13. OBoat Hire - Prescribed Tidal Works Code

Attached to the e-mail OBoat Hire - Proposed landing redevelopment - 222 Gympie Terrace Noosaville - Email 2 of 2.

of 27

Page text shows just the words. Original shows the document exactly as it was published.

NOOSA RIVER ENTERPRISES PTY LTD AS TRUSTEE UNDER INSTRUMENT 708121382 – PRESCRIBED
TIDAL WORKS – OBOATS REDEVELOPMENT
Performance Criteria                          Acceptable Solution                      Comments

Infrastructure, including, access, parking, sewerage and water services

environments, having regard to their         a)   subject to paragraph (b), each       The proposed structure will be
ability to resist the following:-                 Australian Standard relevant to      constructed from materials with a
                                                                                       long life, resilient to marine
                                                  the materials that should be
a)   attack by marine organisms;                                                       organisms, corrosion and salt water.
                                                  used, or the measures that
b)   corrosion;                                                                        The engineered plans show the
                                                  should be taken to treat             materials used.
c)   deterioration    or     breakage
                                                  materials used, for structures, to
     resulting from exposure to
                                                  the extend the requirements
     environmental          conditions
                                                  stated in the Standard apply to
     including, for example, the
                                                  structures located in a marine
     following:-
                                                  environment;
          (i)      abrasion;
                                             b) if a relevant planning scheme
          (ii)     immersion        in
                                                  standard is more stringent than
                   seawater;
                                                  the standard mentioned in
          (iii)    wave action.
                                                  paragraph (a) – the relevant
                                                  planning scheme standard, to the
                                                  extent it is more stringent than
                                                  the standard mentioned in
                                                  paragraph (a).
12.5      Prescribed tidal works are         The design and construction of the        Not applicable.
designed and constructed in a way to         prescribed tidal works is consistent
ensure they do not adversely affect          with the following standards:-
the operation or maintenance of any
existing stormwater outlet.                                                            There are no existing stormwater
                                             a)   subject to paragraph (c), vessels
                                                                                       outlets in this location.
                                                  moored at prescribed tidal work
                                                  do not impede the discharge of
                                                  stormwater;
                                             b) subject       to    paragraph   (c),
                                                  prescribed tidal work does not
                                                  restrict access to any stormwater
                                                  outlet;
                                             c) if a relevant planning scheme
                                                  standard is more stringent than
                                                  the standard mentioned in
                                                  paragraph (a) – the relevant
                                                  planning scheme standard, to the
                                                  extent it is more stringent than
                                                  the standard mentioned in
                                                  paragraph (a) or (b).
12.6    Prescribed tidal works are           The design and construction of the        Compliant.
designed and constructed in a way to         prescribed tidal works is consistent
ensure they do not adversely affect          with the following standards:-
the water quality of any tidal water,
including, in particular, as a result of:-   a) subject to paragraph (b), each         The proposed structure will involve
                                                                                       only minimal and short lived
                                                  Australian Standard relevant to
                                                                                       disturbance to the bed during the
a)   release, into the tidal water, of            the design or construction of
                                                                                       removal of the old piles and
     materials     used      in    the            structures under, within or over     installation of the new piles. Should a
     construction of the work; or                 tidal water, to the extent the       sediment plume occur as a result of
b)   disturbance to the sediment on               requirements stated in the           the piling activities and spread to
     the bed and banks of the tidal               Standard     are   directed   at     greater than 30m from the source,
     water; or                                    maintaining the water quality of     work is to stop and action is taken to
c)   exposure to acid sulphate soils.             tidal water;                         reduce the plume from spreading.
Log in to download the original file

13. OBoat Hire - Prescribed Tidal Works Code.pdf · 289 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.