13. OBoat Hire - Prescribed Tidal Works Code
Attached to the e-mail OBoat Hire - Proposed landing redevelopment - 222 Gympie Terrace Noosaville - Email 2 of 2.
NOOSA RIVER ENTERPRISES PTY LTD AS TRUSTEE UNDER INSTRUMENT 708121382 – PRESCRIBED
TIDAL WORKS – OBOATS REDEVELOPMENT
Performance Criteria Acceptable Solution Comments
Earthwork and Vegetation
7.3 After the construction of Land or vegetation affected by the Compliant
prescribed tidal works, any land prescribed tidal works is dealt with in
damaged or destabilized by, and any a way consistent with the following
vegetation damaged, destroyed or standards:-
removed by, the construction of the The land under the water will only be
works is rehabilitated. a) subject to paragraph (b):- disturbed to the extent required to
undertake the removal of the existing
i) land surfaces damaged or
piles and installation of the new
destabilised by the prescribed
pontoon finger piles. This
tidal works are restored an disturbance will only temporary.
stabilised; and
ii) vegetation damaged,
destroyed or removed by
prescribed tidal works is
replaced with native
vegetation for the locality
within which the work is
located, to the extent it is
reasonably practicable to
replace the vegetation with
native vegetation;
b) if a relevant planning scheme
standard is more stringent than
the standard mentioned in
paragraph (a) – the relevant
planning scheme standard, to the
extent it is more stringent than
the standard mentioned
paragraph (a);
c) any other relevant planning
scheme standard that is not
inconsistent with the standards
mentioned in paragraphs (a) and
(b).
Performance Criteria Acceptable Solution Comments
Public access – availability
8.1 Prescribed tidal works do not have The design and construction of the Compliant
a significant adverse effect on the prescribed tidal work is consistent
availability of public access to, along with:-
or across State coastal land.
a) subject to paragraph (b), The proposed structure will not
involve the erection of any physical
prescribed tidal works do not
barrier preventing access along the
involve the erection or placement
foreshore.
of any physical barrier preventing
existing public access, along or
across State coastal land near the
works;
b) if a relevant planning scheme
standard is more stringent than
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.