                                                      SWMS:09 – Working with Bonded Asbestos Containing Materials – N/A
Safe Work Methods
                                                                                                                                                                  Responsible       Residual
                                                                                           H                       Controls / Work Methods
                                                                                                                                                                  Person/s for        Risk
         Job Steps                     Potential Hazards                L   C       R      O               1. Eliminate 2. Substitute 3. Isolate 4. Engineer       Monitor &       L C R
                                                                                           C                                5. Admin 6. PPE                         Review
                                                                                                 Place down 0.2mm polythene plastic drop sheets on the
                                                                                                  floor below the area where ACM is being removed
                                                                                           3
                               Contact with live electricity            C    3      H     3      De-energise or have a licensed electrician de-energise,        Licensed          D    2      L5
                                                                                    13            isolate and remove any electrical installations from the       Electrician
                                                                                                  asbestos work area.
                                                                                                 If electrical installations cannot be disconnected and
                                                                                          5
                                                                                                  removed, they MUST at the very least be de-energised.
                                                                                                 The electrical installation must be tagged and locked out so
                                                                                          5       it cannot be inadvertently re-energised.
                               Inhalation of airborne asbestos          B    4       E    5      Air monitoring should be performed whenever ACM are            Licensed B        D    3      M
                               fibres                                               21            being removed and the requirements for air monitoring          Class                         9
                                                                                                  will be determined by a competent person independent to        Removalist
                                                                                                  the person responsible for the removal work.
                                                                                                 Where air levels are > 0.01 f/mL control levels should be      Occupational
                                                                                                  reviewed and where the results show levels of > 0.02 f/mL      Hygienist
                                                                                                  work, notify regulator and investigate as per legislative
                                                                                                  requirement.
                                                                                                 Wear a half face respirator with a minimum of a Class P2
                                                                                                  particulate filter and also wear disposable coveralls that
                                                                                                  are dust / fibre penetration proof.
                                                                                                 Where possible wet removal methods are to be used to
                                                                                                  minimise the release of dust.
                                                                                                 Sheets must never be broken and are to be removed in
                                                                                                  whole pieces.
                                                                                                 The nails, screws or fixings are to be removed first without
                                                                                                  damaging / breaking the sheet into small pieces by cutting
                                                                                                  them with a chisel or punching them through the material.

584 Milton Road TOOWONG QLD 4066                               SWMS Developed by:        Jamie Gilbert                                                            VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                            Position:                 National Health & Safety Co-ordinator                                                       Page 75
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.