Skip to the record
Every meeting, every word.

Council archive · source document

Whsmp · OPW16/0021

of 586

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (16.2 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 1, section 1. The text section number identifies this passage in the reader.

71 Seaview Tce Sunshine Beach Q 4567

 Work Health Safety Management Plan

Client: Noel Robinson Architects Pty Ltd
          For Universal Property
Full text of sections 2 to 90 (of 586)

Section 2

                                                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                               WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                                     Version: 9.2



Contents
 Preface ............................................................................................................................................. 5

 Definitions & Abbreviations ............................................................................................................... 6

 Legislation References ....................................................................................................................... 8

 1.    Purpose and Scope ................................................................................................................... 11
       1.1     Purpose ................................................................................................................................11
       1.2     Project Scope/Description....................................................................................................11
       1.3     Proposed major subcontractors ...........................................................................................11
       1.4     Site Rules ..............................................................................................................................12

 2.    Safety & Health Responsibilities (MP:02) .................................................................................. 15
       2.1      Responsibilities as a PCBU....................................................................................................15
       2.2      General Responsibilities .......................................................................................................15
       2.3      Responsibilities of All Personnel Including Sub Contractors (PP:03) ...................................16

 3.    Site Establishment ................................................................................................................... 18
       3.1       Identification of Site Requirements .....................................................................................18
       3.1.1     First Aid Facilities..................................................................................................................19
       3.2       Public Protection Controls....................................................................................................19
       3.3       Site Plan ................................................................................................................................20
       3.4       Hutchinson Builders Provided Plant .....................................................................................21

 4.     Emergency Response (MP:09) .................................................................................................. 23

 5.    Risk Management (MP:10) ....................................................................................................... 24
       5.1     General Guidelines ...............................................................................................................24
       5.1.1   PRA .......................................................................................................................................24
       5.1.2   SWMS ...................................................................................................................................24
       5.1.3   Safety in Design ....................................................................................................................24

 6.    Staff Induction AND Training (PP:02 & MP:04) .......................................................................... 25
       6.1       Hutchinson Builders Site Specific Induction (PP:02) ............................................................25
       6.2       Visitor Process ......................................................................................................................27
       6.3       Training Matrix .....................................................................................................................27

 7.    Fitness for Work (SP:04) ........................................................................................................... 28
       7.1       Fatigue Management ...........................................................................................................28
       7.2       Drugs and Alcohol ................................................................................................................28
       7.3       Smoking ................................................................................................................................28

 8.    Consultation (MP:05 & PP:06) .................................................................................................. 30
       8.1      Pre Start Meetings................................................................................................................30
       8.2      Tool Box meetings ................................................................................................................30
       8.3      Site Health and Safety Committee .......................................................................................31
       8.4      Issue Resolution ...................................................................................................................31

 9.    Audits & Inspections (MP:05) ................................................................................................... 32
       9.1      Safety Audits ........................................................................................................................32


                                                                                                                                                    Page 2 of 58

Section 3

                                                                                                              Hutchinson Builders – ABN:52 009 778 330

                                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                                 Version: 9.2



      9.2           Weekly Site Safety Inspection/Daily Visual Inspection ........................................................32
      9.3           Task Observations ................................................................................................................32

10. Incident Reporting and Investigation (MP:08) ........................................................................... 33
    10.1     Internal Incident Reporting Process (Procedure MP:08) .....................................................33
    10.2     Investigation Process (MP:08) ..............................................................................................34
    10.3     Notification...........................................................................................................................34
    10.4     Rehabilitation & Return to Work .........................................................................................35
    10.5     Record Keeping ....................................................................................................................35
    10.6     Health and Safety Reporting ................................................................................................35

11. Management Of Change (MP:12).............................................................................................. 36

12. Record Maintainance & Retention ............................................................................................ 38

13. Personal Safety (SP:04)............................................................................................................. 39
    13.1     Personal Protective Equipment............................................................................................39
    13.2     Heat Exhaustion ...................................................................................................................39
    13.3     UV Protection .......................................................................................................................40
    13.4     Working Alone ......................................................................................................................40
    13.5     Wet Weather Procedure ......................................................................................................40

14. Manual Handling...................................................................................................................... 42
    14.1    Legislation ............................................................................................................................42
    14.2    General Guidance .................................................................................................................42

15. Permits to Work ....................................................................................................................... 43
    15.1     Isolation/ Tag and Lockout ...................................................................................................43
    15.2     Hot Work ..............................................................................................................................44
    15.3     Working at Heights ...............................................................................................................44
    15.4     Excavation & Penetrations ...................................................................................................45
    15.5     Coring / Drilling ....................................................................................................................45

16. High Risk Work Systems ........................................................................................................... 46
    16.1     Demolition ............................................................................................................................46
    16.2     Asbestos ...............................................................................................................................47
    16.3     Removal of lead materials....................................................................................................48
    16.4     Tower Crane Selection & Positioning ...................................................................................48
    16.5     Scaffolding ............................................................................................................................48
    16.6     Tilt up & Pre-cast Panels ......................................................................................................49
    16.7     Erecting Structural Steel .......................................................................................................49
    16.8     Swing Stage Placement, Erection & Dismantling .................................................................49
    16.9     Erecting, Climbing, Servicing & Dismantling of a Tower Crane ............................................50
    16.10    Electrical ...............................................................................................................................50
    16.11    Electrical Tools and Equipment ............................................................................................50
    16.12    Concrete Pumping ................................................................................................................51

17. Plant and Equipment (PP:07) .................................................................................................... 52
    17.1     Mobile Plant and Equipment ...............................................................................................52
    17.2     Pre Start Checks ...................................................................................................................53
    17.3     Elevated Work Platforms .....................................................................................................53
    17.4     Lasers....................................................................................................................................53
    17.5     Plant Using Compressed Air .................................................................................................54

                                                                                                                                                Page 3 of 58

Section 4

                                                                                                             Hutchinson Builders – ABN:52 009 778 330

                                            WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                                Version: 9.2



      17.6         Explosive Plant & Gas & Power Actuated Tools ...................................................................54
      17.7         Lifting Equipment .................................................................................................................54
      17.8         Loading Platform Procedure ................................................................................................55

18. Dangerous Goods and Hazardous Substances (SP:01) ................................................................ 56
    18.1    Safety Data Sheets ...............................................................................................................56

19. Safety Signage.......................................................................................................................... 57
    19.1      Barricades and Signage ........................................................................................................57

20. Waste Management (see EMS) ................................................................................................. 58
    20.1   Housekeeping (SWMS:006) / Rubbish Removal ..................................................................58
    20.2   Spills and Leakages ...............................................................................................................58


APPENDIX 1 - Risk Assessments
APPENDIX 2 - Safe Work Method Statements
APPENDIX 3 - Project Organisational Chart
APPENDIX 4 - Signed Responsibility Statements
APPENDIX 5 - Registers
APPENDIX 6 - High Risk Checklists & Site WHS Management Forms
APPENDIX 7 - Site Training Registers
APPENDIX 8 - Emergency Management Plan




                                                                                                                                               Page 4 of 58

Section 5

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



PREFACE

Hutchinson Builders has developed this WHSMP: 01- Work Health & Safety Management Plan (WHSMP) as
the appointed Principal Contractor for Noel Robinson Architects Pty Ltd for Universal Property.
This plan provides specific information regarding the management of project-related works and will ensure
that a uniform approach to health and safety is adopted.
A copy of the plan (WHSMP:01) shall be referenced in Hutchinson Builders Site Specific Induction and will be
held on site by Hutchinson Builders so that all site employees, client reps, subcontractors have access to
WHSMP:01 at all times. This plan is to be reviewed (at 3 monthly intervals) or amended where deficiencies
are identified or changes occur in Hutchinson Builders’ OH&S Management System or project works change
such that the information contained in the plan is no longer accurate or valid. If this WHSMP: 01 is altered it
will be the Team Leaders responsibility to ensure that the revised WHSMP: 01 is distributed to all Hutchinson
Builders site management staff, client representatives, site employees and sub-contractors associated with
the work.
Plan Review:

  Name                                   Position                             Signature
 Michael Michell                       Team Leader

 Jarod Dingle                          Project Manager

 Cameron McAndrew                      Team Safety Manager

 Jarod Dingle                          Contract Administrator

 Terry Strahan                         Site Health & Safety Advisor

 Matt Leeke                            Site Manager

 Terry Strahan                         Site Foreman

 Jesse Joyce                           Site Foreman

Plan Revision:

  Revision Number          Review Date           Actions / Amendments                     By Whom
 # 01                  04/07/2016            Site Specific Amendments        Cameron McAndrew




                                                                                                              Page 5 of 58

Section 6

                                                                               Hutchinson Builders – ABN:52 009 778 330

                                  WHSMP:01 – Work Health & Safety Management Plan
                                                                                                             Version: 9.2



DEFINITIONS & ABBREVIATIONS

                      An undesired event that results in physical harm to a person or damage to property
Accident
                      (Refer to Incident).
                      Published standards and codes of practice that give practical advice on ways to be used
Advisory Standards
                      to identify and manage exposure to risk for workplace health and safety.
                      Means a systematic review of the safety management systems being applied on the
Audit
                      project.
                      Shall mean the person nominated by Client to carry out the duties of the Client
Client
                      Representative.
                      A person possessing the necessary skills, training, experience and knowledge or
Competent Person      combination of these traits. Such that a skill can be performed in a safe manner, to the
                      quality expected in the workplace.
                      The process of enhancing the project safety management system as stated by the Work
Continual
                      Health & Safety Management Plan to achieve improvements in overall safety in line
Improvement
                      with the Hutchinson Builders Health and Safety policy.
Contractor            Shall mean Hutchinson Builders and shall include its successors and permitted assigns.
Duty of Care          A statutory legal obligation. To ensure as far reasonably practicable, the health and
                      safety of workers and all other persons; while the workers are at work in the business.
                      Means an undesired event that results in physical harm to a person or damage to
Incident              property, or, any “Near Miss” incident that has the potential to cause physical harm to
                      a person or damage to the property.
Inspection            Means a review or check on the safety requirements being implemented.
May                   The use of “may” indicates a guideline that is to be considered.
                      A legal relationship between two entities in which one entities’ right is the other
Obligation
                      entities’ duty.
Personal Protective   Means clothing or equipment which, when used correctly, protects part or all of The
Equipment             body from identified risks of injury or disease in the workplace.
                      Local Government acts and regulations which prescribe legal obligations of employers,
Regulatory            employees and subcontractors and amongst other things, registration of projects and
Requirements          plant, certificates to operate machinery and undertake certain trades and notifications
                      or injuries.
                      The chance of something happening that shall have an impact upon objectives. It is
Risk
                      measured in terms of consequences and likelihood.
                      The systematic application of management policies, procedures and practices of the
Risk Management
                      tasks of identifying, analysing, assessing, treating and monitoring risk.
Roads                 The pathway to carry vehicles or plant between different locations.
Safe Work Method      A study carried out to ensure that hazards are identified, analysed and properly
Statement (SWMS)      controlled to minimize, or, if practicable, eliminate risks.
                      Means the formal meeting between employees and site management on safety topics
Safety Meeting
                      relating to the workplace.
                      Safety Data Sheets are documented information which clearly identifies a hazardous
SDS: Safety Data
                      substance and states the precautions to be taken for the safe storage and use of the
Sheet – (formerly
                      substance and the health hazards associated with the substance that are relevant to
MSDS)
                      it’s safe use.
Shall                 The use of “shall” indicates a mandatory requirement.
Should                The use of “should” indicates a guideline that is strongly recommended.
Subcontractor         Means any Subcontractor engaged by Hutchinson Builders.
Work Health &         Shall mean the Work Health & Safety Management Plan (WHSMP:01) that applies to
Safety                Hutchinson Builders and it’s sub-contractors.
Management Plan



                                                                                                            Page 6 of 58

Section 7

                                                                             Hutchinson Builders – ABN:52 009 778 330

                                 WHSMP:01 – Work Health & Safety Management Plan
                                                                                                           Version: 9.2



Following abbreviations and acronyms are applicable to this WHSMP:

 ALARP                   As Low As Reasonable Practicable
 AS                      Australian Standard
 AS/NZS                  Australian Standard/ New Zealand Standard
 DA                      Development Area allocated to Hutchinson Builders
 ERP                     Emergency Response Plan
 EWP                     Elevated Work Platform
 FAI                     First Aid Injury
 FSO                     First Aid Officer
 ITP                     Inspection Test Plan
 JSA                     Job Safety Analysis
 LTI                     Lost Time Injury
 MTI                     Medically Treated Injury
 MOT                     Management Of Change
 OFSC                    Office of the Federal Safety Commissioner
 OHSMS                   Occupational Health & Safety Management System
 PRA                     Project Risk Assessment
 RRTW                    Rehabilitation & Return To Work
 SDS                     Safety Data Sheet
 SWMS                    Safe Work Method Statement
 WHSMP                   Work Health & Safety Management Plan




                                                                                                          Page 7 of 58

Section 8

                                                                         Hutchinson Builders – ABN:52 009 778 330

                               WHSMP:01 – Work Health & Safety Management Plan
                                                                                                       Version: 9.2



  LEGISLATION REFERENCES

Acts              Work Health & Safety Act 2011
                  Workers Compensation & Rehabilitation Act 2003
                  Electrical Safety Act 2002
Regulations       Work Health & Safety Regulations 2011
                  Workers Compensation & Rehabilitation Regulations 2003
                  Electrical Safety Regulations 2013
National          How to Safely Remove Asbestos Code of Practice 2011
Codes of          How to Manage and Control Asbestos in the Workplace Code of Practice 2011
Practice          Confined Spaces Code of Practice 2011
                  Construction Work Code of Practice 2013
                  Work Health & Safety Consultation Cooperation & Coordination Code of Practice 2011
                  Demolition Code of Practice 2013
                  Managing Electrical Risks at the Workplace Code of Practice 2012
                  Excavation Work Code of Practice 2013
                  Managing the Risk of Falls at the Workplace Code of Practice 2011
                  Managing the Work Environment & Facilities Code of Practice 2011
                  First Aid in the Workplace 2012
                  Labelling of Workplace Hazardous Chemicals Code of Practice 2011
                  Managing Risks of Hazardous Chemicals in the Workplace Code of Practice 2013
                  Hazardous Manual Tasks Code of Practice 2011
                  Managing Noise and Preventing Hearing Loss at Work Code of Practice 2011
                  Hazardous Chemicals Code of Practice 2003
                  Australian Dangerous goods Code 7th Edition 2011
                  Electrical Safety Code of Practice 2010 (Working Near Exposed Live Parts)
                  Electrical Safety Code of Practice 2010 (Electrical Work)
                  Electrical Safety Code of Practice 2010 (Works)
                  Electrical Safety Code of Practice 2010 (Risk Management)
                  HB-HSEQ-F-005 List of Referenced Legislation and Codes of Practice
                  HB-HSEQ-F-005-A List of Referenced Legislation and Codes of Practice - Environment
QLD State         Concrete Pumping Code of Practice 2005
Codes of          Design of structures Code of Practice 2013
Practice          First Aid Code of Practice 2004
                  Formwork Code Of Practice 2006
                  Managing the Risk of Plant in the Workplace 2013
                  Mobile Crane Code of Practice 2006
                  Scaffolding Code of Practice 2009
                  Steel Construction Code of Practice 2004
                  Tilt-up and Precast Construction Code of Practice 2003
                  Tower Crane Code of Practice 2006
                  Traffic Management For Construction Or Maintenance Work Code of Practice 2008
                  Licensing Persons Performing High Risk Work National Code of Practice 2006
                  Prevention of Workplace Harassment Code of Practice 2004
                  Welding practices Code of Practice 2013
Standards          See;
                  HB-HSEQ-F-004 List of Relevant Australian Standards
                  AS 2865:2009 Confined Spaces
                  AS/NZ 4801-2001 Occupational Health & Safety Systems
                  AS/NZS 31000-2009 Risk Management Principles and Guidelines
                  AS 1940-2004 Storage & handling of flammable & combustible liquids


                                                                                                      Page 8 of 58

Section 9

                                                           Hutchinson Builders – ABN:52 009 778 330

                WHSMP:01 – Work Health & Safety Management Plan
                                                                                         Version: 9.2



   AS 2550.1-2011 Cranes, hoists and winches - Safe use
   AS 1742 Set-2010 Manual of uniform traffic control devices Set
   AS 4497-1997 (Series) Round slings – Synthetic fibre
   AS 1666-2009 (series) Wire-Ropes Slings
   AS 1891-2007 ( Series) Industrial fall arrest systems & devices
   AS/NZ 4602.1-2011 High visibility safety garments
   AS/NZ 2210.1-2010 Safety, protective and occupational footwear – Guide to selection,
    care & use.
   AS/NZS 4836-2011 Safe working on or near low voltage electrical installations and
    equipment




                                                                                        Page 9 of 58

Section 10

Page 10 of 58


[OCR of page images]
HUTCHINSON Work Health & Safety Policy Statement

Estes 1912 Version: 4
Review 2 March 2017

WORK HEALTH AND SAFETY POLICY STATEMENT

Workplace Health and Safety is of critical importance to the successful performance of Hutchinson Builders’
operations. It is the policy of Hutchinson Builders to conduct its activities in such a way that the health, safety and well
being of employees, subcontractors and all workers is not in any way impaired or prejudiced as a result of working
within or for the Company.

To aid in the implementation of this Policy, Hutchinson Builders shall:

* ensure its operations are in accordance with AS 4801 certification and Federal Safety Accreditation through
implementation of a monitoring and review process.

¢ comply with all relevant statutory duties, regulations and codes of practice, making adequate provision of
resources to meet these requirements;

* provide information, instruction and training for employees to increase personal understanding of workplace
hazards and to ensure proper supervision;

* involve employees and sub-contractors on health and safety matters, and consult with them in ways to
reduce workplace hazards and improve control systems;

© provide support, assistance and resources to ensure an integrated rehabilitation program is provided for all
employees who sustain injury or illness;

* set short and long-term objectives in health and safety management as part of an ongoing action plan and
regularly review overall Company performance and the performance of our managers and company
personnel, against the objectives of this policy.

Hutchinson Builders recognises that Health and Safety is both an individual and shared responsibility of all employees,
sub-contractors and other persons involved with the operation of the Company. In this regard, we emphasise the
need to follow and adhere to safe work practices at all times, to ensure that no person is exposed to or exposes others
to a health and safety risk, and to develop an ever improving safety culture within the Company.

Hutchinson Builders recognises there is no task so important that it releases the Company, its managers, employees or
sub-contractors from their responsibility to ensure a healthy and safe work environment.

fr

SIGNED AY . DATED 2 March 2015
( )

 

Greg Quinn
Managing Director

 

Page 10 of 58

Section 11

                                                                             Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                           Version: 9.2




1. PURPOSE AND SCOPE

       1.1   Purpose
The purpose of the WHSMP:01 is to provide a systematic approach to minimizing the workplace health and
safety risk identified for the project works described in section 1.2 Project Scope/Description.
The WHSMP: 01 covers multiple areas that have been identified including; public protection, communication
and consultation, emergency response, fitness for work, inductions, training, continuous improvement and
all other operational issues. The above has been identified and managed through a risk based assessment
process.
Hutchinson Builders has implemented control measures throughout this plan to ensure exposure to the
company, the client, the worker and all other stakeholders has been reduced as low as reasonably
practicable.

       1.2   Project Scope/Description

The project, 71 Seaview Terrace, Sunshine Beach QLD, comprises construction of the following:

       Architecturally designed house built into the side of a hill
       Three-level high-end residence
       Circular lift
       Resort style pool and grounds

This project is expected to be completed within approximately two years/110 weeks with commencement
in July 2016 and completion in July 2018.


       1.3   Proposed major subcontractors

 Name: Piling Civil Australia         Name: CV Services                Name: Commercial Plumbing
 Ph: 07 5500 5898                     Ph: 07 3613 5067                 Ph: 07 5450 1332
 Name: Marc Air                       Name:                            Name:
 Ph: 07 5476 6188                     Ph:                              Ph:
 Name:                                Name:                            Name:
 Ph:                                  Ph:                              Ph:




                                                                                                         Page 11 of 58

Section 12

                                                                           Hutchinson Builders – ABN:52 009 778 330

                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                         Version: 9.2



 1.4    Site Rules
1. All workers MUST have evidence of completion of a General Safety Induction Course and attend a
   site specific induction prior to starting work.
2. Site hours – 7.00am to 5.30pm. Pre-starts can start at 6.30am ready for work commence at 7.00
   Monday to Saturday. In Phase 2 Pre-Starts will be conducted at the offsite compound at Noosa
   Rugby Club.
3. All workers are to participate in Daily Pre-start Meetings with their employer work group
   representative to consult on health and safety issues.
4. All visitors MUST report to the site office and sign onto and off the project.
5. The following Personal Protective Equipment MUST be worn in all work areas at all times;
     Hard Hats – worn the correct way
     Hi-Vis Shirt or Hi-Vis vest worn over a shirt
     Leather safety footwear with protective cap (volleys/joggers not allowed)
     Additional safety gear - as required by employer or directed by HB excluding site sheds.
     All PPE shall be provided by the Subcontractor.
6. Alcohol and drugs of abuse are NOT permitted on site – persons under or observed to be influenced
   by alcohol or drugs at any time during working hours compromises the health and safety of workers
   and will not be ALLOWED on site.
7. Persons caught stealing items of a personal or material nature will be instantly removed from site.
8. Site amenities - lunch rooms and toilets provided are to be used. Persons observed relieving
   themselves other than in the toilets provided will result in that person being instantly removed from
   the site.
9. Subcontractor environmental responsibilities:
    Do not litter streets
    Do not loiter outside adjoining residences or in the access lane.
    No lewd behaviour or bad language.
    Radios are not permitted on site.
    Report any spills on site immediately to HB Site Management.
    No dry grinding (vacuums and other dust minimisation equipment are to be used).
    No illegal discharge of liquids on or off site.
    No entry into the conservation zone or neighbouring properties.
10. All workers are to clean up their rubbish on a DAILY or as needs basis. The Subcontractor shall
    supply all necessary labour and equipment to progressively clean up all trade rubbish to the bins
    provided. Bins shall be supplied by HB. All work areas must be kept clean, tidy and safe to
    Hutchinson Builders’ (HB) satisfaction.
11. All debris, rubble and rubbish must be disposed of in accordance with documentation, codes,
    standards, legislation, regulatory authorities etc. All waste materials that can be recycled must be
    sorted by the Subcontractor and placed in the recycling bins.
12. Workers MUST follow their employer’s site specific Safety Plans / Safe Work Methods Statements,
    site safety signs and ensure safe work practices. These shall be provided by the Subcontractor and
    be site specific, developed in consultation with their own workers.
13. Remember be AWARE of your safety and others when working with or near plant Listen – look up
    – observe – do not assist the plant operator in changing quick hitched or pin plant attachments –
    refer to your Employer SWMS.
14. Consider the SAFETY of your fellow worker and members of the public.

