GENERAL COMMITTEE MEETING AGENDA 12 January 2015
REPORT
1. PROPOSAL
The proposal seeks approval for as constructed building works within the 4.5m setback to the
Noosa Waters canal. The encroachment consists of 4 concrete plinths, 4 steel columns
supporting the roof and a portion of the upper level timber deck of the partially constructed
dwelling. Table 1 below summarises the extent of the encroachments.
Table 1 - Summary of the encroachments
Structure Encroachment Height Above Natural Ground Level
(NGL)
4 x Concrete plinths 3 x 0.9m 2m approx.
1 x 0.33m
Steel columns and roof facia 0.29m – 0.32m 6.8m – 7.8m
Lower deck 0.10m 1.2m approx.
Upper level deck (2.5m width) 0.20m 4m approx.
Figure 3 - Plans showing the encroachment
Page 75 of 147
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.