                                                                              SWMS:26 – Demolition of Structures - N/A
 Safe Work Methods
                                                                                            H                    Controls / Work Methods                       Responsible           Residual
              Job Steps                         Potential Hazards         L   C     R       O            1. Eliminate 2. Substitute 3. Isolate 4. Engineer     Person/s for            Risk
                                                                                            C                             5. Admin 6. PPE                    Monitor & Review    L      C   R
                                                                                                     o 10m Truck or Truck / dog – ( )
                                                                                                     o Industrial Bin – ( )
                                                                                                     o Rubbish chute – ( )
                                                                                                     o ….. tonne crane to lift floor to floor – ( )
    Continuous removable of rumble                                                        5      Plan and identify loading areas where rumble is stock
     off site                               Operators exposed to         B   3     H              piled and ready for removal.                              Competent           D     2    L
                                             plant roll overs                              5      Operators to position plant near or on stock piles so     person
                                            Trucks drivers exposed                 1              as not to induce a roll over during loading the trucks.                                  5
                                             to falling objects from                7             Truck drivers to stay in trucks at all times within the   Licenced
                                             moving machinery.                                     loading zone.                                             operators and
                                            Exposing members of                           1      Entry and exits to the site to be controlled to prevent   truck drivers
                                             the public to being struck                    5       the risk of injury or damage to members of the
                                             by truck movements to                                 general public at or near the site.
                                             and from site.
    Workers understanding the              Workers exposed to risk      A   5     E       5       The competent person for demolition shall be on site    Competent person    D      3   M
     methods of demolition and               of injury due to not                   2                during the level by level demolition.                                                  9
     activities                              understanding          the             5       5       Experienced foreman with WH&S training to               Licenced operator
                                             method of demolition                                    supervise other activities.
                                             and activities.                                        All persons involved given a tool box talk on
                                                                                            5        demolition methods.
                                                                                            6       P.P.E. to be worn at all times

Signed off by:


Competent Person:                                                                                      Signature:
                 Holder of Construction Management Degree or
                    Demolition License D1



Site Manager/Foreman:                                                                                  Signature:


 584 Milton Road TOOWONG QLD 4066                              SWMS Developed by:       Jamie Gilbert                                                          VERSION 7 – September 2015
 P: (07) 3335 5000 F: (07) 3335 5005                           Position:                National Health & Safety Co-ordinator                                                   Page 102
 ABN: 52 009 778 330

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.