24647 - 71 SEAVIEW TCE SUNSHINE BEACH WHS Management Plan – Appendix 1 – Project Risk Assessment


                                                      5                                                      sites Industry   Site Manager
                                                          Subcontractors will ensure all persons
                                                                                                             Standard –
                                                          involved in the mobilisation, commissioning,       VIC
                                                                                                                              HSE Advisor
                                                          use, operation; maintenance, repair and                             Subcontractor
                                                          testing,     and    the     de-commissioning,
                                                          dismantling and demobilisation, of plant are
                                                          provided with all available information
                                                          relating to health and safety about the item of
                                                          plant.
                                                      6   All personnel on site must wear minimum site                        Site Manager
                                                          PPE (high visibility clothing, safety footwear                      HSE Advisor
                                                          and hard hat double up) as well as all PPE                          Subcontractor
                                                          listed in approved SWMS.
                                                      5   All subcontractors will provide a register for                      Site Manager
                                                          all equipment to be used on site. This register                     HSE Advisor
                                                          will detail records of any tests, maintenance,                      Subcontractor
                                                          inspections, commissioning or alteration of
                                                          the plant and must show when the next
                                                          service is due for each item.
                                                      5   Underground services, overhead power lines,                         Site Manager
                                                          unstable ground, and other excavations in the                       HSE Advisor
                                                          vicinity will be identified and details given to                    Subcontractor
                                                          the subcontractor prior to setup and
                                                          commencement of work.
                                                      5                                                                       Site Manager
                                                          Excavation permit to be issued prior to
                                                                                                                              HSE Advisor
                                                          commencing piling works.
                                                                                                                              Subcontractor
                                                      3   An exclusion zone will be established around                        Site Manager
                                                          piling works clearly delineating the pilling                        HSE Advisor
                                                          activities from all other plant on the project                      Subcontractor

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.