                                                                                                       Page 12 of 58

Section 13

                                                                           Hutchinson Builders – ABN:52 009 778 330

                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                         Version: 9.2



15. Do not expose yourself or others to hazards, follow safe work methods and the correct and safe use
    of hand tools to prevent injuries.
16. Workers are not allowed to alter, remove or move temporary services out of the way, provided by
    HB without prior approval of site management.
17. Electrical leads MUST be hung on an insulated Hanging Hook, Stand or Bracket where exposed to
    damage, heat or water hazards – not wrapped around non insulated metal scaffold, pipe work, lift
    cages or other metal objects.
18. Harassment – fighting – or any verbal threats of violence of a fellow worker will not be tolerated –
    resulting in that person/persons removed from site.
19. Fire safety precautions MUST be observed.
20. No glass bottles are permitted on site. Plastic or cardboard cartons are allowed as long as they are
    placed in a bin where used.
21. Permits are required for all high risk work and are to be obtained prior to the commencement of
    any high risk work, no exceptions.
22. Daily Plant Pre-starts / Log books are to be completed for each piece of plant on site.
23. All injuries and incidents to be reported to site management immediately and incident report
    completed.
24. Only site scaffolders are to adjust / erect / dismantle scaffold on site. All others are to gain
    permission from site management.
25. The Subcontractor is not permitted to place signage (other than safety signage) on any part of the
    building, formwork, screen system or attachments to the building.
26. The Subcontractor shall allow for full-time, on-site, qualified supervision for the duration of the
    works, capable of taking direction from HB and carrying out such direction.
27. The Subcontractor is to have an experienced Supervisor on site at all times, with relevant experience
    and authority to execute the works in accordance with the drawings and contract documents,
    attend all site co-ordination meetings, control all daily work activities and comply with all HB’
    document control systems eg. SWMS, WHSMP, EMP, ITPs.
28. The Subcontractor shall allow for all co-ordination of workers to site in accordance with HB Traffic
    Management Plan.
29. No parking on site, along the access lane, surrounding streets or the beach access car park on
    Seaview Terrace. In Phase 2 of construction all vehicles are to be parked at the off-site compound
    at Noosa Rugby Club. A bus service will run between the compound and site twice a day.
30. All deliveries to site must be co-ordinated through HB Site Manager, one day in advance.
    Unscheduled deliveries will be turned away and any associated costs borne by the Subcontractor.
31. Delivery trucks are to firstly park in Bryant Street, call HB Site Manager or Foreman on site and
    receive permission before proceeding to site. Trucks are not permitted to stop along any part of
    Seaview Terrace or the access lane.
32. Due to limited access and space, each parcel of work must be co-ordinated through HB Site
    Management so that the quantity of material and number of personnel brought to site does not
    exceed the capacity of the site conditions and facility.
33. The Subcontractor shall provide any task lighting required for its own use. Task lighting must
    conform to the following minimum standards:
     All lights to be guarded.
     Lights must be permanently fixed to fit for purpose stands.
     Lights to be tested and tagged by qualified electrician.

                                                                                                       Page 13 of 58

Section 14

                                                                           Hutchinson Builders – ABN:52 009 778 330

                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                         Version: 9.2



34. Trade specific and site relevant inspections, Test Plans, SWMS’ and other necessary documentation
    to satisfy requirements indicated in the specifications shall be submitted progressively as the works
    proceed.
35. Preparation and maintenance of a conforming Quality System, ITP’s specific to the project. The
    conforming Quality Procedure is to be prepared by the Subcontractor for the approval of HB and
    any relevant consultants, prior to commencement of work.




                                                                                                       Page 14 of 58

Section 15

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



2. SAFETY & HEALTH RESPONSIBILITIES (MP:02)

Attached in Appendix 3 is Hutchinson Project Organisational Chart, identifying HB Management staff and
their designated roles.
Signed copies of our responsibility statements are included in Appendix 4 of this plan for the Team Leader,
Project Manager, Site Manager, Foreman, Health & Safety Officer, Health & Safety Representative,
Personnel/Employees, Contracts Administrator and Team Health & Safety Manager.
Outlined below are the Site employees and subcontractor roles and responsibilities in relation to the
implementation and management of Health and Safety policies and procedures.

      2.1     Responsibilities as a PCBU
 HB as the appointed PCBU for the project will ensure so far as reasonably practicable that the following
 PCBU legislative requirements are complied with:

     Ensure the health and safety of workers engaged, or caused to be engaged by HB;
     Ensure the health and safety of workers whose activities are influenced or directed by HB;
     Ensure the health and safety of other persons who could be put at risk from work carried out by HB;
     Ensure a safe work environment and safe systems of work are in place;
     Ensure safe plant and structures and safe use/handling and storage of plant, structures and
      substances;
     Ensure provision of information, training, instruction and supervision are provided;
     Ensure facilities for workers’ welfare and workplace monitoring; and,
     Ensure arrangements for consultation, issue resolution and incident notifications are in place.
Outlined below are the Site employees and subcontractor roles and responsibilities in relation to the
implementation and management of Health and Safety policies and procedures.

      2.2     General Responsibilities
All personnel shall strive to achieve the highest standards for Health & Safety and therefore assist to minimise
the risk of accident or injury by:
     Being responsible for their actions and taking due care while performing their work.
     Complying with all necessary requirements that are put into place to prevent injury or loss.
     Reporting and fully disclosing all information regarding accidents, incidents and near misses.
     Using all mechanical and personal equipment provided, in such a manner as to ensure the safety of
      themselves, other personnel and the equipment.
     Maintaining the workplaces in a clean and tidy state.
     Assisting HB by supporting change, so as to achieve the desired goals.
     Each person ensuring his or her own safety and health at work, and avoiding adversely affecting the
      safety or health of any other person through any act or omission at work.
     Sharing the same ownership, responsibilities and liabilities in all areas of safety.
Safety is the responsibility of each individual working in the work place.




                                                                                                              Page 15 of 58

Section 16

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



         2.3   Responsibilities of All Personnel Including Sub Contractors (PP:03)
All personnel performing works on this project are required to conform and comply in all respects with the
relevant Health and Safety Legislation, site direction and conditions of the signed subcontractor agreement.
They will also be required to fulfil the following minimum requirements as a condition of performing work
on this project:
    a)     To comply with all instructions issued by HB in relation to Health and Safety requirements.
    b)     Maintain the correct protective clothing and equipment for their works on this project.
    c)     Ensure that adequate training is completed for the work being performed, and work is performed
           in accordance with the corresponding Safe Work Methods Statements / Job Hazard Analysis sheets
           and ensure correct use of protective clothing and equipment.
    d)     Ensure plant and equipment meet all the requirements outlined in this document.
    e)     Report all incidents to HB Site Management immediately after the occurrence. At which point HB
           shall pass this information to the client representative immediately after being made aware of the
           incident. A high level of reporting is expected throughout the duration of this project.
    f)     HB site specific inductions will need to be completed prior to starting work on the project.
    g)     HB sub-contractors are to provide one worker on request for participation in the site health and
           safety committee as required.
    h)     Ensure a Health and Safety Site Manager is employed on site in accordance with Work Health and
           Safety requirements.
    i)     HB contractors are to help ensure that all workers comply with the relevant Health and Safety
           Legislation.
    j)     Sub-contractors must submit Safe Work Method Statements (SWMS) in accordance with the
           relevant states Health and Safety Legislation to HB for approval prior to work on site and include
           information as detailed below:
                   Provide a list and evidence of all workers with certificates of competency relevant to their
                    proposed works issued under the relevant Health and Safety Act.
                    Scope of work, SWMS and commencement date of works.
                    Staff responsibility statements in implementing safe work practices.
                    Nomination of a supervisor to oversee all works on site.
                   A register of all hazardous substances and dangerous goods, with accompanying copies
                    of all SDS and safe work procedures.
                   Details of all tasks requiring, the use of personal protective equipment as a control and
                    the specific personal protective equipment to be used.
                   Workers required to use fall arrest/restraint equipment are to be instructed in safe work
                    at heights requirements and in the safe use of fall equipment. They are to provide
                    evidence of instruction at the site induction.
                   Evidence of competency for high risk work, including the operation of excavators and
                    other earthmoving equipment.
    k)     HB sub-contractors must attend the daily pre-start meetings in their respective work area.
All personnel are required to meet all HB health and safety standards, and operate within the parameters set
by this Work Health & Safety Management Plan (WHSMP). A copy of the WHSMP is held on site and available
for perusal upon request.
Persons who do not strictly comply with all the requirements of the state’s relevant Health and Safety
Legislation, HB' WHSMP and client standards will be removed immediately from the site and will not be

                                                                                                              Page 16 of 58

Section 17

                                                                              Hutchinson Builders – ABN:52 009 778 330

                                  WHSMP:01 – Work Health & Safety Management Plan
                                                                                                            Version: 9.2



allowed on site until such time as they comply in all respects with the statutory requirements. HB are
responsible for all of sub-contractors on this project. However all sub-contractors are PCBU’s in their own
right and cannot delegate or divorce from the PCBU’s obligations.
The safety management team shall review each subcontractor’s SWMS or Safety Plan where high risk work
activities are undertaken and record their review on the Safe Work Method Statement – Checklist prior to
that subcontractor commencing work (Additional information relating to the management of subcontractors
on HB sites can be located in PP:03 Subcontractor Management and Subcontractor SWMS Checklist - HB-
HSEQ-F-021-A).




                                                                                                          Page 17 of 58

Section 18

                                                                                                                            Hutchinson Builders – ABN:52 009 778 330

                                                     WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                                                Version: 9.2



3. SITE ESTABLISHMENT

             3.1     Identification of Site Requirements
The following site specific table outlines the minimum site requirements for first aid, supply of a first aid
room, toilet facilities and crib room. As the site / project progresses the requirements of the site will change.
After reviewing the requirements outlined in the Table 1, in alignment with the relevant corporate
procedures (PP:04 and PP:05). Table 2 is to be complete at the relevant minimum intervals not exceeding 3
months for the project. This process completes the specific site establishment assessment for the project.
Table 1. Minimum Site Establishment Requirements.
                                                                                          Number of workers on site
 Site Requirement                                                1-20                                21-100                                   100 >
 First Aid Kit (PP:05)                                       Small Kit                           Standard Kit
 First Aid Room                                                                                                                       FA room required
 Toilet Facilities (as per PP:04)                -         Have 1 toilet for each 15 persons
                                                 -         1 urinal per 25 males
                                                 -         Ground level, 4th level, and each 3rd level thereafter.
                                                 -         If less than 15 people a portable toilet can be utilised but must be
                                                           connected to sewerage system within 2 weeks of becoming
                                                           available.
 Crib Room                                       Minimum requirement of a floor space of at least 1 m2 per worker for 20 workers or more.
                                                 Have adequate number of tables and seats to accommodate each worker likely to use the room at
                                                 one time.




Table 2. Specific Site Establishment Assessment.
    Site
 Requiremen              Revision Required                                                        Site specific information
      t

                                                         Initial Set        3 month             6 month             9 month           12 month          15 month
    WHSMP revision




                                                             up               mark                mark                mark              mark              mark
       interval




                     Calculation of staff
                     on site                         ____5____          __10-15___          __15-25___              __15-25__      __15-25__            __15-25__
                                                      Workers            Workers             Workers                 Workers        Workers              Workers
    First Aid Kit
      (PP:05)




                     Insert type and number                 1x                 1x                  1x                  1x                1x                1x
                     of First Aid Kits                   Standard           Standard            Standard            Standard          Standard          Standard
    First Aid




                                                         Site Office        Site Office         Site Office         Site Office       Site Office       Site Office
     Room




                     Insert specifics of First
                     Aid Room


                                                     -       3          -       3           -       3           -       3         -       3         -       3
    Amenities




                     -    Number of toilets
     (PP:04)




                     -    No. urinals                -       TBA        -                   -                   -                 -                 -
                     -    No. Female toilets         -       TBA        -                   -                   -                 -                 -
                     Insert minimum floor                Adequate           Adequate            Adequate            Adequate          Adequate          Adequate
       Crib Room




                     space required.                     tables &           tables &            tables &            tables &          tables &          tables &
                     Specify the number of               chairs as          chairs as           chairs as           chairs as         chairs as         chairs as
                     tables and chairs                   required           required            required            required          required          required
                     required.


                                                                                                                                                             Page 18 of 58

Section 19

                                                                                   Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                 Version: 9.2




3.1.1 First Aid Facilities
A First Aid Kit shall be stocked and replenished and is to be available and maintained in a readily accessible
location. It is the responsibility of the Site Manager / Health & Safety Advisor to ensure First Aid facilities is
adequately stocked. HB First Aid Checklist form HB-HSEQ-F-028-A shall be used to check supplies on a weekly
basis.
Additional supplies of any of the materials listed above may be necessary on sites with large numbers of
personnel. These can be obtained from the nominated safety equipment supplier.
HB will have a First Aid Officer on site at all times. All injuries must be reported to that provider in the first
instance of occurrence.
A First Aid Record will be completed for all injuries and Incident / Injury / Hazard Report Form HB-HSEQ-F-
027-B will be completed for all injuries MTI and above i.e. RWI, LTI and for all serious near miss incidents.

      3.2     Public Protection Controls
HB have identified that specific public protection and exclusion controls need to be implemented throughout
the duration of all projects. These include signage informing of site activity and barriers preventing entry to
the site.
To achieve adequate public protection and exclusion zones HB will undertake the following:
Erect a Mesh fence on the proposed boundary line where exclusion is deemed necessary – refer to Appendix
1 - Project Risk Assessment for guidance and together with;

☒       Erect 1.8m high temporary fence to the property boundary;

               The temporary fence will be supported by metal supports that are to be fixed as well as
                additional incline bracing and supports (F brackets or star pickets secured to fence panels ),
                where required, to ensure the fence cannot easily topple or collapse.
               The temporary fence will be erected at the approximate boundaries, and contain lockable
                gates to allow worker, vehicle and machine access.
               Installed and maintained to manufactures specifications
               The condition and placement of the temporary fence will be monitored on an ongoing basis
                and during documented site inspections by the site team member.
Erect a gantry that complies to an engineer’s design criteria to with stand storage and design loads, on the
proposed line where exclusion is deemed necessary or where loads are being lifted over public access areas;

☐       Erect ……… high Gantry with a 5 kpa rating applied on its overhead platform to the
        ……………………. Boundary;

☐       Erect ……… high Gantry with a 10 kpa rating applied on its overhead platform to the
        ……………………. Boundary;

               Installed to the engineers details and commissioning signed off by installers
               Provide warning signs, flashing lights and audible alarm during lifts
               Provide access lighting of at least 80 lux or natural lighting



                                                                                                               Page 19 of 58

Section 20

                                                                                    Hutchinson Builders – ABN:52 009 778 330

                                      WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                  Version: 9.2




☒         Signage will be displayed at all entrances to the site and at various points on the temporary
          fence that describe;

                 HB as the construction company,
                 The site as a construction site, accessible to workers and authorised personnel only,
                 HB Safety Sign – hard hats, foot wear etc.,
                 Other safety signs as deemed necessary
☒         Develop a Traffic management plan to control heavy and light construction activities for the
          front property boundary.

A designated drop-off and construction “works” zone will be established. This zone will enable delivery
vehicles and plant such as concrete pumps, delivery vehicles to safely park and enter/exit the project. Traffic
controllers will be used in this area where required to warn members of the public/ other contractors on site,
of the moving equipment and to safely direct the vehicles and plant. HB will reschedule any plant and material
movements outside busy access periods.

         3.3   Site Plan
A site plan shall be prepared on the site specific induction board, identifying the following safety information:
    a. Access & egress ,
    b. Emergency Evacuation points.
    c. Amenities (Toilets, lunchroom, drinking water, temporary power etc.).
    d. First Aid Kit location.
    e. Over-head and underground hazards (power lines, sewerage / stormwater services, water and gas
       mains).
    f.     Firefighting equipment locations.
    g. Telephone numbers and location for emergencies.
    h. Bin and waste disposal methods and locations.
    i.     Crane location and lifting zone areas.
    j.     Man and materials hoist location.
    k. Site management personnel (foreman, first aid officer, safety advisor).
    l.     Adjoining public areas that could be affected by construction activities (if any).
    m. Traffic and equipment movement area plan may be a separate than the site hazard plan identifying
       items a to l (above) – refer Project Risk Assessment titled “Plant and Equipment.”
                 Delivery and storage for materials
                 Unloading and loading areas – may be the same as storage area
                 Interaction signage between plant and persons where plant need to travel around site
                 Subcontractor container storage areas
                 Plant storage areas – where required
                 Mobile crane and concrete pump set up areas




                                                                                                                Page 20 of 58

Section 21

                                                                                       Hutchinson Builders – ABN:52 009 778 330

                                      WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                     Version: 9.2



      3.4       HB Provided Plant
In relation to this project, the following items of plant shall be provided by HB for general use by employees
and subcontractors on site:

☒       All temporary fences erected on the proposed line of the construction site are to be maintained on a
        daily basis by site team members – refer to [Public Protection Controls within Section 4 for additional
        details].

☒       Signage:

          Signs will be fixed at entrances to the site, on perimeter hoardings in a number of easy to see
           locations.
          Signs fixed to fence – ensure stability of the fence panel
          Signs will include, but not be limited to, the following:
                   “Construction Site – Do Not Enter Authorized Personnel Only” signs,
                   Mandatory Safety Helmet and Safety Footwear Signs,
                   “HB” Construction Site General Signs, and
                   Directional and descriptive signs indicating the location of the site office, toilets, first aid
                    provisions, traffic management etc. as required.
☒       Construction workplace amenities to be provided in accordance with PP:04 – Construction
        Amenities for the :

          Site office’s, meeting and checked by the site team members during all on-site inspections.
☒       Generator

          Generators will be tested by a licenced electrician on a 3 monthly basis.
          Generators to be run through an earth leakage.
          Generators powering Hoist and crane are to be used exclusively for the specified plant.
☐       Compressor

          Safety clips are to be affixed and maintained for hose connections
          Equipment to be maintained and serviced as per manufacturer’s specifications.
☐       Hoist

          Hoists will be maintained and serviced in accordance with the maintenance & service schedule.
          Licenced Hoist Operators will be responsible for the operation of the Hoist at all times the
           hoist is operational.
☒       Crane (Tower or mobile)

          Crane equipment will be erected in accordance with the engineer approved Site Lift Plan;
          Safe work zones will be created and maintained for the duration of the time the crane is on
           site, with specified exclusion zones;
          Licenced Crane Operators and Dogmen will be responsible for the operation of the crane and
           hooking of all loads at all times; and


                                                                                                                   Page 21 of 58

Section 22

                                                                           Hutchinson Builders – ABN:52 009 778 330

                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                         Version: 9.2



      A monthly servicing schedule will be maintained unless the manufactures specifications
       stipulate otherwise.
☒   Forklift

      Maintenance inspection to be completed in accordance with the service and maintenance
       schedule.
      Daily prestart checks will be completed prior to the use of the plant.
      Only suitably licenced persons are to operate the plant.
☒   Scissor / boom

      Scissor / Boom will be maintained in accordance with the maintenance and service schedule.
      Daily prestart checks will be completed prior to the use of the plant.
      Only suitably licenced persons are to operate the plant.
☒   Scaffolding

      Scaffold is to be erected as per approved scaffold plan.
      Scaffold plant registration number is to be displayed at the main site access point or on the
       font entry fence.
      The scaffold handover certificate must be received prior to the scaffold being used by any
       trades. Handover certificates are also to be obtained following any alterations to the scaffold.
      Only competent licenced persons to erect / dismantle / alter scaffold.
      Scaffold to be reinspected at regular intervals not exceeding 1 month.




                                                                                                       Page 22 of 58

Section 23

                                                                              Hutchinson Builders – ABN:52 009 778 330

                                  WHSMP:01 – Work Health & Safety Management Plan
                                                                                                            Version: 9.2



4. EMERGENCY RESPONSE (MP:09)

HB have developed a comprehensive Emergency Response Procedure (ERP) currently incorporated into every
employee induction. Procedures cover the response process in the event of environmental (fire, flood,
cyclone), chemical (explosion, spills) Plant/Equipment (fire, collision) and worker related emergency
(medical, rescue from high risk work).
Precautions have been taken to reduce risk however in the event of emergency HB Emergency Response
Procedure advises all employees to handle themselves and the situation in a calm controlled manner
reinforcing personal safety and the safety and wellbeing of others as priority. All procedures instruct the
immediate contact of emergency services on ‘000’.
Each site maintains a current copy of the ERP (located in Appendix 8 of this WHSMP) with site specific
evacuation plans displayed, and emergency response equipment available in the event of any of the above
mentioned emergencies.




