Original PDF page 12, section 1. The text section number identifies this passage in the reader.

                                                                           Hutchinson Builders – ABN:52 009 778 330

                              WHSMP:01 – Work Health & Safety Management Plan
                                                                                                         Version: 9.2



 1.4    Site Rules
1. All workers MUST have evidence of completion of a General Safety Induction Course and attend a
   site specific induction prior to starting work.
2. Site hours – 7.00am to 5.30pm. Pre-starts can start at 6.30am ready for work commence at 7.00
   Monday to Saturday. In Phase 2 Pre-Starts will be conducted at the offsite compound at Noosa
   Rugby Club.
3. All workers are to participate in Daily Pre-start Meetings with their employer work group
   representative to consult on health and safety issues.
4. All visitors MUST report to the site office and sign onto and off the project.
5. The following Personal Protective Equipment MUST be worn in all work areas at all times;
     Hard Hats – worn the correct way
     Hi-Vis Shirt or Hi-Vis vest worn over a shirt
     Leather safety footwear with protective cap (volleys/joggers not allowed)
     Additional safety gear - as required by employer or directed by HB excluding site sheds.
     All PPE shall be provided by the Subcontractor.
6. Alcohol and drugs of abuse are NOT permitted on site – persons under or observed to be influenced
   by alcohol or drugs at any time during working hours compromises the health and safety of workers
   and will not be ALLOWED on site.
7. Persons caught stealing items of a personal or material nature will be instantly removed from site.
8. Site amenities - lunch rooms and toilets provided are to be used. Persons observed relieving
   themselves other than in the toilets provided will result in that person being instantly removed from
   the site.
9. Subcontractor environmental responsibilities:
    Do not litter streets
    Do not loiter outside adjoining residences or in the access lane.
    No lewd behaviour or bad language.
    Radios are not permitted on site.
    Report any spills on site immediately to HB Site Management.
    No dry grinding (vacuums and other dust minimisation equipment are to be used).
    No illegal discharge of liquids on or off site.
    No entry into the conservation zone or neighbouring properties.
10. All workers are to clean up their rubbish on a DAILY or as needs basis. The Subcontractor shall
    supply all necessary labour and equipment to progressively clean up all trade rubbish to the bins
    provided. Bins shall be supplied by HB. All work areas must be kept clean, tidy and safe to
    Hutchinson Builders’ (HB) satisfaction.
11. All debris, rubble and rubbish must be disposed of in accordance with documentation, codes,
    standards, legislation, regulatory authorities etc. All waste materials that can be recycled must be
    sorted by the Subcontractor and placed in the recycling bins.
12. Workers MUST follow their employer’s site specific Safety Plans / Safe Work Methods Statements,
    site safety signs and ensure safe work practices. These shall be provided by the Subcontractor and
    be site specific, developed in consultation with their own workers.
13. Remember be AWARE of your safety and others when working with or near plant Listen – look up
    – observe – do not assist the plant operator in changing quick hitched or pin plant attachments –
    refer to your Employer SWMS.
14. Consider the SAFETY of your fellow worker and members of the public.

                                                                                                       Page 12 of 58

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.