5 Workers will be trained in evacuation procedures at site Site manager/
specific induction and will be involved in refresher training foreman/ HSO
through the construction process at planned intervals; Workers
as per trial evacuations
5 Trial evacuation/s will be carried out on site and evaluation of Site
the evacuation plan will be conducted by the site manager/foreman/
management team following each trial evacuation – HSO
depending on the site drills may be;
after 3 months of commencement
when formwork or scaffolding has reached at least 4
levels
simulated medical emergency
site evacuation scenarios
within 6 monthly intervals
5 Following any change to the site emergency plans, full Site manager/
communication of the changes to all personnel working onsite foreman/ HSO
will occur via the safety committee and tool box talks.
5 Combustible materials (including waste materials and dust) All personnel
will not be permitted to accumulate to constitute a fire hazard
and the burning of materials will not be permitted on site.
5 Flammable materials will be stored on site and handled in a Site manager/
manner that minimises the risk of fire; foreman/ HSO
away from other combustible materials
Flammable signs erected adjacent to the storage area
Fire extinguisher with sign erected adjacent to the
storage area
Extinguisher tested and tagged every 6 months
to be maintained on a daily basis and assessed on
Weekly Inspection Checklist
4 Fire prevention and suppression equipment for the Site manager
completed workplace/building will be made operational as
soon as possible. This may include heat and smoke detectors,
etc.
4 All sub-contractors will provide a fire extinguisher of the Site manager/
appropriate type in the immediate area when oxy and foreman HSO
acetylene or other welding equipment is used on site.
5 Warning signs will be displayed wherever a person could Site manager
encounter materials that would burn with extraordinary speed Worker
or could cause an explosion.
1 Activities that generate flammable or explosive atmospheres Site manager/
will be eliminated. foreman / HSO
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 36
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.