                                                                                                          Page 23 of 58

Section 24

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                      WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



5. RISK MANAGEMENT (MP:10)

      5.1    General Guidelines
HB has developed a comprehensive risk management process in accordance with Risk Assessment Procedure
(MP:10). Attempting to manage risk, to a level ‘As Low As Reasonably Practicable’ (ALARP). The project risk
management will be as follows;

            Project Risk Register.
            Safe Work Method Statements (SWMS) – Generic.
            Activity specific SWMS developed on site for high risk site specific tasks.
A Sample of primary Project Risk Assessment & SWMS can be located in Appendix 1 & 2 of this WHSMP:01.

      5.1.1 PRA
The Project Risk Assessment (PRA) is completed as an overall assessment of the potential risks identified for
the project prior to its commencement. The Site Management Team should look at the design risk
assessment, the scope of works and the subcontractor activities and carry out the risk assessment process.
Project risk assessment shall be completed with a consultative approach by the Site Manager, Health & Safety
Officer and Project Manager. Other stakeholders will be involved as required and where appropriate this will
be facilitated through a pre-commencement workshop. Non-relevant controls will be removed or scribed out
from the PRA. The project risk assessment will directly form Appendix 1 of the WHSMP and will be reviewed
on a 3 monthly basis.

      5.1.2 SWMS
The HB Safe Work Method Statement (SWMS) will be completed by all direct employees prior to the
commencement of the task. Subcontractors are to provide completed SWMS relevant to the contracted
works as per section 2.3 Responsibilities of All Personnel Including Sub Contractors (PP:03). The SWMS shall
be developed for specific high risk tasks that will be completed on the project. The SWMS will be reviewed
and completed in consultation with the worker or workers representative, detailing the specific steps in the
activity and any associated controls. The SWMS will be reviewed and signed off by site management prior to
commencement of the task (see MP:10). Ongoing review of both HB and subcontractor SWMS will be carried
out through the Task Observation process detailed in section 9.3


      5.1.3 Safety in Design
HB will ensure that all design work is undertaken within a structured framework of fulfilling WHS obligations
in relation to both the systematic identification of major risks and the subsequent proposal of appropriate
control measures. A formal safety in design risk assessment will be undertaken to review the design of the
project and understand the risks associated with the design integrity and the risk created by the build ability
of that design –MP:13 HB Risk Management for Design-Construct Projects.

The safety in design process may be facilitated through a workshop as detailed in MP:13. Close out of
actions/issues raised in the design risk assessment will be allocated to relevant stakeholders. Any remaining
buildability risks will be transferred to the Project Risk Register and managed as per MP:10 Risk Assessment
Procedure through site based controls and SWMS.




                                                                                                             Page 24 of 58

Section 25

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



6. STAFF INDUCTION AND TRAINING (PP:02 & MP:04)

      6.1    HB Site Specific Induction (PP:02)
HB will carry out site specific inductions for the project which will cover the following information as a
minimum:
Advise workers of HB WHS Policy Statement and its objectives and the content of HB WHSMP.
    1. Advise on site safety rules.
    2.   Identify safety and other key personnel at least including:
            Project Manager
            Site Manager
            Site Health and Safety Officer
            First Aid Officer(s)
    3. Identify and advise workers of the location of HB first aid facilities/provisions.
    4. Give details of incident/hazards and emergency reporting procedures – and that all persons are
       required to report accidents/incidents including near miss incidents to HB Site Manager/Foreman
       immediately.
    5. Give details of the project fire/emergency evacuation procedure.
    6. Identify the location of the following using a map where required:
            Firefighting equipment.
            Emergency evacuation points.
            Site amenities.
            Access points and parking areas.
            Location of phones or other communication points.
            Bins, recycling collection points, etc.
    7. Advise workers of the mandatory PPE requirements on site and the public protection requirements
       to be maintained.
    8. Advise workers of specific site hazards, traffic control issues, common plant issues etc., and of the
       following common hazards requiring actions;
            Workers are not allowed to alter, remove or move temporary services out of the way, provided
             by HB without prior approval of site management.
            Electrical leads MUST be hung on an insulated hanging hook, stand or bracket where exposed
             to damage, heat or water hazards – not wrapped around non insulated metal scaffold, pipe
             work, lift cages or other metal objects.
            Do not expose yourself or others to hazards, follow safe work methods and the correct and
             safe use of hand tools to prevent injuries.
    9.   Give details about the health and safety consultative arrangements on site.
    10. Identify key health and safety obligations of all site personnel.
    11. HB will incorporate an Environmental Induction as detailed in the Environmental Management Plan,
        with the site Health and Safety Induction.



                                                                                                             Page 25 of 58

Section 26

                                                                                             Hutchinson Builders – ABN:52 009 778 330

                                                 WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                           Version: 9.2



                   12. Provide details of HB procedures for monitoring, reviewing and responding to health and safety
                       non-compliance on site or major breaches of statutory requirements;
                           Daily walk through – checking controls implemented, tool box talks
                           HB weekly inspections – corrective action reports issued
                        Removal from site for continual unsafe work practices
                    Records

                           Completed Induction Register (HB-HSEQ-F-025) and HSE Induction Training Record Forms
                            (HB-HSEQ-F-025-A) will be maintained on file on site so that these records may be referenced
                            as required.
                           Copy of the high risk license to be attached with the Induction Form
                           Copy of current driver’s license or photographic license
              An induction booklet and Induction sticker are given out, and held by all persons attending the induction.
              Site specific inductions are VERY IMPORTANT; please follow the below set up format, to communicate the
              message of SAFETY to site workers.




                        Site Rules


                  Emergency Contacts
                       for Site


                     Company Policies
              - WHS Policy (HB-HSEQ-P-001)
              - Environmental Policy (HB-
                HSEQ-P-002)
              - Quality Policy (HB-HSEQ-P-003)




d can be ordered through company services –




                                                                                                                         Page 26 of 58

Section 27

                                                                                     Hutchinson Builders – ABN:52 009 778 330

                                     WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                   Version: 9.2



      6.2     Visitor Process
A Visitor will be required to sign the Visitors Register (HB-HSEQ-F-026) upon entry into the site. Visitors are
required to wear as a minimum PPE including – leather enclosed footwear, hard hat and high-Vis safety vest
(to Australian Standard) when on site, unless in the site office. Visitors are to remain with their guide at all
times whilst on site. Visitors will receive a brief description of the hazards on site, and will be required to sign
out of the visitor register prior to leaving the site.

      6.3     Training Matrix
A Training Matrix shall be developed for the site capturing all internal HB site workers. Ensuring all persons
working on site have been trained and assessed as competent to undertake the tasks required. Data entered
onto the Site Training Matrix (Reference Procedure MP:04 and Site Training Register - HB-HSEQ-F-031) is to
include:

             Current skills obtained.
             HB Training Modules
             Minimum requirements for each skill obtained.
             Certificates of Competency if required.
             Required training (including familiarisation training).
             Expiry dates.
All courses should be booked through the Workforce Development Team in Head Office. The Workforce
Development Team will liaise with the appropriate Registered Training Organizations (RTO’s) to organize the
most appropriate training at the required times.




                                                                                                                 Page 27 of 58

Section 28

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



7. FITNESS FOR WORK (SP:04)

HB has a Fitness for Work Policy and associated Procedure SP:04. Site personnel shall be advised of the effects
of drugs, alcohol and fatigue on their fitness for work and of the relevant HB management procedures.
This section of the WHSMP:01 covers area such as:

            Drugs and Alcohol (Refer SP:04).
            Fitness for Work (Refer SP:04).
            Smoking.

      7.1    Fatigue Management
Fatigue may be due to mental, physical or emotional reasons and affect the ability of an employee to carry
out their duties in a safe manner. Where fatigue may affect a person’s ability to work safely it must be
identified, assessed and controlled like other hazards in the workplace.
HB Employees / Contractors will be encouraged to report to the Site Manager on any occasion where
tiredness or physical condition is impacting on their ability to perform the work in a safe manner. The Project
team is to review all personnel at pre-start meetings toolbox meetings and during the working day to identify
any personnel who are displaying signs of fatigue. Reasonable rest periods shall be allowed according to the
physical demands of the work and in accordance with SP:04 Fitness for Work procedure.
Wherever possible and practicable, heavy work shall be scheduled for the cooler part of the day.
Any additional work time shall be subject to approval from the Site Manager through Project Manager in
liaising with the client and the Health & Safety Officer.
Controlling fatigue in the workplace requires cooperation between employers and employees. Preventing
fatigue is the best form of control but is not always possible due to the number of factors. Not all of these
factors are work related. The Site Manager shall regularly monitor shift lengths and resourcing to help
minimize fatigue.

      7.2    Drugs and Alcohol
HB has a zero tolerance level for drugs and alcohol. If any member of personnel returns a non-negative test
result for drugs or alcohol, their works on this project will cease immediately.
No person may enter or remain on, or in, a project area or operate any equipment if that person is:
 a)   Knowingly suffering from any physical or mental condition, to the extent that the person is prevented
      from performing their duties in an acceptable manner.
 b)   Under the influence of alcohol or drugs or unfit to work in a safe manner.
Any person who is suspected of being under the influence of alcohol must, if requested, immediately submit
themselves for testing, or voluntarily leave the work site.

      7.3    Smoking
Smoking shall be permitted within approved areas only smoking is strictly prohibited in the following areas
or circumstances:
            Inside any workplace building, including workshops and storage containers.
            Within 4 meters of any building entrance as defined by Smoking legislation.


                                                                                                             Page 28 of 58

Section 29

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                  WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



            Within the confines of any area where the processing, storage or transport of gas is
             undertaken.
            Within 100m of any flammable or combustible solid, gas or liquid (including exposed live gas
             lines).
            Within the cabin of any mobile plant (e.g. excavator, crane etc.).
            In any other area that may cause discomfort or offence to others.
Smokers shall be responsible for extinguishing cigarette butts in a responsible manner that does not create
a fire risk (including bush fires). All cigarette butts shall be disposed of in an approved waste collection
container.




                                                                                                              Page 29 of 58

Section 30

                                                                                Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                              Version: 9.2



8. CONSULTATION (MP:05 & PP:06)

The following meetings and standard documents have been developed and will be implemented on the
project to ensure compliance. HB will predominantly provide all documents in English. HB will ensure that
any workers or site visitors that have learning difficulty will be assisted to ensure understanding and
comprehension. Employers of workers who do not understand written or spoken English will be required to
provide suitable translation aids.
HB will ensure consultation / cooperation and consultation occurs with duty holders & site personnel through
the following consultative arrangements:

            Weekly HB Site Meeting
            Weekly Subcontractor Meeting
            Weekly WHS&E Committee Meeting
            Toolbox and Prestart Meetings

      8.1    Pre Start Meetings
Pre-Start Meetings shall be held prior to the commencement of work each day. These meetings shall be
attended by all personnel on site. The purpose of these meetings is to ensure the site personnel are aware
of their daily work requirements and to provide a forum where any issues relating to the job can be discussed.
Any safety issues will be recorded and used to improve site safety. These records must be handed to the
Project / Site Supervisor for use in the weekly site safety inspection. In the event of any personnel missing
the prestart meeting, they shall report to the site manager or subcontract supervisor before commencing
work to review prestart meeting minutes for that day refer Procedure PP:06 and Site Daily Prestart Meeting
Form (HB-HSEQ-F-054).
The Site Manager shall chair the meeting and will advise workers of:
            Any relevant safety alerts,
            Any issues arising from current or previous days worked,
            Changes in high risk activities,
            The current day’s workload/ manning and operational requirements,
            A weekly work schedule,
            Any other information as required.

      8.2    Tool Box meetings
Toolbox meetings will be held on a regular basis. Toolbox meetings will be short information sessions for the
Site Manager / Health & Safety Advisor and the work crew to explain and discuss any issues of the current
works, possible improvements and any safety problems that maybe foreseen and in turn avoided. Toolbox
meetings are to be used to encourage two-way communication and participation in the continuous
improvement process. Refer to Procedure PP:06 and Record of Toolbox Talk Form (HB-HSEQ-F-055).
Details of toolbox meetings shall be formally logged and held on file for future reference and evidence.
Toolbox meetings include, attendance log, topics discussed and proposed actions including responsibility and
time frames.




                                                                                                            Page 30 of 58

Section 31

                                                                                Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                              Version: 9.2



      8.3    Site Health and Safety Committee
HB shall form a Health and Safety Committee upon workers request, or if worker numbers dictate that the
committee is necessary as per legislative requirements detailed in the Act. This Committee will comprise of
elected subcontractor Health and Safety Representatives (HSRs). The election process will be handled on site
and done so by a formal nomination election process. HB procedure PP:06 Consultation Arrangements on
Site, H&S Reps, H&S Committees details how consultation will occur with HSRs over WHS&E issues at the
workplace, and documents access to information and resources that will be provided to the HSR. The site
manager and Safety Advisor will be automatic members of the committee as the nominated employer
representatives.

      8.4    Issue Resolution
Health and safety issues raised on site will be reported and escalated to the following persons/groups in
the order below, until the issue has been resolved:
            Hutchinson Builder Foreman / Subcontractor Supervisor
            HB Health & Safety Advisor
            Hutchinson Builder Site Manager / Project Manager
            Site Health and Safety Committee
            HB HSE Manager / National HSE Manager
Above parties will make reasonable efforts to achieve a timely, final and effective resolution of the health
and safety issue as outlined in PP:06 Consultative Arrangement on Site.




                                                                                                            Page 31 of 58

Section 32

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



9. AUDITS & INSPECTIONS (MP:05)

HB are committed to ensuring that all systems put in place are maintained and continually being improved
on a regular basis. HB are third party certified against AS/NZS 4801 and accredited by the Office of the Federal
Safety Commissioner (OFSC) for compliance with the FSC Scheme. Ongoing auditing including surveillance
and reaccreditation occur as required.
Regular reporting of inspections will be consistent with the HB internal procedures. All audits will identify
control measures, responsibility and timeframes and will be made available to client management upon
request. Additionally the client will also be provided access and assistance for any additional auditing
requirements.

      9.1     Safety Audits
Project HSEQ Compliance Audits or external site inspections and WHSMP reviews shall be undertaken as
prescribed by the Team Safety Manager for the project and in conjunction with Procedure MP: 05 Inspections
and Monitoring of health and Safety;

             Review WHSMP including Project Risk Assessment (not exceeding 3 months)
             HSE Audit refer to HSE / O&T Audit Checklist - HB-HSEQ-F-046-A (not exceeding 3 months)
Records (See MP:12)
             Site Inspection Checklists, Corrective Action Reports and Tool Box Talks will be maintained on
              file on site.
             Weekly Health, Safety & Environment and Corrective Action Reports will be maintained on file
              on site and a copy is to be sent to Project Manager.

      9.2     Weekly Site Safety Inspection/Daily Visual Inspection
The Health & Safety Advisor or delegated person will formally review the site safety standard on a weekly
basis. This will be done by using the Weekly Site Safety Inspection Checklist (HB-HSEQ-F-048). The Site
Manager or Safety Officer shall review the checklist and address findings accordingly. An informal daily visual
inspection shall also be undertaken and any findings addressed accordingly.

      9.3     Task Observations
Task Observations are to be used by all personnel on site to encourage an active role in fostering a safe
behavioural culture in every task undertaken.
Task Observations are to be used during active work tasks to enable personnel to review the work process in
a constructive way to identify possible improvements. The principle behind this observation is that it is not a
personal issue relating to individual performance, but an opportunity to be active in ensuring safety and
health improvements, hence the motto ‘No name, No blame’. Task Observations should be conducted by site
HSE Officer at least once a week, and Site managers are to complete task observations as required by the
HSE Project Performance Measures. The task observations are to be completed when work tasks are being
conducted in order to identify opportunities for improvement. If at risk behaviour is observed, the supervisor
must be informed and act accordingly.
Task Observation Form (HB-HSEQ-F-052) shall be used for all task observations.




                                                                                                              Page 32 of 58

Section 33

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



10. INCIDENT REPORTING AND INVESTIGATION (MP:08)

HB policy is to report and document all accidents / incidents / hazards and near misses, in accordance with
procedure MP:08, on an Incident / Accident / Hazard Report Form (HB-HSEQ-F-027-B). All information
gathered can provide an important indicator of any emerging trends or particularly hazardous items. All
significant incidences must be fully investigated with the cause identified to enable suitable actions be put in
place to prevent similar reoccurrences.
All injuries must be reported to the Health & Safety Officer and First Aid Officer immediately at the time of
occurrence. This is very important for managing injuries and minimising the impact.
The Site Manager, on completion of the investigation, must sign off accidents / incidents / hazards and near
misses on the Incident / Accident / Hazard Report Form (HB-HSEQ-F-027-B).
HB has a legal duty to investigate the circumstances of every accident and incident reported which results in
injury to personnel.

10.1 Internal Incident Reporting Process (Procedure MP:08)
HB Incident reporting process has been outlined in the following flowchart.




                                                                                                              Page 33 of 58

Section 34

                                                                                     Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                   Version: 9.2



      10.2 Investigation Process (MP:08)
 Once an accident has occurred the severity should be assessed and, if of such severity as to warrant an
 investigation, the following steps should be taken by the Site Manager and Safety Officer:

            Enter information into the Incident Report Register (HB-HSEQ-F-027).
            Refer to Incident Management & Notification Process (HB-HSEQ-F-07-A) for clarification of
             all necessary investigation steps.
            Obtain witnesses’ signed statements (HB-HSEQ-F-027C).
            Complete the Incident / Accident / Hazard Report Form (HB-HSEQ-F-027-B).



      10.3 Notification

        10.3.1 Regulator Notification

In alignment with Health & Safety Legislation events must be reported to the local regulator by fastest
possible means (i.e. phone, email or lodgement of relevant form).
Events include:
            The death of a person;
            A serious injury or illness of a person (see injury / incident classification table for full listing
             and classification of injury / illness) or
           A dangerous incident.
 Regulator contact details can be located on Incident Management & Notification Process Form HB-HSEQ-
 F-07-A).

        10.3.2 Office of the Federal Safety Commissioner Notification

HB will report the relevant incidents and injuries to the Office of the Federal Safety Commission (OFSC)
(scheme or Non-Scheme) as required under the FSC Accreditation. The following incidents will be reported
by the corporate HSE Team:
            The death of a person
            Any Lost Time Injury (LTI) or Restricted Work Injury (RWI) on projects with a value of $3
             million dollars or more.
            Any Medically Treated Injury (MTI) on a Scheme project.
 All notification to the OFSC will be completed in the required format in alignment with the OFSC Reporting
 Pack.
        10.3.3 Third Party Notification

All relevant parties’ subcontractors, workers, clients etc. will be notified of the incident in the reasonable
time frames and at various stages throughout the investigation process. Where the client requires completed
incident investigation documents these will be provided upon request or in alignment with contractual
agreements.
All notification processes are to be carried out in accordance with HB Incident / Accident Investigation &
Reporting Procedure (MP:08).


                                                                                                                 Page 34 of 58

Section 35

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



      10.4 Rehabilitation & Return to Work
The Rehabilitation and Return to Work (RRTW) process for internal employees will be conducted by the HB
RRTW Coordinator. The RRTW Coordinator will manage injury in accordance with the WorkCover approved
Rehabilitation and Return to Work Policies and Procedures. Workers Compensation for internal employees
will be applied for by the injured worker and managed by HB. Where the regulator stipulates informative
material is to be included on site.
HB Safety/Rehabilitation personnel will assist injured persons with the following:
             liaising with worker’s nominated treating doctor regarding suitable/alternate duties which are
              available at HB work sites;
             development and implementation of a HB Return to Work Plan;
             Completion of workers compensation forms

10.5 Record Keeping
Following the administration of first aid treatment a record is to be maintained on the Minor first aid register.
For all incident / injury / near miss an incident report form is to be completed and forwarded to the Project
Management Team along with the corporate HSE Team. The records of any investigation are to be
maintained for a period of not less than seven (7) years.

10.6 Health and Safety Reporting

Each month the Project Manager (or nominated person) is responsible for the completion & distribution of
the site’s Monthly Project Performance Report HB-HSEQ-F-049 Project Performance, to the Corporate
WHS&E Manager. Reports are submitted through the Team Safety Manager and are required to be submitted
by the second Friday of the next month. The report records man hours, incidents; an inspection completed
etc. and allows the HB Corporate Safety section to prepare LTIFR, TRIFR etc. statistics.




