SWMS:17 – Operating Mobile Plant (General)
Safe Work Methods
Responsible Residual
H Controls / Work Methods
Person/s for Risk
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Monitor & L C R
C 5. Admin 6. PPE Review
Operators must be aware of other workers when
5 reversing, slewing or moving forward.
Contact with exposed moving C 4 E 4 All machinery is to be fitted with suitable guarding Plant Owner E 4 H
parts 18 around parts that move or transmit power. 10
Workers to keep clear of moving plant and quick
5 hitches attachments Workers
Leaving unattended plant B 4 E 5 Operators must stay in control of plant movements at Plant Operator D 3 M
21 all times when plant is operational. 9
Operators are not allowed to leave the plant when
5 booms, buckets, Masts are elevated in the air or when
the plant is left running.
Ensure that all plant is close down as per manufactures
requirements
5
Exposure to exhaust emissions C 4 E 5 No persons are to be present in a trench excavation Plant Operator E 4 H
18 whilst mobile plant is operating in close proximity. 10
Mobile plant is only to be operated in well-ventilated Workers
5 area(s). Site foreman
Exposure to excessive noise B 3 H 6 Suitable hearing protection is to be worn by personnel Plant Operator D 2 L
17 both operating mobile plant and / or working in the 5
vicinity of mobile plant where they may be exposed to Workers
an excessive noise hazard. Site foreman
Operating mobile plant inside Inhalation of fumes and gases C 4 E 4 Pre-Assess ventilation and ensure use of mechanical Plant Operator D 4 H
buildings, and client workplaces including carbon monoxide 18 assistance including air-conditioning systems (if 14
and carbon dioxide applicable) , electric blowers and extraction fans
Open all available access ways and airways to ensure Site foreman
5 maximum air flow
Workers
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 6 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 15
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.