24647 - 71 SEAVIEW TCE SUNSHINE BEACH WHS Management Plan – Appendix 1 – Project Risk Assessment
5 All work at heights to be completed using Site Manager
appropriate controls. Work at Height Permit HSE Advisor
to be issued for all work at heights Subcontractor
3 Hole surrounds and hole covers are to be used Site Manager
for all open holes. Where required using HSE Advisor
suitable bunting and visual barricading is also Subcontractor
to be implemented.
4 Suitable communication method to be Site Manager
implemented between offsiders and HSE Advisor
operator. Exclusion zone to be established Subcontractor
around spin off area to prevent workers being
struck with flying spoil (clay, rock etc.)
5 When installing cages all lifting equipment to Site Manager
be attached and lifted correctly. All lifting HSE Advisor
equipment to be tested tagged and listed on Subcontractor
lifting register.
5 Ensure rig crews have a spill kit in close Site Manager
proximity to the rig and are trained in spill HSE Advisor
clean-up Subcontractor
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.