Minor Change - Planning Report 22.08.2028
11. Proposed change to condition 97
Propose to change condition 97 to reflect the MCU condition.
Landscaping
A change to reflect the MCU condition. Request Condition 97 to read as follows.
97. The development site must be landscaped. The works must be undertaken in
accordance with the Noosa Plan PSP 2 – Landscaping and generally in accordance with
the approved Landscaping Plans and in particular:
a) A dense 2m minimum landscaped setback to the full length of the site’s frontage
to Pearl Street (excluding access, fence and bin enclosure).
b) A dense 2m minimum landscaped setback to the full length of the site’s frontage
to Elm Street.
c) A dense 1m minimum landscaped setback to all side boundaries (excluding
stormwater infrastructure) except along the proposed driveway which adjoins
Lot 1 RP153798 where a 0.5m wide landscape setback must be provided.
d) The provision of 3 new street trees in accordance with PSP 2 – Landscaping.
e) All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures
healthy, sustained and vigorous plant growth. All plant material must be allowed
to grow to full form and be refurbished when its life expectancy is reached.
12. Delete Item 9 – Reference Documents
It is requested to remove the Site Based Stormwater Management Plan from the reference
documents because the detailed engineering operational works plans are provided and
requested to be part of the approved plans.
Plan No. Rev. Plan/Document Name Date
23098 - SBSMP/4 4 Site-Based Stormwater Management 14/5/2024
Plan prepared by Morgan Consulting
Engineers