                                                                                                              Page 35 of 58

Section 36

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



11. MANAGEMENT OF CHANGE (MP:12)

The purpose of Management of Change (MOC) is to verify that changes in facilities, documentation,
personnel and operations are evaluated and managed. Management will ensure that the safety, health,
quality and environmental risks arising from these changes are controlled.
HB have identified three main degrees of change within an organisation and within a specific project. These
are as follows;
             Permanent Change - A change is considered long term and durable. Any change which is not
              categorised as a Temporary Change.
             Temporary Change - A change which has a defined lifetime and which will be removed before
              a defined date (usually no more than six months). All temporary changes must have a
              specified removal date.
             Emergency Change - The emergency change path allows the change to be implemented and
              commissioned immediately in order to address an immediate safety, operational, health,
              environmental, or product quality situation.
Resulting from the MOC process controlled documents may need alteration, controlling and reissuing which
would be managed under the HB Corporate Management Procedure OHS Records and Document
Development (MP:12). The process identified below will assist in the MOC with respect to the Operational
and resourcing issues that may be encountered on the project.
The two significant types of change that will affect the project are:
      Systems Change
A systems change includes a change in the system as a result of a defect, identified hazard, incident, accident,
environmental impact or the like that will result in a change to the systematic approach to delivery. This type
of change will not impact the program if rectified immediately.
      Operations Change
An operations change is any change to the process that will affect the operations and impact overall program.
The operations change may include resourcing issues, subcontractor deficiencies, management of key
personnel, design changes etc.
At HB all personnel will identify changes & initiate the MOC process when required. The MOC will be handled
initially by the project management team and will then be escalated to the Team Leader if a resolution cannot
be sought. The Corporate Safety Manager may also be required to assist when a systems change has the
potential to impact the entire organisation.
The change management process at HB will be managed through the use of a Corrective Action Report Form
(HB-HSEQ-F-029-A) and will be submitted through the project team and recorded on the Project CAR Register
(HB-HSEQ-F-029).
The following areas will be reviewed as part of the CAR process;

             Changes are designed so that the safety, health, environmental, and security risks remain
              acceptable. Changes are analysed for safety, health, human factors, environmental, and
              product quality impact, using methods appropriate to the hazards associated with the change.
             Changes are described in documentation that includes the reasons for the change and the
              potential impact to safety, security, human factors, health, environment, and product quality.
             Changes are communicated to employees and third parties before the employees become
              involved in operating the equipment or processes that have changes.

                                                                                                              Page 36 of 58

Section 37

                                                                     Hutchinson Builders – ABN:52 009 778 330

                        WHSMP:01 – Work Health & Safety Management Plan
                                                                                                   Version: 9.2



   When training is needed, in addition to communication of the change, it will be provided
    before an employee becomes involved in operating the change.
   Documentation that is necessary for authorizing the change will be updated and available for
    use in implementing the change.
   Changes in key personnel will be made promptly and be communicated to all of the relevant
    stakeholders.




                                                                                                 Page 37 of 58

Section 38

                                                                               Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                             Version: 9.2



12. RECORD MAINTAINANCE & RETENTION

Throughout the life of the project various documents will be required to be maintained on site. Upon
completion of the project there will be various plans, registers and forms that under law will be required to
be retained for an additional period (see Document Record Matrix HB-HSEQ-F-002).
In the event of a serious or notifiable incident occurring onsite state specific Health & Safety Regulations
require additional retention periods of the following documents:
            Incident Report
            Safe Work Method Statement associated with the works
            Induction Records
            Corrective Actions Issued
            Toolbox Talks / Pre-start meetings
            Photographs
            Permits
            Regulator reports and
            Any additional supporting evidence
All incident reports and supporting evidence are to be reported to HB Corporate Health & Safety Team in
accordance with Section 10 of the WHSMP and Corporate Management Procedure Incident / Accident
Investigation & Reporting (MP:08). All relevant documentation will be retained on file for a period not less
than 7 years following a serious or notifiable event and records will be maintained by the Team HSE Manager
and the Corporate HSE Team.




                                                                                                           Page 38 of 58

Section 39

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



13. PERSONAL SAFETY (SP:04)

      13.1 Personal Protective Equipment
HB identifies the requirements to provide Personal Protective Equipment (PPE) to direct employees. As such
HB will provide suitable PPE in alignment with Australian Standards. Employees will be instructed on how to
adequately use and personal protective equipment. PPE will be replaced on a ‘fair wear & tear’ basis when
defective/damaged or when an expiry date has been reached. Following supply and instruction it is then the
responsibility of the worker to maintain and look after their individual PPE, and inform the appropriate
people if and when equipment replacements are required.
The PPE requirement for visitors on site includes – leather enclosed footwear, hard hat and high-Vis safety
vest (to Australian standard) unless in the site office. Where necessary the site management must make
additional PPE available for use.
HB will meet the requirements through compliance with the relevant Health & Safety Regulations as detailed
below.

            Suitable and sufficient equipment for the employee’s protection
            Information and training on the correct use, maintenance and storage of PPE
            Compatible signage required
            Personal Protective Equipment issued must comply with Codes of Practice and Australian
             Standards.
All persons on site must wear the required PPE as noted in the site induction and in the site rules.
            Additional PPE to shall be worn for tasks where identified in the SWMS.

      13.2 Heat Exhaustion
Heat exhaustion is a serious illness caused by excessive exposure to heat. It is often brought on by
overexertion or profuse sweating in a hot, humid, poorly ventilated environment. Acclimatization is a factor
that needs to be considered and observed as the change in climate from project area to usual work area may
differ. During prolonged heat waves the very young and the very old are also often at risk, even if they are
not active. If heat exhaustion is recognized and treated promptly, the effects can easily be reversed.
Signs and symptoms of heat exhaustion include:

            Feeling weak, faint or dizzy with an accompanying headache or nausea.
            Cold, clammy skin with ashen pallor.
            Dry tongue and thirst.
            Severe muscle fatigue.
            Loss of appetite.
            Profuse sweating.
            Physical collapse with muscle fatigue and sometimes cramping
Under the current WHS (2011) legislation, there is no prescribed maximum or minimum temperature
specified where work at a construction site must cease. HB will manage the effects of potential heat stress
by;
            Ensuring cold water bubblers are installed on site, in working order and encourage personnel
             to use them regularly

                                                                                                             Page 39 of 58

Section 40

                                                                                Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                              Version: 9.2



            Provide clip on wide brimmed visors for hard hats
            Encourage when possible to work in shaded areas.
            Train personnel on how to prevent heat exhaustion, recognize the signs and to take regular
             breaks when physically exerting themselves.
During extreme hot weather conditions HB in conjunction with all subcontractors on site will ensure the
following is considered:
            nature of works being undertaken;
            duration of exposure to the heat;
            workers who raise safety issues as a result of working in hot weather conditions may be
             relocated to cooler shaded work areas on site (where reasonably practicable). This process will
             be undertaken in consultation with the Site HSE Committee

      13.3 UV Protection
Harmful to the skin, Ultra-violet (UV) radiation is emitted by the sun. Causing sunburn and often leading to
the development of potentially cancerous melanomas. In an effort to protect all workers HB recommend all
personnel follow the guidelines listed below:
For best protection from the sun, a combination of sun protection measures is recommended, including:
            Seeking shade.
            Wearing protective clothing that covers the arms and legs as well as the body.
            Wearing a hard hat with shade brim to protect face and neck.
            Wearing wraparound tinted safety glasses.
            Using SPF30+ or SPF 50+ broad spectrum sunscreen, this should be reapplied every 2 hours.

      13.4 Working Alone
In the event a worker is required to work alone a specific SWMS must be submitted to the Project Manager
for approval. It is essential the worker is able to operate safely and responsibly with limited infrastructure
and support in all climates.
The person must be provided with a suitable vehicle, where appropriate, and suitable equipment to work
alone (including communications and emergency equipment).
A person working alone must be competent to:

            Carry out all work activities safely without direct supervision.
            Manage events that are likely to occur when working alone.
            Follow procedures to obtain emergency assistance if required.
            Follow procedures to establish regular contact with a nominated person at 3 hour intervals,
             until they returned to site.
This is very unlikely to happen and only under extreme situations may this occur.

      13.5 Wet Weather Procedure
After periods of wet weather, HB Supervisor personnel and Subcontractor Supervisors/Representatives will
inspect all work areas prior to workers commencing / re-commencing works on site. The inspection will cover
all work areas and access ways and determine whether the areas are safe to open or whether dewatering is

                                                                                                            Page 40 of 58

Section 41

                                                                            Hutchinson Builders – ABN:52 009 778 330

                                 WHSMP:01 – Work Health & Safety Management Plan
                                                                                                          Version: 9.2



required. The status of dry work areas and access ways will be communicated to Project personnel. Workers
required undertaking dewatering activities will be supplied with appropriate PPE.




                                                                                                        Page 41 of 58

Section 42

                                                                                    Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                  Version: 9.2



14. MANUAL HANDLING

HB recognises that manual handling of loads is the largest single category of workplace injury and every effort
must be made to prevent this. Work related back pain is the most common type of manual handling injury.
Other injuries, such as those to the shoulders, neck, knees and ankles, can also result from manual handling.
HB have developed a Project Risk Assessment and Generic Safe Work Method Statement (SWMS:04 –
Manual Tasks) to identify and control risks associated with manual handling.

      14.1 Legislation
Australia’s National Standard for Manual Handling, and Code of Practice 2011 – Hazardous Manual Tasks.
Requires employers, so far as is reasonably practical, to avoid manual handling operations which involve a
risk of injury to personnel. Where it is not reasonable for manual handling to be avoided an assessment of
the operation must be carried out and the risk reduced.

      14.2 General Guidance
Manual handling is not simply lifting items. It concerns all aspects of manually manoeuvring loads, e.g.
pushing, pulling, lifting, carrying, tilting, etc. A load is anything that has to be moved, e.g. an oil drum, a box
of typing paper, a crate full of machinery, a vacuum cleaner, a tool box, etc.
Severe and sometimes permanent injuries can be caused by incorrect manual handling of materials and
loads. Some of the injuries sustained include:
             Acute or chronic muscle strain.
             Ruptured discs.
             Fractured bones.
             Damaged ligaments or tendons.
             Hernias.
             Wounds or bruises.
             Sprains and strains arising from the incorrect application and/or prolonged use of bodily
              force.
Poor posture and excessive repetition of movement can be important factors in the onset of injury. Many
handling injuries are cumulative rather than being truly attributable to any single handling incident.
When conducting the risk assessment the following guidelines apply:

             Observe all existing and proposed manual handling activities and consider whether they are
              hazardous, i.e. likely to cause injury to the individual(s) concerned with the job.
             Ensure SWMS covers required lifting and manual handling control measures.
             Follow SDS for chemical handling and movement.
Ergonomic Workstation Assessment will be completed if deemed necessary.




                                                                                                                Page 42 of 58

Section 43

                                                                               Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                             Version: 9.2



15. PERMITS TO WORK

HB utilises a Permit System to reduce the safety risks associated with specific work tasks. Specific work
permits have been designed to ensure the risks associated with performing specific work are considered and
controls implemented prior to the commencement of work. Permits are required to be completed prior to
the commencement of work and at the commencement of the works all permits must be closed out and filed
in accordance with Document Record Matrix (HB-HSEQ-F-002).
The following permits are required on HB projects:

      15.1 Isolation/ Tag and Lockout
When working in the operational area, HB must comply with the Isolation & Lock Out Permit - HB-HSEQ-F-
074.
      Out of Service tags:

An “Out of Service” tag is a notice that distinguishes appliances or equipment out of operation for repairs
and alteration or which is still being installed. While an Out of Service tag is attached to the appliance or
equipment it must not be operated. Out of service tags may be placed by any person familiar with the process
but shall only be removed by an authorized person.




      Dangers Tags
The Danger Tag is designed to give YOU personal protection where there is risk of injury to YOU from the
operation of plant.
Danger Tags are used in a number of isolation situations:
         a)     Personal Danger Tags only;
         b)     Personal Danger Tags with locks (where applicable);
         c)     Personal Danger Tags with hasps and multiple locks (where applicable).




                                                                                                           Page 43 of 58

Section 44

                                                                                   Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                 Version: 9.2



      15.2 Hot Work
Prior to the commencement of any hot work activity, a Hot Works Permit (HB-HSEQ-F-076) must be
completed by the person(s) requesting the permit. It then must be authorised by a Site Supervisor/Foreman,
or persons in control of the hot work. Whenever hot work is to be carried out in the specific SWMS shall be
completed. To ensure that the appropriate protection equipment is available and all necessary fire
precautions have been put into place. The operators shall wear the appropriate safety equipment and
protective clothing. Suitable screens shall be installed to prevent welding flashes affecting persons passing
the work area.
Prior to carry out any welding or cutting, procedure operators are required to:
             Check that all leads, hoses and fittings are in good condition,
             Check that the welder has the correct electrical tag and has been tested by a qualified
              electrician,
             Ensure that flash back arresters are fitted next to the regulators and hand pieces of the
              oxygen and acetylene bottles,
             Ensure correct PPE is used,
             All welders must have correct deadmans switch or voltage reduction device (VRD) in place.
             Electrical auxiliary outlets are to be blocked off on all welders.

      15.3 Working at Heights
All tasks involving Working at Heights require a trained and in-date qualified person to carry out the task. The
qualification must be in Working at Heights and meet HB standards as a minimum and any other qualification
required for the task. All equipment required for Working at Heights, will be used, and with current testing
and tagging proof of in-date inspections. Working at Heights Permits (HB-HSEQ-F-077) will be required and
followed for working at heights i.e. No edge protection or in boom lifts, 100% hooked up with a harness is
required.

Platform Ladders & Ladders for Access
All ladders shall be of industrial 120kg load rating as a minimum, and shall conform to all applicable Australian
Standards.

             Ladders should always be checked before use for faulty rungs or side rails and should not be
              in use if faulty. It should be tagged with an “Out of Service tag,” reported and inspected by a
              trained, qualified person.
             The ladders should be placed on level and firm footings at a 4:1 ratio (4 meters up one meter
              out), extended one meter (3 rungs) beyond the landing point, in a clearway and held by
              another person as it is secured to the structure. Access points to roofs from ladders will be
              free from crossbeams/posts.
             Mud or grease must be cleaned off boots before attempting to climb the ladder.
             A firm grip must be maintained while climbing up and down the ladder with three-point
              contact with the ladder maintained at all times.
             All tools and materials should be carried in a suitable pack with shoulder straps or be hoisted
              by rope.
             Checks must be made to determine if it is permissible to use aluminium ladders on the project
              site prior to doing so.

                                                                                                               Page 44 of 58

Section 45

                                                                                    Hutchinson Builders – ABN:52 009 778 330

                                      WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                  Version: 9.2



                Aluminium ladders must never be used while undertaking electrical work.
                Any works to be performed from ladders must be done so from a platform ladder.
                Ladders in use on mobile scaffolds will be attached to the mobile scaffold, not in the
                 permanent structure.
                Is no longer than;
                   o 6 meters for a single ladder,
                   o Extension ladder for electrical work as defined in the Electrical Act 2002 – 9.2 meters or;
                An extension ladder 7.5 meters.

      15.4 Excavation & Penetrations
Excavations must be carried out in accordance with the SWMS to ensure a safe and efficient standard for
work is followed. Excavation includes, but is not limited to, breaking into:
                 Ground                                                Tunnelling
                 Trenching                                             Vertical Earth Cuts
                 Bulk earth excavation
Before any excavation work is carried out an Excavation Permit (HB-HSEQ-F-078) must be completed and
signed off by the person(s) requesting the permit, Site Manager/Foreman or person(s) in control of the
excavation.
                Any opening or excavation exposed in the ground, wall or structure that could cause an accident
                 by person(s)/equipment falling in/through should be roped off or barricaded as soon as
                 practicable. The barrier must be maintained until the opening/excavation is closed off or
                 backfilled.
                If the opening / excavation for ground excavations only have to be left open during the hours
                 of darkness the area should be clearly identified with the use of yellow flashing light.
                Any unusual or unexpected conditions, such as underground power lines, pipes or sewers must
                 be reported immediately.

      15.5 Coring / Drilling
Coring or drilling work must be carried out in accordance with the relevant SWMS and includes any coring /
cutting work where the worker will be breaking into:

                 Walls                                                 Ceilings
                 tilt – up panels                                      Ground
                 Soffit

Before any excavation work is carried out a Coring / Cutting Permit (HB-HSEQ-F-079) must be completed
and signed off by the person(s) requesting the permit, Site Manager/Foreman or person(s) in control of the
excavation.




                                                                                                                Page 45 of 58

Section 46

                                                                                                       Hutchinson Builders – ABN:52 009 778 330

                                          WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                                          Version: 9.2




                                     Maximum duration the
  Form Number       Permit Name                                             Type of work or work environment requiring a permit
                                         permit is valid
 HB-HSEQ-F-074     Isolation &    To be enforced for the         This covers the servicing and maintenance of machines and equipment in
                   Lockout        duration of the isolation.     which the unexpected energizing, start-up of the machines or equipment,
                   Permit                                        or release of stored energy could cause injury to employees. Energy
                                                                 sources may include: electrical, mechanical, hydraulic, pneumatic,
                                                                 chemical, nuclear, thermal or other energy.
 HB-HSEQ-F-075     Confined       For the duration of the task   To be obtained for work occurring in an enclosed or partially enclosed
                   Space Permit   on the day of application      space that:
                                  ONLY.                            - Is not designed or intended to be primarily occupied by a person
                                                                   - E.g. vats, tanks, pits, pipes, ducts, flutes, chimney’s, silos, containers,
                                                                       pressure vessels, underground sewers, wet or dry wells, shafts,
                                                                       trenches, tunnels or other similar enclosed or partially enclosed
                                                                       structures.
 HB-HSEQ-F-076     Hot Works      For the duration of the task     - Flame (Welding / soldering / brazing)
                   Permit         on the day of application        - Spark or slag (grinding/ cutting/ friction tools /welding)
                                  ONLY.                            - Hot Objects (metal surface / plate etc.)
                                                                   - Other works
 HB-HSEQ-F-077     Working at     Flexibility to cover the         - For all works over 2.0 meters from the ground – working on any of
                   Heights        duration of the W@H                  the following:
                   Permit         activity. Must be reviewed                o     Scaffold / mobile scaffold / EWP / scissor lift / ladder /
                                                                                  platform ladder
                                  weekly.
 HB-HSEQ-F-078     Excavation     Flexibility to cover the         -   Bulk cut
                   Permit         duration of the excavation       -   Drilling / piling
                                  activity. Must be reviewed       -   Trenching
                                                                   -   Other
                                  weekly.
 HB-HSEQ-F-079     Coring /       For the duration of the task     -   Cutting activities
                   Cutting        on the day of application        -   Coring
                   Permit         ONLY                             -   Other


16. HIGH RISK WORK SYSTEMS

HB recognizes that there is a need for high risk work to be completed on construction projects. To meet this
requirement HB have developed SWMS for safe systems of work. Site specific SWMS are developed once
final scope and details of construction have been received. SWMS will be monitored through the completion
of Task Observations. Please refer to section 5.1.2 of this Plan for more information on SWMS requirements.
In the event of inclimate weather sites are to refer to the Bureau of Meteorology and/or relevant government
website in conjunction with Site Shut Down and Storm Preparation Checklist (HBHSEQ-F-084). In serious
weather conditions high risk work tasks should only be conducted following the completion of a relevant risk
assessment that deems the works safe to all stakeholders.
In addition to the above mentioned high risk work systems the following requirements shall also be met:

      16.1 Demolition
All Demolition works shall only be undertaken by a licensed Demolition contractor in accordance with AS
2601 (The Demolition of Structures).
Demolition work includes any work to demolish, deconstruct or dismantle a structure, or part of a structure
that is load-bearing or otherwise related to the physical integrity of the structure. Demolition work involves
hazards for which potential exposure must be controlled, including:
                falling objects, including part or all of a structure or debris
                being struck or crushed by operating mobile plant
                airborne contaminants, such as asbestos or silica.



                                                                                                                                        Page 46 of 58

Section 47

                                                                               Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                             Version: 9.2



The WHS Regulation requires that demolition work be carried out by an appropriately licensed person
conducting a business or undertaking (PCBU). The WHS Regulation also requires that certain types of
demolition work be notified to the relevant state regulator. Notification is required 5 days prior to the
commencement of demolition works.
There are other requirements in the WHS Regulation which may apply to demolition or dismantling of a
structure. For example when demolition of a structure or plant containing asbestos occurs, specific asbestos
removal notification will be required.
Our qualifications/competencies check list; Demolition of Work Structures (HB-HSEQ-066) shall be enforced
prior to demolition work, and at regular intervals throughout demolition works.

      16.2 Asbestos
All Project Management teams completing refurbishment works on existing buildings constructed before
1990’s should assume that there will be asbestos containing materials (ACM) in the existing structure. Where
teams are not sure whether a material contains asbestos assume it does and take adequate precautions. The
Project Risk Assessment (Appendix 1 of this WHSMP) is used to plan for the safe and compliant removal of
asbestos from the job site. In the event that ACM is found on site refer to the Asbestos Removal Checklist
(HB-HSEQ-F-063) and isolate the suspected area accordingly.
To ensure compliance with company procedure and legislation all sites are reminded that the following steps
should be followed to adequately prepare for the identification and removal of ACM during the construction
process;
            Completion of the PRA – ‘Asbestos Removal’ section prior to commencement on site
            Notification to the regulator 5 days prior to commencement
            If ACM is identified refer to Removal of Asbestos material Checklist - HB-HSEQ-F-063.
Ensure the following occur if ACM is identified:
            HB asbestos checklist will be completed prior to work starting.
            The asbestos removal site will be clearly defined to ensure that non-essential persons do not
             enter and to warn person that asbestos removal work is being carried out.
The Asbestos Removalist will be required to provide an Asbestos Removal Plan specific to the site that
addresses the following (as detailed in the COP - Safe Removal of Asbestos):
            Third party air monitoring and sampling will be carried out to ensure minimum health and
             safety standards for the duration of any asbestos removal work.
            All dumping receipts for asbestos products will be obtained from the Asbestos Contractor.
            The asbestos register will be updated following the asbestos removal work
            A clearance certificate will be obtained from an independent third party certifier to the
             Asbestos Contractor and forwarded to HB on completion of any asbestos removal work prior
             to re-entry to the asbestos removal area.
Where site staff identify additional training requirements in HB procedures and processes for handling
asbestos and ACM refer to Future Leaders Module (Task 6 Health & Safety, Topic 10 Asbestos Demolition &
Lead) for further guidance.




