SWMS:18 – A Pre Cast Panel Erection – N/A
Methods for monitoring and reviewing effectiveness of chosen control measures
Persons performing pre cast and tilt-up panel erection under the direction of Intermediate rigger: Follow procedure and report inconsistencies to the intermediate rigger
Hutchinson Builders Foreman: Monitor procedural requirements on site.
Developed & approved on site by:
Name: Position: Date:
Matt Leeke Site Manager/ Foreman
Workers Representative
I acknowledge that I have been trained in the SWMS listed above, the controls are clearly understood, my qualifications are current to undertake the activity, I will
comply with the SWMS and I have been consulted and had the opportunity to input into the SWMS.
PRESCRIBED CERTIFICATE HOLDERS
Name Signature Certificate Type Certificate Number Work Activity @
@ crane operator – supervising rigging, panel securing – dogging loads
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 9 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 30
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.