                                                                              SWMS:17 – Operating Mobile Plant (General)
Safe Work Methods
                                                                                                                                                              Responsible        Residual
                                                                                         H                    Controls / Work Methods
                                                                                                                                                              Person/s for         Risk
            Job Steps                       Potential Hazards             L    C    R    O            1. Eliminate 2. Substitute 3. Isolate 4. Engineer        Monitor &       L    C R
                                                                                         C                             5. Admin 6. PPE                           Review
                                      Contact with overhead power        C     5     E   1     No part of the mobile plant or person / equipment etc.,     Hutchinson         D    5        E
                                      lines                                         22          is to enter a power line exclusion zone. Note: This is 3m   Builders Site                   19
                                                                                                minimum for low voltage, if unsure check with site          Foreman
                                                                                                manager.
                                                                                                  Refer to SWMS:29 Working with Overhead Power              Plant Operator
                                                                                                  lines
                                      Contact with underground           C     5     E   5     No excavation / digging work is to commence prior to        Hutchinson         D    5        E
                                      services                                      22          the operator receiving (in writing) the prescribed          Builders Site                   19
                                                                                                information regarding the location of all underground       Foreman
                                                                                                services on site.
                                                                                                  Refer to - SWMS: 07 Excavations & Trenching.              Plant Operator
                                      Striking other plant /             C     5     E   3     If working in areas exposed to site traffic – adequate      Hutchinson         E    5       H
                                      structures / workers                          22          exclusion zones erected or public roads – as per the        Builders Site                   15
                                                                                                road management plan.                                       Foreman
                                                                                         5     Ensure travel alarms and flashing warning lights are
                                                                                                working.                                                    Plant Operator

                                                                                         5     No person is to enter into the operating zone of mobile     Workers
                                                                                                plant without first establishing contact with the
                                                                                                operator.
                                                                                         6     Operators and workers are to wear high visibility vests.
                                                                                               Where there is a potential for mobile plant to contact
                                                                                                scaffolding, formwork, tilt-up panel bracing or similar
                                                                                         3      load bearing structures, appropriate barricading must
                                                                                                be installed / erected to prevent mobile plant access
                                                                                                to the immediate area, or protect the structure from
                                                                                                such collisions.
                                                                                               Operators are not to operate plant at excessive
                                                                                                speeds, fast turns or stops
                                                                                         5
584 Milton Road TOOWONG QLD 4066                               SWMS Developed by:    Jamie Gilbert                                                             VERSION 6 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                            Position:             National Health & Safety Co-ordinator                                                        Page 14
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.