                                                                                                           Page 47 of 58

Section 48

                                                                                   Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                 Version: 9.2



      16.3 Removal of lead materials
All works involving the disturbance of lead and lead containing materials are to be performed in compliance
with HB process for removal of lead materials (see Project Risk Assessment – Appendix 1 WHSMP). Prior to
the commencement of works the necessary risk assessment is to be performed and SWMS relevant to the
task are to be submitted for site management approval.
HB Removal of Lead Materials Checklist – (HB-HSEQ-F-071) form is to be utilized throughout the works to
ensure all required steps have been addressed throughout the removal of lead from site. Specific steps
involved include:
          1. Completion of the relevant information regarding lead is documented in the Hazardous
             Substances Register (HB-HSEQ-F-040) for the relevant site;
                a. A risk assessment is to be undertaken by a competent person of all tasks involving lead
                   processes undertaken by HB’ employees. The assessment is to be done when a new lead
                   process starts at the workplace and again within 4 weeks after the process starts;
          2. The completed risk assessment is to comply with the requirements of the relevant legislation
             (e.g. Work Health and Safety Act 2011 Part 3 (QLD & NSW),- VIC OHS Regulation 2007 chapter
             4 part 4.1) and is to:
                a. Identify the lead used;
                b. Involve a review of the SDS or if the SDS is not available a review of the available
                   equivalent information and, where the lead is contained in a consumer package, a review
                   of the package’s label.
                c. Identify whether the job in the lead process is a “lead risk work” for the purposes of the
                   relevant legislation;
                d. Identify the type of atmospheric monitoring required; and the control measures needed.
Regulators require notification of removal of lead work within 7 days of the determination that the removal
work is lead related. All necessary checklists are to be completed by the Supervisor who shall also define the
methodology as well as reviewing and approving the risk assessment and SWMS specific to the task. The Site
Manager/Foreman/HSE Advisor will ensure workers are consulted through site pre-start and tool box talks
prior to all removal works. Any formal inspections, atmospheric monitoring, regulator reporting and high risk
checklist re to have records maintained for a minimum of 30 years.

      16.4 Tower Crane Selection & Positioning
All Tower Crane Selection and Positioning shall be completed after consultation with both Site Management
and the Crane Division. The Design of the crane will be completed by a RPEQ Engineer in accordance with the
Tower Crane Code of Practice, and relevant Australian Standards. The Tower Crane Selection & Positioning
Form (HB-HSEQ-F-068) will be completed with the Site Management and Crane Division and all copies will
be retained on site to be made available upon request.

      16.5 Scaffolding
All scaffolding shall only be installed, erected and dismantled by a certified scaffolder in accordance with AS
1576.4. Scaffolding shall be checked weekly (HB-HSEQ-F-048) by site management and inspected monthly
(HB-HSEQ-F-061) by a certified scaffolder utilising the relevant internal forms / checklists. No scaffolding shall
be used unless an up to date scaffold handover certificate has been issued indicating the scaffolding is safe
for use.



                                                                                                               Page 48 of 58

Section 49

                                                                                   Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                 Version: 9.2



Following the daily site prestart employees/ leading hands will be required to inspect any scaffolding prior to
commencement of work.
Any formal inspections including weekly certified scaffolder inspections and HB Scaffold High Risk Checklist
will require records.

      16.6 Tilt up & Pre-cast Panels
All lifting, erection and installation of Tilt-Up and Pre-Cast Panels are to be performed in compliance with HB
process for construction and erection of pre-cast panels and walls (see PRA – Appendix 1 WHSMP). Prior to
the commencement of works the necessary risk assessment is to be performed and SWMS relevant to the
task are to be submitted for site management approval.
HB internal forms (Construct and Erect Tilt-Up Concrete Panels - HB-HSEQ-F-062, Erection of Precast Wall
and Column Panels Checklist - HB-HSEQ-F-064) are to be utilized throughout the works to ensure all required
steps have been addressed throughout the construction and or erection of the pre-cast panels on site.
For the erection of ‘Tilt-Up Pre-Cast Panels’ checklists are to be completed by the Panel Supervisor with a
minimum qualification of Intermediate Rigger (OHSCER223A Perform Intermediate Rigging Operations or
OHSCER224A Perform Advanced Rigging Operations). The Panel Supervisor shall define the methodology as
well as review and approve the risk assessment and SWMS specific to the task. The Site
Manager/Foreman/HSE Advisor will ensure workers are consulted through site pre-start and tool box talks
prior to all lifts. Any formal inspections and high risk checklist will require records kept and made available if
required.

      16.7    Erecting Structural Steel
The erection of structural steel is to be performed in accordance with HB process for erecting structural steel
utilising the risk control methods outlined in the PRA (see Project Risk Assessment – Appendix 1 WHSMP).
Prior to the commencement of works the necessary risk assessment is to be performed and SWMS relevant
to the task are to be submitted for site management approval.
HB internal form (Erecting Steel Structures - HB-HSEQ-F-067) is to be utilized throughout the works to ensure
all required steps have been addressed for the site works.
Erection of Structural Steel checklists are to be completed by the Supervisor with a minimum qualification of
Intermediate Rigger (OHSCER223A Perform Intermediate Rigging Operations or OHSCER224A Perform
Advanced Rigging Operations) and in alignment with the relevant Codes of Practice and Australian Standards.
The Supervisor shall define the methodology as well as review and approve the risk assessment and SWMS
specific to the task. The Site Manager/Foreman/HSE Advisor will ensure workers are consulted through site
pre-start and tool box talks prior to the steel erection works. Any formal inspections and high risk checklist
will require records kept and made available if required.

      16.8 Swing Stage Placement, Erection & Dismantling
Only a competent licensed scaffolder (CPCCLSF4001A Advanced Scaffolding (SA) or OHSCER224A Perform
Advanced Rigging Operations in QLD the state required course in safe use of swing stage and scaffold is also
required) shall be permitted to carry out placement, erection or dismantling work of swinging stage scaffold.
All works involving swing stage scaffold are to be carried out in alignment with the approved methodology
and risk control methods outlined in the Project Risk Assessment (see Project Risk Assessment – Appendix 1
WHSMP).



                                                                                                               Page 49 of 58

Section 50

                                                                                    Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                  Version: 9.2



HB internal checklists (Swing Stage Placement, Erection & Dismantling HB-HSEQ-F-070) are to be utilized
throughout the process to ensure the necessary steps have been completed.
All swing stage placement, erection and dismantling works will be carried out in accordance with WHS
Regulations, Scaffolding Code of Practice and the relevant Australian Standards, in conjunction with the
Project Risk Assessment; and with the subcontractor’s relevant SWMS. With all swing stage documentation
(SWMS, checklists, logbooks, and emergency procedures) collated and maintained on site to be made
available upon request.

      16.9 Erecting, Climbing, Servicing & Dismantling of a Tower Crane
All activities associated with the erection, climbing, servicing and dismantling of a tower cranes are to be
performed under the direct instruction of an Intermediate Rigger (OHSCER223A Perform Intermediate
Rigging Operations or OHSCER224A Perform Advanced Rigging Operations). For the various tasks additional
suitably qualified trades will be required (including but not limited to boilermakers, diesel fitter and electrical
fitter).

All works are to be performed in compliance with the submitted and approved Lift Plan /s, in conjunction
with all SWMS associated to the task and in accordance with HB Project Risk Assessment (see Project Risk
Assessment – Appendix 1 WHSMP). All lift plans and safety documentation for high risk work is to be
submitted to site management and approved 1 week prior to commencement of works on site.

HB internal checklists (Erection of a Tower Crane HB-HSEQ-F-069-A, Tie Installation and Climbing of a Tower
Crane HB-HSEQ-F-069-B, Dismantling a Tower Crane HB-HSEQ-F-069-C) are to be utilized throughout the
process to ensure the necessary steps have been completed with records maintained on site and made
available when required.

For all processes the Intermediate Rigger shall define the methodology as well as review and approve the risk
assessment. Task specific SWMS are to be reviewed by all Crane crew and inductions in to the SWMS content
completed prior to their submission to HB site management. Certified engineers will be consulted at
designated intervals to inspect and sign off on the crane base and any modifications. To ensure workers are
consulted on site HB site management will advise via site pre-start and tool box talks prior to all lifts.

      16.10 Electrical
Only qualified licensed electricians shall be permitted to carry out electrical installation, commissioning and
maintenance work. Electrical workers competency and isolation qualifications are required as a minimum.
Isolation procedures shall be followed (SP:03). All Electrical Installation works will be installed in accordance
with AS 3000 Electrical Installations, AS 3012 Electrical Installations – Construction and Demolition Sites, COP
Working near Electrical Live Parts and Project Risk Assessment; along with the subcontractor’s relevant Safe
Work Method Statements. Electrical personnel will have all licenses captured during inductions and be
verified as competent to complete the allotted duties.
All electrical leads, hand tools and appliances shall be checked and tested on a quarterly basis and tagged
with the appropriate coloured inspection tag. If the inspection tag is missing or not current the appliance
should not be used, an ‘Out of Service’ tag secured to the appliance and the Project/ Site Supervisor advised.



      16.11 Electrical Tools and Equipment
Only a qualified person is permitted to undertake the testing and tagging of the portable tools and
equipment. Earth leakage protection devices (RCD) are to be provided to all circuits providing alternating

                                                                                                                Page 50 of 58

Section 51

                                                                                 Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                               Version: 9.2



current supply to portable, mobile or moveable electrical apparatus. Testing of RCD units is to occur in
alignment with state legislative requirements (QLD / NSW 3 monthly, VIC – monthly). All electrical devises
shall be plugged into a RCD unit.

      16.12 Concrete Pumping
Concrete pumps will be subject to rigorous pre-start processes prior to use on the site. The pre-start process
will identifies the registration, checks, inspections, maintenance and sign offs required designated intervals.
Operators of concrete pumps shall be licensed in accordance with regulatory requirements. Concrete pumps
are to be established and used in a manner to minimize potential risk to the worker and members of the
public. Each pipe bend and reducer shall be clearly identified and be traceable through the plant logbook.
The operators must be able to produce logbook whilst on site.
Where required traffic control shall be in place to ensure safe entry for trucks to back onto the concrete
pump.




                                                                                                             Page 51 of 58

Section 52

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



17. PLANT AND EQUIPMENT (PP:07)

HB will ensure the safety and the absence of risks to health of personnel, contractors, visitors and the general
public so far as is practical, in connection with design, purchase, installation, commissioning, operation,
maintenance, and decommissioning of plant.
HB shall provide such information, training and supervision in relation to plant safety to personnel and
contractors, as far as is practicable, to enable them to perform their work in a manner that is safe and without
risk to health.
Subcontractors will be required to provide any/ all of the information listed below prior to arriving on site.
Failure to do so may result in cancellation of the order.
To achieve the objectives of this policy, HB will:

             Develop and maintain an up-to-date Plant and Equipment Register (HB-HSEQ-F-032).
             Ensure risk assessments are completed for all plant & equipment operated at the site. Prior to
              initial use such risk assessments will be reviewed at least annually thereafter or whenever
              conditions change or a hazard is noted;
                      o After a major service or modification.
                      o Before use in an unusual operating mode.
             Keep up-to-date records for plant information, plant maintenance, plant hazards,
              manufactures specifications, statutory records and requirements.
             Provide current health and safety information to personnel and contractors using and/ or
              exposed to plant in the workplace.
             Provide training on the purchase, design, installation, operation, maintenance and disposal of
              all plant.
             Keep relevant information and personnel training records on Site training Register (HB-HSEQ-
              F-031).
             Provide appropriate procedures and training for emergencies involving plant.
             Ensure all electrical leads and portable equipment are tested and tagged for safety by a
              qualified person every 3 months for field equipment and as regulated for office equipment
              (QLD, NSW – 6 monthly, VIC – 3 monthly).
             Ensure that a Residual Current Device (RCD) governs all electrical equipment.


In addition to those items listed, the following requirements will be met;

      17.1 Mobile Plant and Equipment
All mobile plant and equipment shall be operated by competent operators who will hold appropriate licenses
or have the necessary Statement of Attainment (SOA) in a nationally recognised competency where required.
Previous experience and competence can be demonstrated by any of the following:
             Holding a previous certificate of competency or
             Holding a statement of attainment from RTO or nationally recognised course or
             Holding an industry competency card for that type of equipment or
             Completion of Subcontractor Operator Competency Declaration Form (HB-HSEQ-F-025B).


                                                                                                              Page 52 of 58

Section 53

                                                                                   Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                 Version: 9.2



 Plant & equipment will comply with HB Selection & Purchasing of Plant, Goods and Services (MP:11) and:

            Be registered if operating on gazetted public roads.
            Licensed if operating on gazetted public roads.
            Be mechanically safe in good working order, and approved for site use.
            Contain a current “Daily Inspection” log that may at any time be inspected by a client
             representative.
            Shall have the appropriate log books and comply with all statutory requirements before being
             sent to site. The approved provider will be requested to ensure full compliance covering such
             aspects as noise, machine guarding, emergency stop switches, RCD protection, colour coding
             of equipment and general conditions with relation to hazards.

      17.2 Pre Start Checks
 At the commencement of each shift all operators of plant, equipment and vehicles:

            Must complete a plant specific pre-start check appropriate to that plant or equipment.
            Must immediately place a red HB Plant sticker on any plant or equipment found to be defective.
             The sticker is to be placed in a visible spot, identifying that the plant has not been accepted for
             use on the project. The plant will be removed from site, or if it is to be fixed onsite, the plant is
             to be isolated in accordance with Isolation & Lock Out Procedure (SP:03), will be applied prior
             to any service or maintenance.
Defects that occur during the shift must be reported immediately to the Site Manager. The plant or
equipment shall be isolated (in accordance with Isolation & Lock-out Procedure (SP:03) and shall not be
operated until declared safe for use by a competent person (fitter/mechanic).
The Site Supervisor is responsible for the consultation process between the operator reporting the defect
and the competent person.

      17.3 Elevated Work Platforms
 All persons required to use a EWP must be:
            Trained, assessed and deemed competent to operate the machine.
            Be inducted and comply with SWMS.
            Hold a national high risk work license for EWP greater than 11 metres.

 Factors to be considered when using a EWP are:
            The supporting surface has enough load bearing capacity for the EWP
            The incline should not exceed the manufacturer’s recommendations
            The outriggers where equipped should be fully extended with the pads bearing evenly
            A standby person shall be present and competent to override controls if necessary
            Persons must remain in the basket at all times
            A safety harness must be worn and attached to an approved anchorage point 100% hook up
             at all times except in scissor lifts.


      17.4 Lasers

                                                                                                               Page 53 of 58

Section 54

                                                                                     Hutchinson Builders – ABN:52 009 778 330

                                     WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                   Version: 9.2



If a laser is being used, ensure that warning signs are displayed and other site personnel are warned not to
look directly into the beam of the laser. Set up laser well below or above normal eye level and ensure that
they are operated by trained personnel. Lasers should comply with AS 2211 Safety of Laser Products. A
Radiator/ Laser Safety Advisor will be appointed for the site in certain circumstances.

      17.5 Plant Using Compressed Air
Compressed air is used for air-driven tools or equipment. This air must be used with caution as misuse as
outlined below, can cause serious injury and possibly death. The following precautions will be taken at all
times;

             Never direct the stream of compressed air towards your body or towards anyone else.
             Never use compressed air to blow dust from objects or any part of your body.
             Never use water hoses as air-line hoses.
             Never indulge in horseplay with compressed air.
             Hoses, connections and securing clamps shall be checked to ensure they are not damaged,
              before putting any pressure in the line and ensure they are suitable for using compressed air.
             Lines shall be bled before disconnecting the equipment or air hoses.
             Ensure all joints in air hoses and lines are tight. Safety clips must be used on all quick release
              couplings (Chicago type) and safety chains/hose whips secured to the bull hose lines with the
              larger diameter.
             Air receivers are required to be inspected and have a current inspection certificate, which
              must be displayed prominently. Frequency of inspections corresponds with the expiry date of
              the certificate.

      17.6 Explosive Plant & Gas & Power Actuated Tools
Explosive plant/tools including Ramset and Hilti fastening tools shall be tested in accordance with the
manufacturer’s recommendations. As described in the Risk Management section of the WHSMP a SWMS will
be reviewed on site prior to the task commencing. All tools will be compliant with the relevant Australian
Standards.

      17.7 Lifting Equipment
All lifting equipment and Height Safety equipment shall be registered before being brought into use. Both
lifting equipment and height safety equipment shall be checked by trained competent persons and recorded
on the relevant registers (Lifting Gear Register - HB-HSEQ-F-038 or Height Safety Gear Register - HB-HSEQ-
F-039) before being placed into service. All lifting equipment is to be tagged and tested on a 3 month basis
in accordance with the state legislation requirements. Only trained competent persons shall use Height
Safety equipment.
High risk lifting activities requiring the crane contractor to provide lift plans include:
1.   Erection / Dismantle of Tower Cranes                 7. Lifting Large Pressure Vessels or tanks
2.   Lifting panels                                       8. Mobile Crane bigger than 100 Ton
3.   Dual Crane Lift                                      9. When exceeding 90% of the cranes Chart (WLL)
4.   Working Near Power lines                             10. Lifts over 15 ton
5.   Using a dogbox                                       11. Lifts near Trenches
6.   Lifting Bridge Beams



                                                                                                                 Page 54 of 58

Section 55

                                                                                     Hutchinson Builders – ABN:52 009 778 330

                                     WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                   Version: 9.2




Lifting will be in accordance with the lift plan and under direction of the relevant person stipulated in the
plan. If issues arise during the lift, the load will be secured safely and a solution will be identified by the team.

        17.8 Loading Platform Procedure
The following procedures/controls must be complied with for the installation/removal of loading platforms
on HB sites:

        Loading bays are to be designed into the scaffold design drawings and must be verified by a qualified
         engineer
        The installation/removal of loading platforms must be covered by a site specific SWMS
        Persons undertaking the activity of installing/removing loading platforms must have completed a
         competency course conducted by the supplier (i.e. Prestons)
        Only persons with a basic riggers ticket/intermediate scaffold ticket who have been VOC assessed as
         competent are to install/remove loading platforms
        The above qualified person must complete a Loading Platform Installation Checklist each time a
         platform is installed
        A nominated competent person is to complete a Loading Platform Daily Check Sheet for each loading
         platform installed on site.




                                                                                                                 Page 55 of 58

Section 56

                                                                                  Hutchinson Builders – ABN:52 009 778 330

                                    WHSMP:01 – Work Health & Safety Management Plan
                                                                                                                Version: 9.2



18. DANGEROUS GOODS AND HAZARDOUS SUBSTANCES (SP:01)

HB recognizes its responsibilities regarding dangerous and hazardous substances and the need to ensure that
all chemicals used on this project have been registered. This ensures they are appropriate to the tasks for
which they are required, the safest available product, and to ensure that where an element of risk is present
measures are taken to control that risk.
Further information relating to the handling / storage / training and disposal of dangerous goods and
hazardous substances on HB sites can be located in SP:01 Hazardous Substances, Dangerous Goods and lead.
It is necessary to keep appropriate copies of this information where the chemicals are stored or used. The
Dangerous Goods & Hazardous Substances Inventory should be completed at each site or work location.
HB provides details regarding the Dangerous Goods & Hazardous Substances. Some Items listed are;

               Legislation                                           Packing and labelling
               Procedures                                            Risk management
               Inventory                                             Storage and transport
               Purchasing                                            Individual risk assessments
               Safety Data Sheets (formerly MSDS)

      18.1 Safety Data Sheets
A Safety Data Sheets (SDS) register shall be maintained by HB on site. All chemicals or hazardous substance
supplied to the site will be required to have SDS sheet with the product. All hazardous materials will be
transported, handled, stored and disposed of as defined by the SDS sheets. This will include the identification
of class and correct storage and separation.
A Hazardous Substance Risk Assessment (HB-HSEQ-F-040-A) and Hazardous Substances / Dangerous Goods
Training Record (HB-HSEQ-F-040-B) form will be completed for all substances brought onto the site. A
Hazardous Substances Register (HB-HSEQ-F-040) shall be maintained at the project site office.
Personnel required to work with or handle chemicals shall be trained in the correct and safe manner to do
so.
Copies of the SDS shall be present in the location of storage and prior to use in the site office for workers to
review.




