SWMS:24 – Working with Explosive Power Tools
Safe Work Methods
H Controls / Work Methods Responsible Residual
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for Risk
C 5. Admin 6. PPE Monitor & Review L C R
injury or property All of the above work activities shall be monitored
damage. and controlled by the person in control of the panel
crew and subcontractor.
P.P.E. to be worn
Form A
Qualifications / Competencies: Experienced qualified tradesman, trained person, qualified engineer licensed rigger and crane operator
PANEL
DATE INSPECTED DATE AND MPA DATE MPA PIOR WEIGHT DATE TO
PANEL NO. SIGNED
ENGINEER / PHOTO CONCRETE POUR LAB / TEST TO LIFT OF PANEL LIFT PANEL
OFF
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 6 – May 2014
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 92
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.