c) Where eccentric loading is to be applied to U-heads (i.e.
single bearers are positioned to one side of the U-head),
the formwork drawings should state that this is permitted.
d) Details sufficient to fully describe important or unusual
features of the design.
e) Reference to documentation for proprietary items.
f) Work method statements for the erection and stripping of
the formwork assembly.
g) The areas of the form designed to carry stacked loads.
h) Acceptance criteria for single use formwork.
i) Requirements for the project documentation relating to
formwork.
j) Method of provision for field adjustment of the forms
prior to and during concrete placement.
k) Where required, location of weep holes, vibrator holes,
clean-out holes and inspection openings.
l) Sequence of concrete placement, including direction of
intended pour on ranking or sloping surfaces.
m) Wrecking strips and other details relating to stripping of
other forms.
n) Design assumptions, including those related to strength, Site Manager /
stability and stiffness. Subcontractor
o) Footing design assumptions, such as foundation material
description, safe bearing value, limitations on settlement
during erection of formwork, placement of concrete and
dismantling of formwork. Reference to information
sources such as geotechnical reports should also be
included.
p) Preparation of the foundation, such as filling, compaction
and drainage.
q) Footing details, such as type and size of footings, level of
soffit, concrete strength, reinforcement, specification and
details of site filling or compaction, and precautions
against washouts.
r) Professional engineer certification of non-proprietary
equipment.
s) Evidence that the formply conforms to Australian
Standards.
t) Vertical pour rates.
u) Methods of securing single or multiple props.
5 Hutchinson Formwork checklist to be completed prior to the Site Manager
placement of concrete on the deck.
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 42
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.