                                                                                                              Page 56 of 58

Section 57

                                                                                Hutchinson Builders – ABN:52 009 778 330

                                     WHSMP:01 – Work Health & Safety Management Plan
                                                                                                              Version: 9.2



19. SAFETY SIGNAGE

A variety of safety signage information and instruction regarding site Health and Safety matters can be
located on all HB sites. All safety signage erected shall be compliant with AS 1319:1994 Safety signs for the
occupational environment for design, colour and location.
Signage types covered in the standard are:


                    Prohibition signs.                                Emergency and First Aid signs.
                    Warning signs.                                    Fire Fighting signs.
                    Mandatory signs

      19.1 Barricades and Signage
Work areas shall be marked with suitable barricades, bunting, warning signs and lighting as deemed
necessary so as to provide a safe environment and prevent unauthorized persons entering the work area.
Work areas shall be protected in such a manner to allow for the safe access to and/or egress from that work
area for all persons working in the area. All barricading shall be established in accordance with the control
method.
Barricades are required around:

                    Excavations                                       At the edges of roofs
                    Holes or openings in floor or roof                Whenever necessary to warn
                     areas                                              people against: Falling in,
                                                                        overhead hazards
Barricading can include but are not limited to:

                    Barrier fencing mesh                              Reflective self-adhesive tape
                    Scaffold                                          Bunting
                    Industrial warning tape                           Delineation cones
                    Emergency service tape                            T bollards
                    Flagging tape                                     Barrier boards
                    Webbed barricade tape                             Guard railing
                    Reflective barrier tape                        




                                                                                                            Page 57 of 58

Section 58

                                                                                Hutchinson Builders – ABN:52 009 778 330

                                   WHSMP:01 – Work Health & Safety Management Plan
                                                                                                              Version: 9.2



20. WASTE MANAGEMENT (SEE EMS)

HB recognizes the importance of a safe Waste Management system. HB will arrange for the disposal of all
waste products regularly, safely, and in an environmentally sound manner in accordance with statutory
authorities. Disposal of waste involves the collection / storage / movement and disposal of the waste product.
HB will manage the collection and safe storage of waste on site and will utilise the servicers of approved/
licensed contractors to move and dispose of waste to a licensed facility. As the waste generator, HB will
request and store documentation (dockets) relating to the transportation and disposal of waste created at
its work sites.
HB will arrange for the disposal of all waste products regularly, safely, and in an environmentally sound
manner in accordance with statutory authorities. A waste minimization program has been initialized, and
strategies that can be used as part of the site waste management program include:

            Undertaking a review of waste generated at the contract.
            Ordering smaller quantities of products as they are required.
            Using double-sided photocopying.
            Developing a recycling program which redirects waste such as paper, cardboard, glass, plastics
             and aluminium cans.
            Composting food, garden and other organic refuse.
            Re-inking toner cartridges for printers and fax machines.
            Using non-hazardous or less hazardous chemicals where possible.
            Seeking out company’s which may be able to use the by-products and wastes.

      20.1 Housekeeping (SWMS:006) / Rubbish Removal
Wherever practicable, recyclable wastes are to be identified and segregated for recycling in preference to
ordinary waste disposal. Where a process generates large quantities of specific waste, efforts will be made
to find ways to minimize the generation of such wastes. Generation of hazardous wastes in particular is to
be minimised. Appropriate containers will be used for the segregation and collection of recyclable wastes. If
due to space restrictions, segregation is unavailable waste will be collected by a reputable waste contractor
and sorted off site. A report detailing separation of recycled waste quantities will be forwarded to the
contract administrator on a monthly basis or as requested.

      20.2 Spills and Leakages
Any accidents or incidents involving hazardous wastes must be reported to the Project/ Site Supervisor and
the Safety Manager. Any material spilled or leaked, whether on to paved surface or bare soil, must be cleaned
up immediately. The relevant SDS will be consulted for information on appropriate clean up and waste
disposal procedures. Once the initial spill has been cleaned up an assessment to any remediation shall take
place and an action plan developed. An Incident Report (HB-HSEQ-F-27-B) is to be filled out for all spill
incidents as per the environmental management plan.




                                                                                                            Page 58 of 58

Section 59

                              HUTCHINSON BUILDERS | Established 1912




71 Sea View Terrace Construction Management Plan                                     March 2016

Ref. MCU14/0084

Preamble

Hutchinson Builders has been engaged to construct a private residence on vacant land situated at 71
Seaview Tce Sunshine Beach QLD.

A MCU approval has been granted with conditions that necessitate the lodgement of a Construction
Management Plan as part of the Operational Works submission.

The Operational Works application has been submitted on behalf of the owner by Martoo Consulting
and this plan forms part of that submission.

MCU Conditions

This submission seeks to address conditions 17 of the MCU14/0084 Decision Notice

Objectives

To observe the MCU conditions

    1. To minimise the disturbance of the construction process upon neighbouring properties.
    2. To provide a consultative process for the neighbouring property occupants.

Constraints

              1. The construction works will be protracted and carried out over 24 months
              2. The site is bounded by occupied premises on two sides
              3. The site is accessed along a laneway owned in common by three other properties

This plan recognises each of these constraints and submits the following in consideration.

Plan

To mitigate potential disturbance to neighbouring premises the following will be observed:

              a. Working Hours will be restricted to Mon-Fri 7.00am to 5.30pm and Sat 7.00am to
                 1.00pm. The site will not open on public holidays.
              b. The neighbouring property owners will be provided with the builders representative
                 contact details in writing and invited to advise such of concerns or questions. The
                 letter will also explain the nature and duration of the works and request the owners
                 to provide their email addressed so that the builder can keep them apprised of the
                 works. Hutchinson Builders has been in contact with all neighbouring properties and
                 also all residents that access the private easement.
              c. Hutchinson Builders will produce and distribute a monthly newsletter to all residents
                 in the affected area to keep the residents in the loop with all activities.


M.J.Leeke                                                                                      Page 1

Section 60

                               HUTCHINSON BUILDERS | Established 1912


            d. Hutchinson Builders has agreed to email the residents of the private access-way
               directly to keep lines of communication open. All neighbouring parties have the site
               manager’s site contact details.
            e. Complaint Management Procedures

      Contact Matt Leeke Site Manager with the specific complaint
      Matt Leeke will address the concern on the spot if possible
      If not resolved a meeting will be held with all parties including Hutchinson’s management.

            f.   The following nuisances will be control and suppressed.



            Noise

                         Radios or amplified music will not be permitted on site
                         If jackhammers are required to be used they will be fitted with sound
                          attenuators if available. Compressors will also be sound attenuated.
                         The reversing of trucks along the access handle will be limited by providing
                          on-site turn-around facility whenever possible.

                 Vibration

                                 All piling methods will be non- vibratory and non-driven. Generally,
                                  a combination of systems involving CFA, Micro-piles and Screw-piles
                                  will be utilised.
                                 Vibrating earth working equipment, such as road rollers, will not be
                                  used. Road base and earth will, where needed, be consolidated
                                  using a sheep’s- foot style compactor.
                                 Vibration monitoring stations will be established prior to the
                                  commencement of the project.
                                 A dilapidation survey of the neighbouring houses will be undertaken
                                  prior to the commencement of the project.

                 Dust

                                 Cutting and drilling of concrete will, whenever possible, be done
                                  ‘wet’.
                                 Stockpiling of soil on site will be kept to a minimum and covered
                                  when necessary.

                 Odours and Exhaust

                              
                              Any motorised plant that produces exhaust fumes will be located
                              away from the neighbouring property boundaries.
            g. Workers Induction



M.J.Leeke                                                                                        Page 2

Section 61

                          HUTCHINSON BUILDERS | Established 1912


                             Before commencing each worker will be inducted to site in
                              accordance with the builder’s internal procedure and workplace
                              law. Part of the process will include a signed acceptance by the
                              worker of the site rules. The site rules will include a summary of the
                              Construction Management Plan and Traffic Management Plan.



Attachments

              Site Plan with Loading Areas




M.J.Leeke                                                                                    Page 3

Section 62

                              HUTCHINSON BUILDERS | Established 1912




71 Sea View Terrace Construction Management Plan                                     March 2016

Ref. MCU14/0084

Preamble

Hutchinson Builders has been engaged to construct a private residence on vacant land situated at 71
Seaview Tce Sunshine Beach QLD.

A MCU approval has been granted with conditions that necessitate the lodgement of a Construction
Management Plan as part of the Operational Works submission.

The Operational Works application has been submitted on behalf of the owner by Martoo Consulting
and this plan forms part of that submission.

MCU Conditions

This submission seeks to address conditions 17 of the MCU14/0084 Decision Notice

Objectives

To observe the MCU conditions

    1. To minimise the disturbance of the construction process upon neighbouring properties.
    2. To provide a consultative process for the neighbouring property occupants.

Constraints

              1. The construction works will be protracted and carried out over 24 months
              2. The site is bounded by occupied premises on two sides
              3. The site is accessed along a laneway owned in common by three other properties

This plan recognises each of these constraints and submits the following in consideration.

Plan

To mitigate potential disturbance to neighbouring premises the following will be observed:

              a. Working Hours will be restricted to Mon-Fri 7.00am to 5.30pm and Sat 7.00am to
                 1.00pm. The site will not open on public holidays.
              b. The neighbouring property owners will be provided with the builders representative
                 contact details in writing and invited to advise such of concerns or questions. The
                 letter will also explain the nature and duration of the works and request the owners
                 to provide their email addressed so that the builder can keep them apprised of the
                 works.
              c. The following nuisances will be control and suppressed.




M.J.Leeke                                                                                     Page 1

Section 63

                              HUTCHINSON BUILDERS | Established 1912


            Noise

                        Radios or amplified music will not be permitted on site
                        If jackhammers are required to be used they will be fitted with sound
                         attenuators if available. Compressors will also be sound attenuated.
                        The reversing of trucks along the access handle will be limited by providing
                         on-site turn-around facility whenever possible.

                Vibration

                                All piling methods will be non- vibratory and non-driven. Generally,
                                 a combination of systems involving CFA, Micro-piles and Screw-piles
                                 will be utilised.
                                Vibrating earth working equipment, such as road rollers, will not be
                                 used. Road base and earth will, where needed, be consolidated
                                 using a sheep’s- foot style compactor.
                                Vibration monitoring stations will be established prior to the
                                 commencement of the project.
                                A dilapidation survey of the neighbouring houses will be undertaken
                                 prior to the commencement of the project.

                Dust

                                Cutting and drilling of concrete will, whenever possible, be done
                                 ‘wet’.
                                Stockpiling of soil on site will be kept to a minimum and covered
                                 when necessary.

                Odours and Exhaust

                             Any motorised plant that produces exhaust fumes will be located
                              away from the neighbouring property boundaries.
            d. Workers Induction
                           Before commencing each worker will be inducted to site in
                              accordance with the builder’s internal procedure and workplace
                              law. Part of the process will include a signed acceptance by the
                              worker of the site rules. The site rules will include a summary of the
                              Construction Management Plan and Traffic Management Plan.



Attachments

                Site Plan with Loading Areas




M.J.Leeke                                                                                       Page 2

Section 64

HUTCHINSON BUILDERS | established 1912

Sea View Terrace Traffic Management Plan March 2016
Ref. MCU14/0084
Preamble

Hutchinson Builders has been engaged to construct a private residence on vacant land situated at 71
Seaview Tce. Sunshine Beach QLD.

A MCU approval has been granted with conditions that necessitate the lodgement of a Traffic and
Pedestrian Management Plan as part of the Operational Works submission.

The Operational Works application has been submitted on behalf of the owner by Martoo Consulting
and this plan forms part of that submission.

MCU Conditions

This submission seeks to address conditions 18-19 of the MCU14/0084 Decision Notice
A) Objectives

To observe the MCU conditions

1. To minimise the impact the movement of traffic to and from the worksite will have on the
premise occupants of Seaview Tce.

2. To protect the safety of occupants and pedestrians on the street and footpath of Seaview
Tce.

3. To ensure that access is maintained to the residences of Seaview Tce and to the worksite.

4. To reduce the incidence of compliant to the local government authority.

B) Constraints

1. Roadway width: Seaview Tce. between Macannaly Dve and the cul-de-sac, allows for
one street car parking on the western side of the street only. The distance between a
parked car and the edge of the asphalt seal is less than 3 metres, with the road reserve
sloping away from the roadway edge.

2. Other building works: Construction work is current in this section of the street. Delivery
trucks are at times unloaded from the street. This prevents passageway of vehicles in
and out of Seaview Tce. Similar renovation and new construction work can be expected
over the duration of the building programme.

3. The site is situated at the termination of a narrow access handle that does not provide
for the parking of workers vehicles. The site itself provides little opportunity for site
accommodation, storage of materials.

This plan recognises each of these constraints and submits the following in consideration.

(see over page}

es

MJ.Leeke Page 1

Section 65

HUTCHINSON BUILDERS | established 1912

C) Plan Overview per attachments

A MUTCD compliant Traffic & Pedestrian Plan for two phases of construction

Proposed route for heavy vehicles with holding areas designated

Proposed facility for bus parking and traffic control personnel amenities

Proposed facility for transport, day to day car parking, material lay down, accommodation
and overnight bus parking

5. Provision for loading and unloading of vehicles within the site

PYNEP

D) Plan Proposal

The applicant acknowledges the MCU prohibition of workers parking their cars in the streets
surrounding the site. It proposes to manage this by the following:

1, Establishment of a remote compound and car park on suitable road reserve. (See Off Site
Parking Plan) The location and suitability of the site has been arrived at in consultation with
the council's technical officer, Martin Sergus. The compound will serve to alleviate
congestion in Seaview Tce resulting from material deliveries by semi- trailer. It will also
provide lunch and toilet facilities.

2. Asmall bus will transport workers to and from the compound and to site.

3. The bus will be parked in Seaview Tce on road reserve during the day. The location and
suitability of the parking area has been arrived at in consultation with Martin Sergus. (See
Bus Parking Plan) Outside of working hours the bus will be parked at the remote compound.

The applicant acknowledges that passageway along end the section of Seaview Tce. is constricted
due to the narrowness of the road, permitted car parking along the western side, and lack of
trafficable verge. The constriction is such that an ill-parked car will prevent truck access. The
applicant proposes to manage this by:

1. 1 Traffic contro! in accordance with the MUTCD compliant Traffic & Pedestrian Plan
attached.

2. Demarcation of the street parking from the carriageway by means of line marking
and signage.

E) Attachments

Heavy Vehicle Route & Holding Plan
Compound & Off Site Parking Plan

Bus Route Plan

Daytime Bus Parking Plan

MUTCD compliant Traffic & Pedestrian Plan

NN rr

M.].Leeke Page 2

Section 66

 CTM2059-2 traffic CTM2059-1 long
control short term V1.pdf
                    term parking V1.pdf




From: Pariss Trim [mailto:[email protected]]
Sent: Monday, 18 July 2016 10:41 AM
To: Matt Leeke; Design
Cc: Michael Michell; Jarod Dingle; Damian Hasthorpe
Subject: RE: Seaview Tce

Hello Matt,

Please find attached amended plans as requested.

If there is anything else that you require please let me know.

Thanks

--
Kind Regards
Pariss Trim
Assistant Manager

P 07 3821 4522 F 3806 0944
49 Chetwynd St, Loganholme QLD 4129
www.civforce.com.au




Please note that under the seven day window agreement with DTMR and Local Authorities we require a minimum of 7-
10 full business days to process all traffic control permit applications. The seven full business days commences on
receipt of all required information. Please ensure you allow sufficient time for your initial application prior to the
proposed closures.

Section 67

From: Matt Leeke [mailto:[email protected]]
Sent: Monday, 18 July 2016 8:43 AM
To: Design <[email protected]>
Cc: Pariss Trim <[email protected]>; Michael Michell
<[email protected]>; Jarod Dingle <[email protected]>
Subject: RE: Seaview Tce

Hello Christopher,
I do not disagree with your assessment of the conditions or difficulties involved.

A parked car leaves about 3m of roadway for the trucks, but the council’s decision has given us little
alternative but to comply with their requirements.

Furthermore, my enquiries to them has left me with little confidence they will relax the conditions if
we go through the long process of appeal.

What I am asking you is if you will amend the TGS on the points they have listed for us.


Regards,

           Matt Leeke
       Construction Manager

HUTCHINSON BUILDERS | Established 1912

T 07 5451 9777 | F 07 5443 1922 | M 0414691314
A LEVEL 1/1 BEACH RD, MAROOCHYDORE QLD 4558
P PO BOX 3028, MAROOCHYDORE QLD 4558




From: Design [mailto:[email protected]]
Sent: Friday, 15 July 2016 2:52 PM
To: Matt Leeke
Cc: Pariss Trim
Subject: RE: Seaview Tce

Hi Matt.

I’ve had a quick look at councils request.

The reasoning to not allowing parking along the road is we measure the road width to be approx.
3.5- 4.5 meters wide.( total available room )
I believe that this would leave insufficient room for construction equipment to pass a parked vehicle.
(attached image)


Maintaining traffic flow is the underlying reason for a no parking precinct during work hours. These
could be reduced to only occur when trucks are using the roadway, ie if there is restrictions to the
hours trucks can use this road. We could reduce the no parking to 9am-3pm ( within school hours).

Section 68

Stop slow operations of the street won’t fix the width problem in my opinion, a detour isn’t possible,
and two way traffic is problematic in narrow streets, so exclusion was the only option left for parked
cars.

Re pedestrians.
Their appears to be very limited access to pedestrians along one side of the road, and nil on the
other.
Maintaining access along one side isn’t an issue as I can’t see how this could be affected.
There will be some restrictions at the works end, this being managed by the traffic controller.
Instructions can be given to staff to give pedestrians priority to cross the road at this location if
required.

I’m unsure of where trucks would park on this street as it appears that any parking would in effect
block the street. I was of the understanding that their was an off site parking area. ( from memory).

I can add these clauses to the TGS but after a risk assessment of the road, I don’t believe what’s
being asked for is possible and still provide a safe corridor for work vehicles and residents.



Kind Regards
Christopher Thomas

P 07 3821 4522 F 3806 0944
49 Chetwynd St, Loganholme QLD 4129
www.civforce.com.au




Please note that under the seven day window agreement with DTMR and Local Authorities we require a minimum of 7-
10 full business days to process all traffic control permit applications. The seven full business days commences on
receipt of all required information. Please ensure you allow sufficient time for your initial application prior to the
proposed closures.

Section 69

                                                                                                                                                                                                                                                                                                                                                                www.invarion.com



 RECORDS:                                                                                         Speed compliance through work site: Approx. % of compliance = _________ Comments;
Set up: start time:                         finish time:                Date:
Pack up: start time                         finish time:                Date:                     Alterations & or changes to plan (give reasons why?):
Sign check times: 1-            2-            3-           4-      5-           6-                Approved by: _________________                                                                                                                                               15m




                                                                                                                                                                                                                                                                                                                                   workd
                                                                                                                                                                                                                                                                                                                                     6pm
                                                                                                                                                                                                                                                                                                                                      6am-
                                                                                                                                                                                                                                                                                                                                         ays
TGS effectiveness and/or suggested improvements:




                                                                                                                                                                                                                                                                                                                                  workd
                                                                                                                                                                                                                                                                                                                                    6pm
                                                                                                                                                                                                                                                                                                                                     6am-
                                                                                                                                                                                                                                                                                                                                        ays
                                                                                                                                                                                                                                                                                                   ays
                                                                                                                                                                                                                                                                                                 6am-
                                                                                                                                            Please email plans back [email protected] for evaluation purposes.




                                                                                                                                                                                                                                                                                              workdm
                                                                                                                                                                                                                                                                                                6p




                                                                                                                                                                                                                                                                                                                            workd
                                                                                                                                                                                                                                                                                                                              6pm
                                                                                                                                                                                                                                                                                                                               6am-
                                                                                                                                                                                                                                                                                                                                  ays
                                                                                                                                                                                        w Tce
                                                                                                                                                                                                         - Ensure any pedestrian walkways (existing ) are preserved and maintained.
                                                                                                                                                                                                         - No queuing of trucks on any residential street prior to 7am.




