Hutchinson Builders – ABN:52 009 778 330
WHSMP:01 – Work Health & Safety Management Plan
Version: 9.2
3.1.1 First Aid Facilities
A First Aid Kit shall be stocked and replenished and is to be available and maintained in a readily accessible
location. It is the responsibility of the Site Manager / Health & Safety Advisor to ensure First Aid facilities is
adequately stocked. HB First Aid Checklist form HB-HSEQ-F-028-A shall be used to check supplies on a weekly
basis.
Additional supplies of any of the materials listed above may be necessary on sites with large numbers of
personnel. These can be obtained from the nominated safety equipment supplier.
HB will have a First Aid Officer on site at all times. All injuries must be reported to that provider in the first
instance of occurrence.
A First Aid Record will be completed for all injuries and Incident / Injury / Hazard Report Form HB-HSEQ-F-
027-B will be completed for all injuries MTI and above i.e. RWI, LTI and for all serious near miss incidents.
3.2 Public Protection Controls
HB have identified that specific public protection and exclusion controls need to be implemented throughout
the duration of all projects. These include signage informing of site activity and barriers preventing entry to
the site.
To achieve adequate public protection and exclusion zones HB will undertake the following:
Erect a Mesh fence on the proposed boundary line where exclusion is deemed necessary – refer to Appendix
1 - Project Risk Assessment for guidance and together with;
☒ Erect 1.8m high temporary fence to the property boundary;
The temporary fence will be supported by metal supports that are to be fixed as well as
additional incline bracing and supports (F brackets or star pickets secured to fence panels ),
where required, to ensure the fence cannot easily topple or collapse.
The temporary fence will be erected at the approximate boundaries, and contain lockable
gates to allow worker, vehicle and machine access.
Installed and maintained to manufactures specifications
The condition and placement of the temporary fence will be monitored on an ongoing basis
and during documented site inspections by the site team member.
Erect a gantry that complies to an engineer’s design criteria to with stand storage and design loads, on the
proposed line where exclusion is deemed necessary or where loads are being lifted over public access areas;
☐ Erect ……… high Gantry with a 5 kpa rating applied on its overhead platform to the
……………………. Boundary;
☐ Erect ……… high Gantry with a 10 kpa rating applied on its overhead platform to the
……………………. Boundary;
Installed to the engineers details and commissioning signed off by installers
Provide warning signs, flashing lights and audible alarm during lifts
Provide access lighting of at least 80 lux or natural lighting
Page 19 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.