                                                                                     SWMS:22 – Kwik Stage Scaffolds

Safe Work Methods
                                                                                      H                    Controls / Work Methods                        Responsible        Residual
             Job Steps                     Potential Hazards            L   C    R    O            1. Eliminate 2. Substitute 3. Isolate 4. Engineer      Person/s for         Risk
                                                                                      C                             5. Admin 6. PPE                     Monitor & Review    L    C      R
                                                                        B   5     E    5            Scaffold plans are be prepared by an engineer /    Licenced            E    5      H
Planning for the erection of Kwik      Scaffold unsuitable for work                                                                                                                     15
                                                                                 24           competent person that is experienced in scaffold          Scaffolder /
Stage                                  environment
                                                                                              design.                                                   Competent Person
                                                                                                    Scaffold Plan to include site layout and details
                                                                                              of elevations and sections of the scaffold and should
                                                                                              address the following issues
                                                                                                  Basis of design
                                                                                                  Foundations (including ground conditions)
                                                                                                  Supporting structure
                                                                                                  Access and egress
                                                                                                  Tying arrangements
                                                                                                  End and bay bracing
                                                                                                  Edge protection requirements
                                                                                                  Working height of scaffold.
                                                                                                  Work and environmental loads etc.
                                                                                                    Scaffold plan to be available for inspection at
                                                                                              the work site.
                                                                        B   4     E    5            Ensure that delivery trucks are directed to a      Site foreman /
Delivery of scaffold components to     Unloading of scaffold stillage
                                                                                 21           position on site where equipment can be unloaded in       Truck diver         D    3      M
site locations                         and components from truck
                                                                                              a safe manner by using mechanical aids where                                              9
                                                                                              possible.

                                                                        B   4     E    3            Ensure that an exclusion zone is in place to       Site foreman /
                                       Workers being struck by
                                                                                 21           prevent workers and others from entering the              Scaffolder          D    3      M
                                       unloading and loading
                                                                                              unloading area.                                                                           9
                                       movements
                                                                                       5            Ensure that workers are clear when scaffold
                                                                                              components are being placed around the site
                                                                        B   5     E    5            Only a licenced scaffolder or competently          Licenced            E    5      H
Erection, alteration and dismantling   Incorrect set out and
                                                                                 24           trained person is to erect scaffolds < 4 metres high on   Scaffolder /                    1
a Kwik stage scaffold                  unstable scaffold                                                                                                                                5
                                                                                              site.                                                     Competent Person

584 Milton Road TOOWONG QLD 4066                            SWMS Developed by:   Jamie Gilbert                                                             VERSION 8 – September 2015
P: (07) 3335 5000 F: (07) 3335 5005                         Position:            National Health & Safety Co-ordinator                                                        Page 63
ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.