achieve no loss of regional floodplain
storage.
Response:
In response to Council’s information request, a cumulative flood assessment was conducted to look at the
potential impact of filling in flood affected residential areas, limited development areas and rural use areas that
have been predominantly cleared (similar to the area of filling proposed on site). The existing Noosa Airport and
sportsgrounds on Weyba Road were also filled. The 100 year ARI flood inundation extent was taken from SCRC
mapping. The volume of fill assessed was more than 14 times that proposed for the site.
The results showed that there was a negligible increase (maximum of 5mm) in regional flood levels as they are
dominated by the storm surge levels within the Noosa River. Filling of the low-lying areas around Noosa River
and Lake Weyba would have minimal impact on storm surge levels, which are expected to further increase with
the impact of climate change. However, filling to the extent modelled would not be achievable, as it is likely that
there would be impacts on local flood levels for neighbouring areas. Therefore the scenario modelled is a
conservative overestimation of the achievable fill within the catchment area.
Due to the unique location of the site, where the upstream properties are located at higher surface levels, and
the provision of suitably sized waterway corridors within the site, filling has resulted in negligible impact for
surrounding properties for both the regional and local flood events. For some surrounding areas the flood levels
have actually been improved.
For further information regarding the above item please refer to Section 9 of the amended Flood Study
(Attachment 13).
Coastal Management
Issue
The Draft Coastal Protection State Planning Regulatory Provision Protecting the Coastal Environment (Draft
SPRP) states that to the extent practicable, erosion prone areas are to remain undeveloped apart from
acceptable temporary or relocatable structures for safety and recreational purposes. The QCP Access to the
eastern portion of the Northbrook site and Lake Weyba can be achieved without passing through the revised
erosion prone area.
Information Required
89 Provide revised plans for the development which to the extent practicable leave erosion prone
areas of the site undeveloped.
Response:
Since the original application was properly made the access to the eastern portion of the site has been
57
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Council Lake Weyba Information Response 28-10-13_FINALRelated documentApplication case desk ↗
About this file
- File size
- 1.6 MB (small file)
- File type
No other editions are linked here.