SWMS:24 – Working with Explosive Power Tools
Safe Work Methods
H Controls / Work Methods Responsible Residual
Job Steps Potential Hazards L C R O 1. Eliminate 2. Substitute 3. Isolate 4. Engineer Person/s for Risk
C 5. Admin 6. PPE Monitor & Review L C R
causing death, serious Locating pins and “R” clips to lock out braces, in
bodily injury or property 5 high risk vandal areas consider wiring off “R” clips
damage. or use lockable heads.
4 Always have the weight of the panel on the crane
until braces are secure.
5 Securing bolts are to be tension to the required
torque and as per manufacturer’s requirements.
Communication between crane operator, rigger
clutch and brace person is essential for safe
erection of panels.
Carrying out work at heights; Exposing workers to falls B 4 E When using a ladder remember: Employer D 4 H
Disconnect bracing using unsafe work 21 4 To be tied off or supported by a fellow worker Site Foreman 14
Patching panels practices with ladders and have 3 points of contact at all times. Worker
and EWP’s, causing 5 Not to climb down carrying supporting brace or
death or serious bodily heavy equipment.
injury When using Boom Lift remember:
5 Be clear of bracing and licensed to operate.
4 Wear a harness and be attached at all times.
Operating plant near secured Exposing workers to B 5 E 1 Plant movements MUST NOT come in contact with Operator D 3 M
braces falling panels where 24 secured panel bracing. 9
panels have been struck When operating plant near braces remember;
by plant movements, 5 - Use a spotter if too close to bracing.
causing death, serious 3 - Hazard tape, para webbing or signage to identify
bodily injury or property safe work area.
damage. - Use plant that can be set up clear of bracing.
5
Release of bracing on panels Exposing workers to B 5 E 5 Erection of steel work is to completed as per Worker C 5 E
Panels are to be secured to major building collapse 24 structural engineer’s DWG’s. Licenced operator 22
steel fabrication removing braces to soon Only release bracing from panels when the
before steel work is engineer has certify the steel work and confirmed
completed, causing release of bracing.
death, serious bodily
584 Milton Road TOOWONG QLD 4066 SWMS Developed by: Jamie Gilbert VERSION 6 – May 2014
P: (07) 3335 5000 F: (07) 3335 5005 Position: National Health & Safety Co-ordinator Page 91
ABN: 52 009 778 330
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.