Hutchinson Builders – ABN:52 009 778 330
WHSMP:01 – Work Health & Safety Management Plan
Version: 9.2
15. Do not expose yourself or others to hazards, follow safe work methods and the correct and safe use
of hand tools to prevent injuries.
16. Workers are not allowed to alter, remove or move temporary services out of the way, provided by
HB without prior approval of site management.
17. Electrical leads MUST be hung on an insulated Hanging Hook, Stand or Bracket where exposed to
damage, heat or water hazards – not wrapped around non insulated metal scaffold, pipe work, lift
cages or other metal objects.
18. Harassment – fighting – or any verbal threats of violence of a fellow worker will not be tolerated –
resulting in that person/persons removed from site.
19. Fire safety precautions MUST be observed.
20. No glass bottles are permitted on site. Plastic or cardboard cartons are allowed as long as they are
placed in a bin where used.
21. Permits are required for all high risk work and are to be obtained prior to the commencement of
any high risk work, no exceptions.
22. Daily Plant Pre-starts / Log books are to be completed for each piece of plant on site.
23. All injuries and incidents to be reported to site management immediately and incident report
completed.
24. Only site scaffolders are to adjust / erect / dismantle scaffold on site. All others are to gain
permission from site management.
25. The Subcontractor is not permitted to place signage (other than safety signage) on any part of the
building, formwork, screen system or attachments to the building.
26. The Subcontractor shall allow for full-time, on-site, qualified supervision for the duration of the
works, capable of taking direction from HB and carrying out such direction.
27. The Subcontractor is to have an experienced Supervisor on site at all times, with relevant experience
and authority to execute the works in accordance with the drawings and contract documents,
attend all site co-ordination meetings, control all daily work activities and comply with all HB’
document control systems eg. SWMS, WHSMP, EMP, ITPs.
28. The Subcontractor shall allow for all co-ordination of workers to site in accordance with HB Traffic
Management Plan.
29. No parking on site, along the access lane, surrounding streets or the beach access car park on
Seaview Terrace. In Phase 2 of construction all vehicles are to be parked at the off-site compound
at Noosa Rugby Club. A bus service will run between the compound and site twice a day.
30. All deliveries to site must be co-ordinated through HB Site Manager, one day in advance.
Unscheduled deliveries will be turned away and any associated costs borne by the Subcontractor.
31. Delivery trucks are to firstly park in Bryant Street, call HB Site Manager or Foreman on site and
receive permission before proceeding to site. Trucks are not permitted to stop along any part of
Seaview Terrace or the access lane.
32. Due to limited access and space, each parcel of work must be co-ordinated through HB Site
Management so that the quantity of material and number of personnel brought to site does not
exceed the capacity of the site conditions and facility.
33. The Subcontractor shall provide any task lighting required for its own use. Task lighting must
conform to the following minimum standards:
All lights to be guarded.
Lights must be permanently fixed to fit for purpose stands.
Lights to be tested and tagged by qualified electrician.
Page 13 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.