                                                                                                                                                                                      Seavie
                                                                                                                                                                                                         - All trucks to turn engines off when parked.
                                                                                                                                                                                                         - Street parking for residents shall be maintained at all times unless with
                                                                                                                                                                                                           prior arrangement and approval.
                                                                                                  Mc
                                                                                                       An
                                                                                                             all
                                                                                                                 yD
                                                                                                                        r
                                                                                                                                                    ROA
                                                                                                                                                        DW
                                                                                                                                                     AHE ORK
                                                                                                                                                         AD

                                                                                                                                                                                                    K        R
                                                                                                                                                                                                        D WO
                                                                                                                                                                                                     ROA ND
                                                                                                                                                                                                        E




                                                                                                                                                                                                                                                                                     w Tce
                                                                                                                                                                                                                                                                                Seavie
    NOTES:
    - For worker safety, 40 km/h zone length is specified as 1 km maximum. There is a requirement for workers to be visible.
    Table 4.7 MUTCD 2014
    - Where workers are within 1.2m of travel path, a 40km/h zone shall be implimented.
    - Residential and business property access shall be maintained.
    - Lane width. 60km/h or less = 3.0m 70=90km/h = 3.2m 100+ = 3.4m
    - Edge Clearance - Clearance between edge of traffic lane to line of traffic cones, bollards or barrier system.
      (i) Posted speed limit during roadwork's up to 60km/h = 0.5m
      (ii) posted speed limit during roadwork's above 60km/h = 1.0m                                                                                                                                     Current "no parking" yellow lines marked on road
    Ensure all relevant Permits and these plans are onsite and can be produced upon request by an authorized person.
    - Cone spacing; Taper - Traffic Controller at 6m
                               - Lateral shift at 6m
                               - Merge at 6m                                                                                                                                                            Work times parking restriction                                               Version Date             Description
                                                                                                                                                                                                        Stated as 6am to 6pm but will represent actual work hours
                                                                                                                                                                                          6am-

                      Closure - Lane at 12m                                                                                                                                                6pm
                                                                                                                                                                                         workdays


                               - Shoulder at 12m                                                                                                                                                                                                                                      0          29-03-2016   Initial Drawing
    - A Traffic Management Level 2 is responsible for installing, maintaining and removing traffic
                                                                                                                                                                                                                                                                                             18-07-16               Amendment

                                                                                                                                                                                                                                                                                                                                                             CTM2059-1
    management devices in accordance with this TGS.                                                                                                                                                                                                                                   1
    - Where the TGS includes changes to regulatory signs or devices, a Sign Usage Checklist is to be completed, signed
    and a copy retained by the client.
                                                                                                                                                                                                                                                                                      2
    - Any existing signs that conflict with the traffic control plan shall be removed or covered during construction. All signs                                                                                                                                                       3
    that are removed shall be delivered to a storage site designated by the client.
    - Signs such as symbolic workers signs and speed limits, introduced due to reduced clearances to workers, should                                                                                                                                                                  4
    be covered or removed during periods when workers are no longer on site.
    - Workers Symbolic and traffic Controller signs to be covered when workers and Traffic Controllers are not in attendance.                                                                                                                                                         5

                       Notes                                                                                                                                                                                                                                        Issue Date: 29-03-16                              LEGEND:
         N             1. Ensure TGS has been approved.                                     8. Daily inspections to be completed after setup,
                                                                                                                                                                                                         Client: Hutchinson Builders                                                                                                                                Traffic control ute
                                                                                                                                                                                                                                                                    Start Date: TBA                                                            Work Area
                       2. Plan your emergency escape route & document on the pre-start. during closure & upon completion of pack up                                                                      Site Contact: Matt Leeke - Construction Manager
                                                                                            9. Signs to be clean & legible                                                                                                                                                                                                                     Cones
W                E     3. An accredited traffic controller must not contravene the Traffic 10. Existing signs & traffic control devices which                                                            Working Hours: All                                         Order No: CTM2059                                                                               TMA
                       Controller Accreditation Scheme Approved Procedure (TCASAP) & are inappropriate to, or conflict with, the temporary                                                                                                                                                                                                     Buffer zone
                       must direct traffic in a way stated in both the Approved Procedure work site situation shall be fully covered or removed.                                                         Work Activity: Construction                                 Long/Short Term: Long                                                     Footpath             Traffic Controller
         S
                       & the Manual of Uniform Traffic Control Devices. Breaks shall be                                                                                                                  Job Location: Seaview Tc Sunshine Coast                     Day / Night: All                                                          Driveway
     Print in          taken as specified in TCASAP.                                                                                                                                                     Road Configuration: 2 way                                                                                                                                  Police officer
                       4. Ensure a location risk assessment is undertaken prior to ALL                                                                        All Signage and Equipment is in accordance
    A3 ONLY                                                                                                                                                   with Queensland MUTCD Part 3 May 2014      Drawing Number: CTM2059-1
                       traffic control setups                                                                                                                                                                                                                                                                                                                       Barrier Board
 NOT                   5. No on site changes are allowed unless approved by & signed                                                                          (Sixth Issue including Amdt.1)             Traffic Method: Parking Restrictions - long term           Open/Built up: Built Up
                       off by a Level 3 Officer                                                                                                              Drawn By: Christopher Thomas                 Licence Number: Lvl 3 -   ;Lvl 4 -2055
  TO                   6. Ensure you maintain a safe working distance from traffic                                                                           Approved By: Pariss Trimm                    Licence Number: Lvl 3 -   ; Lvl 4 - 21598        Date:    Signed:
                                                                                                                                                                                                                                                                                                                      Signs shall be duplicated on the right hand side
                                                                                                                                                                                                                                                                                                                      of a one-way roadway, multi lane where practicable.
SCALE                  7. Remain aware of traffic conditions and maintain line of sight                                                                       Approved By:                                Licence Number: Lvl 3 -   ; Lvl 4 -              Date:    Signed:

Section 70

 RECORDS:                                                                                                        Speed compliance through work site: Approx. % of compliance = _________ Comments;                                                                                                                                         www.invarion.com
Set up: start time:                         finish time:                          Date:
Pack up: start time                         finish time:                          Date:                          Alterations & or changes to plan (give reasons why?):
Sign check times: 1-            2-            3-         4-                  5-            6-                    Approved by: _________________
TGS effectiveness and/or suggested improvements:


                     Version Date                 Description                                                                                                                               Joins below
                       0        29-03-2016        Initial Drawing
                                                                                                                                                                                                                                                                       30m
                             18-07-16                  Amendment

                                                                                           CTM2059-2
                       1
                      2
                      3




                                                                                                                                                                                w Tce
                      4
                      5
                                                                                                                                                                                                                                                                                     PREPA
                                                                                                                                                                                                                                                                                             RE




                                                                                                                                                                              Seavie
                                                                                                                                                                                                                                                                                       TO
                                                                                                                                                                                                                                                                                      STOP
                                                                                                                                                                                                                                                                       DO NO
                                                                                                                                                                                                                                                                            T OVE
                                                                                                                                                                                                                                                                                     RTAKE

                                                                                                                                                                                                                                                             10-15m
                                                                                                  Mc
                                                                                                       An
                                                                                                           all
                                                                                                               yD
                                                                                                                     r                         ROA
                                                                                                                                                   DW
                                                                                                                                                AHE ORK
                                                                                                                                                    AD                                                                                                                    40                      FELY
                                                                                                                                                                                                                                                                RED                                    E SA
                                                                                                                                                                                                                                                                   UCE                                     DRIV
                                                                                                                                                                                        K        R                                                                       SPE
                                                                                                                                                                                            D WO                                                                               ED
                                                                                                                                                                                         ROA ND
                                                                                                                                                                                            E
                                                                                                                                                                                                                                                                                                  50




                                                                                                                                                                                                                                                                                    w Tce
                                                                                                                                                                                                                                                                               Seavie
                                                                                                                                                                            - Ensure any pedestrian walkways (existing ) are preserved and maintained.
                                                                                                                                                                            - No queuing of trucks on any residential street prior to 7am.
                                                                                                                                                                            - All trucks to turn engines off when parked.
                                                                                                                                                                            - Street parking for residents shall be maintained at all times unless with
                                                                                                                                                                              prior arrangement and approval.

     NOTES:
     - For worker safety, 40 km/h zone length is specified as 1 km maximum. There is a requirement for workers to be visible.
     Table 4.7 MUTCD 2014
     - Where workers are within 1.2m of travel path, a 40km/h zone shall be implimented.
     - Residential and business property access shall be maintained.
     - Lane width. 60km/h or less = 3.0m 70=90km/h = 3.2m 100+ = 3.4m
     - Edge Clearance - Clearance between edge of traffic lane to line of traffic cones, bollards or barrier system.
       (i) Posted speed limit during roadwork's up to 60km/h = 0.5m
       (ii) posted speed limit during roadwork's above 60km/h = 1.0m
     Ensure all relevant Permits and these plans are onsite and can be produced upon request by an authorized person.
     - Cone spacing; Taper - Traffic Controller at 6m
                                - Lateral shift at 6m
                                - Merge at 6m
                       Closure - Lane at 12m
                                - Shoulder at 12m
     - A Traffic Management Level 2 is responsible for installing, maintaining and removing traffic
     management devices in accordance with this TGS.
     - Where the TGS includes changes to regulatory signs or devices, a Sign Usage Checklist is to be completed, signed
     and a copy retained by the client.
     - Any existing signs that conflict with the traffic control plan shall be removed or covered during construction. All signs
     that are removed shall be delivered to a storage site designated by the client.
     - Signs such as symbolic workers signs and speed limits, introduced due to reduced clearances to workers, should
     be covered or removed during periods when workers are no longer on site.
     - Workers Symbolic and traffic Controller signs to be covered when workers and Traffic Controllers are not in attendance.
                                                                                                                                                                                                                                               Joins above
                       Notes                                                                                                                                                                                                                                 Issue Date: 29-03-16                             LEGEND:
          N            1. Ensure TGS has been approved.                                     8. Daily inspections to be completed after setup,
                                                                                                                                                                                                     Client: Hutchinson Builders                                                                                                                  Traffic control ute
                                                                                                                                                                                                                                                             Start Date: TBA                                        Work Area
                       2. Plan your emergency escape route & document on the pre-start. during closure & upon completion of pack up                                                                  Site Contact: Matt Leeke - Construction Manager
                                                                                            9. Signs to be clean & legible                                                                                                                                                                                          Cones
 W               E     3. An accredited traffic controller must not contravene the Traffic 10. Existing signs & traffic control devices which                                                        Working Hours: All                                      Order No: CTM2059                                                                    TMA
                       Controller Accreditation Scheme Approved Procedure (TCASAP) & are inappropriate to, or conflict with, the temporary                                                                                                                                                                          Buffer zone
                       must direct traffic in a way stated in both the Approved Procedure work site situation shall be fully covered or removed.                                                     Work Activity: Construction                              Long/Short Term: Short                                Footpath                      Traffic Controller
          S
                       & the Manual of Uniform Traffic Control Devices. Breaks shall be                                                                                                              Job Location: Seaview Tc Sunshine Coast                  Day / Night: All                                      Driveway
      Print in         taken as specified in TCASAP.                                                                                                                                                 Road Configuration: 2 way                                                                                                                    Police officer
                       4. Ensure a location risk assessment is undertaken prior to ALL                                                                    All Signage and Equipment is in accordance
     A3 ONLY                                                                                                                                              with Queensland MUTCD Part 3 May 2014      Drawing Number: CTM2059-2
                       traffic control setups                                                                                                                                                                                                                                                                                                     Barrier Board
   NOT                 5. No on site changes are allowed unless approved by & signed                                                                      (Sixth Issue including Amdt.1)             Traffic Method: Short term                              Open/Built up: Built Up
                       off by a Level 3 Officer                                                                                                          Drawn By: Christopher Thomas           Licence Number: Lvl 3 -   ;Lvl 4 -2055
    TO                 6. Ensure you maintain a safe working distance from traffic                                                                       Approved By: Pariss Trimm              Licence Number: Lvl 3 -   ; Lvl 4 - 21598     Date:          Signed:
                                                                                                                                                                                                                                                                                                              Signs shall be duplicated on the right hand side
                                                                                                                                                                                                                                                                                                              of a one-way roadway, multi lane where practicable.
  SCALE                7. Remain aware of traffic conditions and maintain line of sight                                                                  Approved By:                           Licence Number: Lvl 3 -   ; Lvl 4 -           Date:          Signed:

Section 71

                                                                                                                                                                         Site and Compound
                                                       Bus Route
Map Legend
Property Mapping                                             Site 71 Seaview Tce
    Openspace
       BEACH AND DUNAL SYSTEM
       ENVIRONMENTAL RESERVE
       INVESTIGATE
       LANDSCAPE & AMENITY
       NATURAL AMENITY RESERVE
       RECREATION PARK
       RIPARIAN TRACT                                 Route taken by site bus
       SPORTS GROUND/PARK
                                                      between proposed car
       UTILITY
   StreetView_Link
                                                      park location and site
   NoosaLGA_2013




Compound and Site Car
Park Facility




                                                                                                                                                                            11 February 2016
                                 0m   200 m   400 m             While every care is taken to ensure the accuracy of this product, neither the Noosa Council nor the State of Queensland makes
                                                                any representations or warranties about its accuracy, reliability, completeness for any particular purpose and disclaims all
                                                                responsibility and all liability (including without limitation, liability in negligence) for all expenses, loses, damages and costs that
                                                                may occur as a result of the product being inaccurate or incomplete in any way or for any reason.

Section 72

                                                                                                                                                                                                        Compound

Map Legend
Transport Mapping
   JettyPontoon
                                      Compound: 20m x 15m
   BoatRamps
    PathwaysExisting                  hardstand with site shed, toilet
       Beach access                   and overnight bus parking.
       Boardwalk                      Car Park: Facility for 20
       Crossing Controlled
                                      vehicles during work hours
       Crossing Pedestrian
       Crossing Uncontrolled
       Deck
       Footbridge
       Footpath
       Pathway
       Ramp
       Roadbridge path
       Stairway
                                                               Proposed Compound
      Underpass
    OnRoadBikeRoutesExisting
                                                               Car Parking
       BAZ
       Cycle bus lane
       Cycle lane
       Cycle parking lane
       Green treatment
       Greenlink
       Intersection
       Intersection signalised
       Mixed traffic street
       Roundabout
       Sealed shoulder
       Shared zone
   TransLinkStops
    TransLinkBusRoutes
       620
       622
       626 East
       626 West                                                                                                                                                                            02 February 2016
       627                       0m       100 m      200 m                     While every care is taken to ensure the accuracy of this product, neither the Noosa Council nor the State of Queensland makes
                                                                               any representations or warranties about its accuracy, reliability, completeness for any particular purpose and disclaims all
       628                                                                     responsibility and all liability (including without limitation, liability in negligence) for all expenses, loses, damages and costs that
       629                                                                     may occur as a result of the product being inaccurate or incomplete in any way or for any reason.

       630
       631
       632

Section 73

                                    32
                               153°06'48".547
                                                                                   34                                                 36
                                                                                                                                  153°06'50"
                                                                                                                                                                                             38         153°06'51".056




          26°23'49".084                                                                                                                                                                                                   26°23'49".084
                                                                                                                   4
                           A
                           1                                                                                                           RP189884
                                 RP197117
                                 RP179371
                                                                 FH
                                                                 EA
  34                                               9942m²
                                                   465m²                                                                                                                                                                                34

                            70
                          RP81810                                                                                                                               FH
                                 FH

                                  531m²
             71                                                                                                              3317m²
   Road Reserve
  32
          26°23'50"
                                                                                                                         PATH
                                                                                                              Small Shed for TC
                                                                                                                                                                                                                             26°23'50"
                                                                                                                                                                                                                                        32
          RP81810                                                                                                            WAY
     3-4m Property
            FHto edge
     Boundary                                                                                                    69
     of Asphalt                                                                                                 RP81810                                                 Vacant Lot
                                                                  ACE




           531m²
                                                                TERR




                                                                                                                                                                        51
                     72                                                                              FH                                                               RP81810
                                                                IEW




                   RP81810
                                                                                            Bus Parking Work Hours
                                                            SEAV




                          FH
  7080                                                                                                                                                                                                                          7080
           30                                                                                                                                                                                                                           30
                                                                                                                              574m²
                  531m²
                                                                                                   68
                                                                                                    RP81810
                                                                                                                                                                       FH
                                                                                                           FH

    7080
            28 0 m N                                                                                                                                                                                                                    28
                                                                                                                             544m²
                                                                                         67
                                                                                                                                                                                                         ROAD




                                                                                           RP81810

                                                                                                    FH                                                    9497m²
          26°23'51".751                                                                                                                                                                                                   26°23'51".751




                                                                                                          556m²
                               153°06'48".547                                                                                     153°06'50"                                                            153°06'51".056
                                511     0m
                                    32         E                                   34                                                  36                                                    38



                                                        0                     10                     20                         30                         40                          50
STANDARD MAP NUMBER
9545-33112                                                  HORIZONTAL DATUM:GDA94      ZONE:56                SCALE 1 : 500
                                                                                                                                                                                            m
                                                                                                                                                                                                    SmartMap
                                                                                                                                                                                                    An External Product of
MAP WINDOW POSITION &
NEAREST LOCATION                                                                                                                                                                                    SmartMap Information Services

                                     SUBJECT PARCEL DESCRIPTION                            CLIENT SERVICE STANDARDS                                                                                 Based upon an extraction from the
                                                                                                                                                                                                       Digital Cadastral Data Base
                                                                                            PRINTED (dd/mm/yyyy) 11/02/2016
                                  DCDB
                                    Lot/Plan                    69/RP81810
                                    Area/Volume                 574m²
153°06'49".802                                                                              DCDB       10/02/2016
26°23'50".417                       Tenure                      FREEHOLD
SUNSHINE BEACH                      Local Government            NOOSA SHIRE
1.38 KM                                                                                     Users of the information recorded in this document (the Information) accept all responsibility and
                                    Locality                    SUNSHINE BEACH
                                                                                            risk associated with the use of the Information and should seek independent professional advice in
                                    Segment/Parcel              30803/18                    relation to dealings with property.

                                                                                            Despite Department of Natural Resources and Mines(DNRM)'s best efforts, DNRM makes
                                                                                            no representations or warranties in relation to the Information, and, to the extent permitted by law,
                                                                                            exclude or limit all warranties relating to correctness, accuracy, reliability, completeness or
                                                                                            currency and all liability for any direct, indirect and consequential costs, losses, damages and
                                                                                            expenses incurred in any way (including but not limited to that arising from negligence) in
                                                                                            connection with any use of or reliance on the Information                                                (c) The State of Queensland,

GDA                                                                                         For further information on SmartMap products visit http://nrw.qld.gov.au/property/mapping/blinmap
                                                                                                                                                                                                     (Department of Natural
                                                                                                                                                                                                     Resources and Mines) 2016.

Section 74

                                                                                                                                                                                Heavy Vehicle Routes

Map Legend
No overlays selected

                                                                                  Site: 71 Seaview Tce
                                                   Heavy vehicles on
                                                   rotation will be held
                                                   on Solway Dve. or
       Note: No loading/                           Bryan St. until
       unloading, or holding of                    called up.
       trucks will take place in
       Seaview Tce.




                                                                                                                                                          Proposed Heavy
                                                                                                                                                          Vehicle Route to
                                                                                                                                                          and from site




                                                                                                                                                                                       11 February 2016
                                   0m   450 m   900 m                      While every care is taken to ensure the accuracy of this product, neither the Noosa Council nor the State of Queensland makes
                                                                           any representations or warranties about its accuracy, reliability, completeness for any particular purpose and disclaims all
                                                                           responsibility and all liability (including without limitation, liability in negligence) for all expenses, loses, damages and costs that
                                                                           may occur as a result of the product being inaccurate or incomplete in any way or for any reason.

Section 75

                                                                                        Incorporating:




Our Ref: 151516 - RPT1                                               22 July 2016       GOLD COAST
                                                                                        (HEAD OFFICE)
Hutchinson Builders                                                                     PO Box 5021
                                                                                        GCMC QLD 9726
Level 1 / 1 Beach Road
Maroochydore                                                                            95 Upton Street
QLD 4558                                                                                Bundall QLD 4217
                                                                                        Ph: 07 5574 0733
Via Email: [email protected]
                                                                                        BRISBANE
                                                                                        Suite 1/189 Kelvin
ATTENTION: JAROD DINGLE                                                                 Grove Road
                                                                                        Kelvin Grove QLD 4059
                                                                                        Ph: 07 3839 7200
Dear Jarod,                                                                             COOMERA
                                                                                        9 Jowett Street
RE:             SITE STRUCTURE MONITORING                                               Coomera QLD 4209
                                                                                        Ph: 07 5573 6177
AT:             71 SEAVIEW TCE, SEAVIEW TERRACE SUNSHINE BEACH
                                                                                        IPSWICH
BEING:          LOT 1 ON RP197117                                                       Suite 5/5-11 Downs Street
                                                                                        North Ipswich QLD 4305
                                                                                        Ph: 07 3202 1575
In accordance with our scope of works for the above mentioned project                   SUNSHINE COAST
please find enclosed a breakdown of the monitoring program that has been                Suite 2/34 Maud Street
established for the site to date.                                                       Maroochydore QLD 4558
                                                                                        Ph: 07 5438 8104



BENNETT + BENNETT SERVICES:

           SURVEYING                      TOWN PLANNING                      SPATIAL DATA

  Land Subdivision Surveys           Development Applications &        Geospatial Services
  Building Construction Control      Application Strategies            Building Information Modelling
  Civil Construction Control         Subdivision Proposal Plans        Visualisation Services
  Community + Strata Title /         Statutory planning advice         Video Dilapidation reports
  Volumetric Surveys / Resort        Expert Witness Services           Photogrammetry (Terrestrial &
  Developments                       Development/ Property             Close Range)
  Mining & Infrastructure Projects   Feasibility and Due Diligence     Laser Scanning
  Site Detail & Feature Surveys      Urban Design Services
  Boundary Identification Surveys    Strategic Relationships
  Lease Plans

Section 76

Fee Proposal


1.0     MONITORING ZONE

A combination of fixed prism and ‘Retro’ stations have been established in accessible and cleared zones on the
subject site structures and in locations along the access easement. The below provides a visual clarification of
the monitoring stations that have been established on site to date.




                                                                                                                   2

Section 77

Fee Proposal


2.0     MONITORING STATIONS




M1 (Prism on existing Wall)           M2 (Prism on existing Wall)




M3 (Prism on existing Wall)           M4 (Prism on adjoining Pool soffit)




M5 (Prism on adjoining Pool Soffit)   M6 (Prism on adjoining Pool Soffit)




                                                                            3

Section 78

Fee Proposal




M7 (Prism on adjoining Pool wall)   R8001 (Retro on wall)




R8002 (Retro on slate)              R8003 (Retro on slate)




M6000 (Prism on existing wall)




                                                             4

Section 79

Fee Proposal


3.0        GENERAL NOTES

      1. Monitoring points have been established on all accessible and clearly visible sections of the
          site.
      2. Additional monitoring points to be established on block wall along boundary of Lot 5 on
          RP197117 once site vegetation has been cleared.
      3. Lot 6 on RP197117 will have monitoring stations established once access to site is granted and
          site vegetation has been cleared.
      4. All monitoring points have been fixed to structural elements avoiding facia and cladding
          where possible.
      5. Results for all subsequent monitoring rounds are to be issued within 24 hours of monitoring
          taking place
      6. Expected accuracies for the monitoring campaign (+/- 3mm horizontal and vertical
      7. Instrumentation to be used: Fully calibrated Trimble S6 3” instrument (3” angle and +/- 2mm +
          2ppm for distance
      8. All of our instruments have been tested against Department of Natural Resources EDM ranges
          and the associated EDM calibration certificate is attached for your reference.
      9. Redundant monitoring stations have been established outside of the proposed zone of
          influence to assist in quality assurance of deliverables
      10. All monitoring rounds are to be undertaken on site at a similar time of day and at periods
          when no heavy machinery is in operation on site. This will minimize the effects of material
          expansion and vibration.


4.0        APPENDICES

      A.   Monitoring Spreadsheet 1
      B.   Monitoring Spreadsheet 2
      C.   BBED34 – UPG Calibration Certificate
      D.   BBED34 – EDM Calibration Certificate

5.0        CONCLUSION

Please do not hesitate to contact us on (07) 5438 8104 if you would like to discuss anything further in
relation to this document, its appendices or the project specifically.

