INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 1 MARCH 2016
Page 24 of 81
INFRASTRUCTURE & SERVICES COMMITTEE MEETING AGENDA 1 MARCH 2016
spaces in the recreation reserve near the Veggie
Village. This will provide more spaces that are
accessible near the Laneway and closer to the
Village Centre. Further, the provision of
additional carparks at this location is likely to be
more cost effective, given the cost already
involved in providing spaces at this location,
having regard to the net gain.
The total number of carparks has been increased
to 169 (Stage 2), as follows:
e 66 plus 2 disabled spaces being for the
Digital Hub;
e 5, plus 1 disabled space provided near
the kindergarten;
e 50, plus 1 disabled provided near the
Veggie Village;
e 19, plus 1 disabled space in Rufous St;
and
e 24 spaces for the Community House.
Consequently, the net increase in parking
numbers is now 34 spaces; however the 68
spaces for the Digital Hub are also able to be
shared spaces.
The extension of the Vegie Village carpark | The provision of additional carparks near the
should be with Stage 1. Veggie Village would be desirable in the Stage 1.
However, given the cost of providing this
carpark as well as the protracted process of
obtaining approval from the State, this carpark is
to be provided in Stage 2. Further consideration
has been given to providing additional parking
spaces at this location, in lieu of spaces provided
in the open space area in Rufous Street, which is
a more desirable planning outcome.
Council should amend the draft plan and | The comments about making provision of extra
provide potentially 15-20 extra carparks in Area | carparks in these locations are noted; however
6 to the East and 15-20 carparks extra in Area 7 | the Master Plan seeks to obtain a balance with
or at least a minimum of 15 to 20 carparks in | the provision of open space, parking and other
Areas 6 & 7. facilities. Further consideration has been given in
the final Master Plan to providing additional
parks near the Peregian Village, in the recreation
reserve area, near the Veggie Village.
Regulated parking should be provided in Rufus | It is agreed that there is a need for some
Street, minimum of 3 hours. regulated parking to be provided in Rufous
Street; however the extent and nature of
regulated parking will need to be further
considered. This is in order to encourage longer
Page 24 of 81See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.