Yours faithfully

BENNETT + BENNETT



BEN MADDEN-HOLMES
Partner | Sunshine Coast Manager




                                                                                                          5

Section 80

             Client: Hutchinson Builders
             Project: 71 Seaview Terrace, Sunshine Beach
             Title: Monitoring of adjoining structures


             See Monitoring Layout Sketch for location of monitoring points



             NOTES:
             1) All residuals are differences from base observation. Easting, Northing and Elevation residuals are shown in metres (to 3 decimal places) and are
             within +/- 3 mm as per instrument specifications.
             2) A negative elevation difference refers to an increase in the reduced height of the Monitoring Point

                                                                                               Lot 2 on RP189884 (Brick Wall)                                                                                                         Lot 5 on RP197117 (Pool Structure)                                                                                                        Lot 5 on RP197117 (Block Retaining Wall on boundary)
                                                         M1 (Prism)                                      M2 (Prism)                                      M3 (Prism)                      M4 (Prism)                      M5 (Prism)                                        M6 (Prism)                      M7 (Prism)                      M8 (Retro)                          M9 (Retro)                                   M10 (Retro)                                     M11 (Retro)
  Date              Descriptor
                                            East           North          Elevation         East           North          Elevation          East           North     Elevation   East     North      Elevation   East     North          Elevation         East             North      Elevation   East     North      Elevation   East     North      Elevation   East         North            Elevation            East             North            Elevation   East     North       Elevation
22/07/2016      Base rounds read            Base            Base              Base          Base            Base            Base             Base            Base       Base      Base      Base        Base      Base      Base             Base           Base              Base        Base      Base      Base        Base                                             Monitoring points not established. Awaiting clearing of vegetation on site.
                    Round 1

Section 81

             Client: Hutchinson Builders
             Project: 71 Seaview Terrace, Sunshine Beach
             Title: Monitoring of adjoining structures


             See Monitoring Layout Sketch for location of monitoring points



             NOTES:
             1) All residuals are differences from base observation. Easting, Northing and Elevation residuals are shown in metres (to 3 decimal places) and are
             within +/- 3 mm as per instrument specifications.
             2) A negative elevation difference refers to an increase in the reduced height of the Monitoring Point

                                                                                     Lot 3 on RP189884 (Structures facing Easement)                                               Lot 2 on RP189884 (Wall facing Easement)
                                                      R8001 (Retro)                                  R8002 (Retro)                                    R8003 (Retro)                            M6000 (Prism)
   Date             Descriptor
                                           East          North           Elevation         East          North          Elevation          East          North        Elevation      East          North          Elevation
22/07/2016      Base rounds read           Base            Base               Base         Base            Base            Base            Base            Base         Base         Base           Base           Base

Section 82

 

 

 

ULTIMATE POSITIONING GROUP PTY LTD
UPG ABN 12 135 812 903
33 Allison Streat
yp Bowen ills OLD 4006
P +617 3851 e300

F464 7 3282 1278
—E OLDoffice Bupgsoiutions com

 

Calibration Certificate

Trimble S6 3” DR Plus Total station with serial number 931 1 1394 was tested on the
30 June 2015 and complies with Trimble’s manufacturer specifications:

 

MANUFACTURERS SPECIFI CATION

Angle Measurement

Accuracy (Standard deviation based on DIN 18723): 3“
Automatic Level Compensator dual-axis with a working range of: +54?

Distance Measurement
ohlance Measurement

Accuracy SDV (without Reflector) according to ISO 17123-4 +2mm +2ppm
Accuracy SDV (with Reflector) according to ISO 17123-4 + 2mm +2ppm

UPG confirms the instrument mentioned was tested over established baselines at our T; timble Certified Service
Centers (TCSC), which are regularly checked using a Total Station calibrated at a NATA certified Government
baseline. As UPG baselines are regularly checked but are not a registered baseline, if required by your state
regulations, further checking at a Government Registered Baseline is recommended.

Trimble Certified Service Center. UPG will not assume liability after the unit has been transported from UPG’s
TCSC should the instrument lose calibration.

Trimble is a Quality Assured Company and is registered as a supplier under SS-EN ISO 9001.
UPG Service Centres work to AS/NZS ISO 10012:2004 guidelines, traceable to the National Standard,

All instruments are recorded under serial number and date of testing.

 

 

 

 

Yours faithfully,
Kenny Chu
www.upgsolutions.com Trimble.

Brisbane « Rockhamptori « Townsville « Sydney © Wollongong « telbourne « Adelaide * Darwin * Hobart « PNG

 

 

 

 

 

 

 

 

 

 

 

 

Section 83

Page 1 of 2
Job Identification: BBED34_EDM CAL_150923

EDM Calibration Certificate

This report has been generated by program Baseline Version 6.1.0.3, developed by the Western Australian Land
Information Agency.

Use of this application elsewhere should rely on baseline distances certified by the relevant authority.

Observation Date: 23/09/2015 Computation Date: 4/01/2016
Instrument Operator: Liam Thierens Computation Time: 9:45:57 AM

Equipment Details

Instrument Owner: Bennett + Bennett

Owner Address: 2/34 Maud Street, Maroochydore QLD 4558 Reflector Make: | AGA Geotronics

EDM instrument Make: Trimble Reflector Model: — Old (-30 mm)

EDM Instrument Model: S6 DR300+ Serial Number: 12345

EDM Serial Number: 93111394 Reflector Constant: 9mm
Baseline Details

Name CABOOLTURE Location: Dances Rd

Authority: DNRM Last calibration Date: 20/08/2015

Authority Address:Level 4, 33 King St, CABOOLTURE, QLD, 4510

This baseline consists of known lengths, which are the certified distances between the pillars of the baseline. All certified
distances are on the same horizontal plane and on the same vertical plane running through the first and last stations.

The Baseline calibration is traceable to the Australian national standards for length.

Instrument Correction (IC) in mm (to be added to the instrument reading)

IC= -1.81- 0.00102 L

Where L = distance in metres
The reflector constant has been entered into the instrument

Calibration Parameters Value Uncertainty(95%)
Index -1.81 mm + 1.00mm
Scale -1.02 ppm + 2.00 ppm

The instrument correction has been determined from measurements in the range of 65 to 1149 metres

© Western Australian Land Information Authority 2007
4/01/2016 9:45:58 AM

Section 84

Page 2 of 2
Job Identification: BBED34_EDM CAL_150923

EDM Calibration Certificate

This report has been generated by program Baseline Version 6.1.0.3, developed by the Western Australian Land
Information Agency.

Use of this application elsewhere should rely on baseline distances certified by the relevant authority.

Uncertainty of the Instrument Correction

Minimum standard for the uncertainty of calibration of an EDM instrument is +( 4.00 mm + 20.00 ppm) as described in
terms of Recommendation No.8 of the Working Party of the National Standards Commision on the calibration of EDM
Equipment of 1 February, 1983. All uncertainties are specified at the 95 % confidence level. A coverage factor of 2 has
been used for the uncertainty computations. The Least Uncertainty of Measurement as specified by the Accreditation
Authority has been used for the uncertainty of the instrument correction.

Uncertainty of instrument correction: +( 1.00 mm+ 2.00 ppm)

Instrument Minimum
Distance Uncertainty Standard

 

(metres) (mm) (mm) Comparison Test
50 +1.10 +5.00 PASS
100 £1.20 +6.00 PASS
300 £1.60 +10.00 PASS
500 +2.00 +14.00 PASS
800 +2.60 +20.00 PASS
1100 +3.20 +26.00 PASS

This instrument satisfies the National Standards Commission standards.

First Velocity Correction (Atmospheric Correction)

The atmospheric correction dial of the EDM instrument was set for all observations. Therefore the observed distances
have already been corrected for atmospheric effects.

To obtain a Regulation 13 Certificate for the purpose of legal traceability to the Australian standard of length, contact
the Verifying Authority responsible for length measurements in your State or Territory.

The calibration of the EDM Instrument has been carried out according to DNRM Work Instructions as described
in the latest version of CBD.041230.LTOLE_EDME_Comparison_Procedure.

Data entry by: 2/47 TTULERE MES. Results checked by:
Position SCRLEYOCR Position:

Signature: we Approved Signatory:

Date: 4 J) J 6 Date:

© Western Australian Land Information Authority 2007
4/01/2016 9:45:58 AM

Section 85

                             WHS Management Plan – Appendix 1
                                              Project Risk Assessment
                                                           Version 9.2

APPENDIX 1

   PROJECT RISK ASSESSMENT

Section 86

                                                                                                 PROJECT RISK REGISTER
                Project: 71 Seaview Terrace Sunshine Beach                                                                                    Project Address: 71 Seaview Terrace Sunshine Beach Q 4567
             Project No: 24647                                                                                                       Commencement Date: July 2016-July 2018
                                                                                                                                             Project Duration: 110 weeks approx


Table 1 –Consequence
 Level         Descriptor               Health and Safety                                                                               Environmental                                                         $$$ Example
                                                                                                                                                                                                           Low Financial Loss
    1          Insignificant                 No Injuries                                                 No off-site impact, negligible on-site impact, few public complaints,             &/or
                                                                                                                                                                                                                <$500
                                             First aid treatment, on-site release immediately            No off-site impact, on-site impact easily controlled and remediated several                   Medium Financial Loss
    2          Minor                                                                                                                                                                       &/or
                                             contained                                                   community complaints.                                                                            $500 - $5,000

                                            Medical treatment required, on-site release                  On-site release contained without assistance, no effect on ecosystem                              High Financial Loss
    3          Moderate                                                                                                                                                                    &/or
                                            contained with outside assistance                            functions, negative local media coverage, multiple complaints received.                            $5,000 - $25,000

               Major                        Extensive injuries, loss of production capability, off-      Off-site impact with detrimental environmental impact attracts growing                            Major Financial Loss
    4                                                                                                                                                                                      &/or
                                            site release with no detrimental effects                     public concern and critical state / federal media coverage.                                       $25,000 – $200,000

                                                                                                         Toxic release off-site with detrimental and long term effect, major public                        Huge Financial Loss
    5          Catastrophic                 Death, toxic release off-site with detrimental effect                                                                                          &/or
                                                                                                         outrage, political / government intervention.                                                        >$200,000


Table 2 – Likelihood                                                                                  Table 3 – Risk Level / Priority
                                                                                                                                                                                 CONSEQUENCES
   Level                       Descriptor                             Description                             LIKELIHOOD
                                                                                                                                      Insignificant            Minor              Moderate        Major               Catastrophic
                                                                                                                                            1                    2                   3             4                       5
                                                           The event is expected to occur in              A (almost
         A           Almost Certain                                                                                                      H    11               H    16                E   20      E   23                  E      25
                                                           most circumstances                             certain)
                                                                                                          B (likely)                     M      7              H    12                H 17        E   21                  E      24
                                                           The event will probably occur in
         B           Likely                                                                               C (possible)                   L     4                M    8                H 13        E   18                  E      22
                                                           most circumstances
                                                                                                          D (unlikely)                   L     2                L    5                M    9      H   14                  E      19
                                                           The event might occur at some
         C           Possible
                                                           time                                           E (rare)                       L     1                L    3                M    6      H   10                  H       15
                                                           The event could occur at some               Legend
         D           Unlikely
                                                           time
                                                                                                         E: extreme risk; immediate reaction required (18-25)
                                                           The event may occur only in                   H: high risk; senior management attention needed (10-17)
         E          Rare
                                                           exceptional circumstances
                                                                                                         M: moderate risk; management responsibility must be specified (6-9)
                                                                                                         L: low risk; manage by routine procedures (1-5)



                                                                                    WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                                                                                       Page 2

Section 87

Next Review Due Date:

                        04/09/2016                        04/12/2016                            04/01/2017




Project Risk Assessment Development / Review Team

Name:           Michael Michell       Position:         Team Leader                     Signature:

Name:           Jarod Dingle          Position:         Project Manager                 Signature:

Name:           Matt Leeke            Position:         Site Manager                    Signature:

Name:           Terry Strahan         Position:         Site Foreman                    Signature:

Name:           Jesse Joyce           Position:         Site Foreman                    Signature:

Name:           Terry Strahan         Position:         Site HSE Officer                Signature:

Name:           Cameron McAndrew      Position:         Team HSE Manager                Signature:
                                                                                End of Project Review Date:




                                         WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                              Page 3

Section 88

Table of Contents
Asbestos Removal N/A ......................................................................... 5                               Post Tension Slab N/A ......................................................................... 56
Biological Hazards ................................................................................. 6                         Pre-cast and Tilt up Construction N/A ................................................. 57
Block Walls / Brick Walls ....................................................................... 7                            Public Protection ................................................................................. 58
Confined Spaces .................................................................................... 8                         Reinforcing Bars (Starter bars) ............................................................. 61
Concrete Pumping ............................................................................... 11                            Scaffolding ........................................................................................... 61
Contracted Crane Activities ................................................................. 13                               Slips, Trips and Falls ............................................................................. 63
Demolition N/A .................................................................................. 17                           Steel Erection ....................................................................................... 64
Design Risk Management Construct Only ........................................... 19                                           Suspended Swing Stage N/A ............................................................... 65
Electricity Supply ................................................................................. 21                        Traffic and Roadway Management ...................................................... 66
Elevating Work Platform Use .............................................................. 25                                  Welding and Hot Work ........................................................................ 67
Excavation and Trenching ................................................................... 30                                Work at Heights ................................................................................... 69
Explosive Power Tools ......................................................................... 33                             Work Environment Hazards ................................................................. 73
Fire Protection on Site ......................................................................... 34                           Working at a Client’s Workplace N/A .................................................. 74
First Aid ............................................................................................... 37                   Piling ………………………………………………………………………………………………..76
Formwork ........................................................................................... 39
Hazardous Substances and Dangerous Goods ..................................... 43
Lead Removal N/A.............................................................................. 46
Lighting ............................................................................................... 46
Loading Bays ....................................................................................... 47
Manual Handling ................................................................................. 47
Man/ Material Hoist N/A ................................................................... 48
Mast Climber N/A .............................................................................. 48
Noise ................................................................................................... 49
Penetrations ....................................................................................... 50
Physical and Mental Wellbeing Hazards .............................................. 51
Plant and Equipment ........................................................................... 51
Portable Power Tools .......................................................................... 55
                                                                                              WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                                                                                            Page 4

Section 89

                                                                                                                                                                                                                 Reference                                    Monitoring &




                                                                                                                                                                                                                                   Residual Risk Rating
                                       Hazard & Risks                    Risk Assessment                                                                  Control Measures
if Applicable to this
                                                                                                                                                                                                                                                                Review
                         Work                                                                                                                                                                                  Refers to WHS                               Document the person/s
      Mark X

      project

                                                                                                                           Document the control measures to be implemented in accordance with the




                                                                              Consequence




                                                                                                            Hierarchy of
                        Activity                                                                                                                                                                             legislation, C.O.P,                              responsible for




                                                                                              Risk Rating
                                                                 Likelihood
                                   Identify and document the                                                                                             HIERARCHY of CONTROLS




                                                                                                              Control
                                                                                                                                                                                                                  AS/NZS,                                 monitoring the activity to
                         steps     hazards associated with the                                                                                                                                                  Procedures /                                ensure compliance.
                                                                                                                                                                                                       PPE
                                          work activity.                                                                    Elimination   Substitution      Isolation   Engineering   Administration
                                                                                                                                                                                                                   SWMS.
                                                                                                                                1              2               3            4               5          6

                                                                 A            5              E25            5
                                                                                                      Licensed Asbestos Removalist (with the appropriate asbestos                                                WHS Act                                 Site Manager /
                   Asbestos         Friable and non-
☐                  Removal           friable asbestos
                                                                                                      removal certification) will be used for the removal of asbestos.
                                                                                                                                                                                                             
                                                                                                                                                                                                                  2011 Part 2
                                                                                                                                                                                                                  WHS Reg
                                                                                                                                                                                                                                                          Asbestos Removalist
                                                                                                  5 Licences / permits / notifications (as relevant) will be checked
                                    Exposure to asbestos                                                                                                                                                         2011
                                                                                                      at time of review of the asbestos removal plan.                                                             Chapter 8
                                     resulting in lung
                                                                                                  5 A copy of the relevant asbestos register (inclusive of relevant                                              Vic OH&S
                                     disease
                                                                                                      risk assessments) will be provided to the Asbestos Removalist.                                              Act 2004
                                     (mesothelioma etc.).                                                                                                                                                         Part 6
                                                                                                  5 The Asbestos Removalist will be provided with the specific
                                                                                                                                                                                                                 Vic OHS Reg
                                                                                                      requirements of the asbestos removal as per the COP for Safe                                                Part 4 .3 Div.
                                                                                                      Removal of Asbestos.                                                                                        5
                                                                                                  5 The asbestos removal site will be clearly defined to ensure that                                             How to
                                                                                                      non-essential persons do not enter and to warn person that                                                  safely
                                                                                                                                                                                                                  remove
                                                                                                      asbestos removal work is being carried out.
                                                                                                                                                                                                                  asbestos
                                                                                                  5   The Asbestos Removalist will be required to provide an                                                      COP 2011.
                                                                                                      Asbestos Removal Plan specific to the site.                                                                 (QLD, NSW,
                                                                                                      The Asbestos Removal Plan will addresses the following (as                                                  SA
                                                                                                      detailed in the COP - Safe Removal of Asbestos):                                                           How To
                                                                                                                                                                                                                  Manage and
                                                                                                           - Details of the ACM to be removed (e.g. the location(s),                                              Control
                                                                                                              whether it is friable or non-friable, type, condition and                                           Asbestos In
                                                                                                              the quantity to be removed);                                                                        The
                                                                                                           - Responsibilities for removal;                                                                        Workplace
                                                                                                                                                                                                                  COP 2011
                                                                                                           - Program of commencement and completion dates;                                                        (QLD,
                                                                                                           - Emergency plans;                                                                                     NSW,SA
                                                                                                           - Asbestos removal boundaries, including the type and                                                 Managing
                                                                                                              extent of the isolation required and the location of any                                            Asbestos In
                                                                                                                                                                                                                  Workplace
                                                                                                              signs and barriers;
                                                                                                                                                                                                                  VIC
                                                                                                           - Control of electrical and lighting installations;                                                    Compliance
                                                                                                           - PPE to be used, including respiratory protective                                                     Code 2008
                                                                                                              equipment;                                                                                         Removing
                                                                                                           - Details of air monitoring program;                                                                   Asbestos In
                                                                                                                                                                                                                  Workplace
                                                                                                           - Waste storage and disposal program;                                                                  VIC
                                                                                                           - Methods for removing the ACM (wet or dry methods);                                                   Compliance
                                                                                                           - Asbestos removal equipment (spray equipment,                                                         Code 2008
                                                                                                              asbestos vacuum cleaners, cutting tools, etc.);
                                                                                            WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                                                                                                                               Page 5

Section 90

                                                                   -   Details on required enclosures including details on         How to
                                                                       their size, shape, structure, etc., smoke testing            manage and
                                                                                                                                    control
                                                                       enclosures and the location of negative pressure             Asbestos In
                                                                       exhaust units;                                               The
                                                                   - Details on temporary buildings required by the                 Workplace
                                                                       asbestos removalist (e.g. decontamination units)             COP
                                                                                                                                    2012(TAS,
                                                                       including details on water, lighting and power               NT)
                                                                       requirements, negative air pressure exhaust units and       How To
                                                                       the locations of decontamination units;                      Safely
                                                                   - Other control measures to be used to contain asbestos          Remove
                                                                       within the asbestos work area;                               Asbestos
                                                                                                                                    COP 2012
                                                                   - Detailed procedures for workplace decontamination,             (TAS, NT)
                                                                       the decontamination of tools and equipment, personal
                                                                       decontamination and the decontamination of non-
                                                                       disposable PPE and RPE;
                                                                   - Methods of disposing of asbestos wastes, including
                                                                       details on the disposal of:
                                                                             o Disposable       protective    clothing   and
                                                                                equipment, and
                                                                             o The structure(s) used to enclose the removal
                                                                                area.
                                                           1    Removed asbestos materials will not be reused in the                                   Site Manager /
                                                                construction in any way.                                                               Asbestos Removalist
                                                           5   Third party air monitoring and sampling will be carried out to                          Site Manager /
                                                               ensure minimum health and safety standards for the duration                             Foreman
                                                               of any asbestos removal work.
                                                           5   A clearance certificate will be obtained from the Asbestos                              Site Manager /
                                                               Contractor on completion of any asbestos removal work prior                             Foreman
                                                               to re-entry to the asbestos removal area.
                                                           5   All dumping receipts for asbestos products will be obtained                             Site Manager /
                                                                from the Asbestos Contractor.                                                          Asbestos Removalist
                                                           5   Hutchinson Builders asbestos checklist will be completed prior                          Site Manager /
                                                               to the commencement / recommencement of site work.                                      Foreman
                                                           5   The relevant asbestos register will be updated following the                            Asbestos Removalist
                                                               asbestos removal work.

                                           C   4    E18    4   (specify insects) are a particular hazard on this site and          WH&S Act      D2   Site Manager /
    Biological    Exposure to Insects,
☒   Hazards        Snakes, Animals &                           pesticide spraying will be undertaken
                                                                                                                                
                                                                                                                                    2011 Part 2
                                                                                                                                    Vic OHS Act   L5
                                                                                                                                                       Foreman
                   Infectious Substances                   6   Workers will be encouraged to wear long sleeved shirts and           Part 3             Site Manager/ All
                                                               long pants and insect repellent to prevent mosquito bites.                              personnel
                                                           5   Any sighting of snakes will be reported to site management.                             All personnel
                                                   WHS Management Plan – Appendix 1 – Project Risk Assessment
                                                                                                                                                                        Page 6

The text continues on section 91.

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.