Hutchinson Builders – ABN:52 009 778 330
WHSMP:01 – Work Health & Safety Management Plan
Version: 9.2
15.2 Hot Work
Prior to the commencement of any hot work activity, a Hot Works Permit (HB-HSEQ-F-076) must be
completed by the person(s) requesting the permit. It then must be authorised by a Site Supervisor/Foreman,
or persons in control of the hot work. Whenever hot work is to be carried out in the specific SWMS shall be
completed. To ensure that the appropriate protection equipment is available and all necessary fire
precautions have been put into place. The operators shall wear the appropriate safety equipment and
protective clothing. Suitable screens shall be installed to prevent welding flashes affecting persons passing
the work area.
Prior to carry out any welding or cutting, procedure operators are required to:
Check that all leads, hoses and fittings are in good condition,
Check that the welder has the correct electrical tag and has been tested by a qualified
electrician,
Ensure that flash back arresters are fitted next to the regulators and hand pieces of the
oxygen and acetylene bottles,
Ensure correct PPE is used,
All welders must have correct deadmans switch or voltage reduction device (VRD) in place.
Electrical auxiliary outlets are to be blocked off on all welders.
15.3 Working at Heights
All tasks involving Working at Heights require a trained and in-date qualified person to carry out the task. The
qualification must be in Working at Heights and meet HB standards as a minimum and any other qualification
required for the task. All equipment required for Working at Heights, will be used, and with current testing
and tagging proof of in-date inspections. Working at Heights Permits (HB-HSEQ-F-077) will be required and
followed for working at heights i.e. No edge protection or in boom lifts, 100% hooked up with a harness is
required.
Platform Ladders & Ladders for Access
All ladders shall be of industrial 120kg load rating as a minimum, and shall conform to all applicable Australian
Standards.
Ladders should always be checked before use for faulty rungs or side rails and should not be
in use if faulty. It should be tagged with an “Out of Service tag,” reported and inspected by a
trained, qualified person.
The ladders should be placed on level and firm footings at a 4:1 ratio (4 meters up one meter
out), extended one meter (3 rungs) beyond the landing point, in a clearway and held by
another person as it is secured to the structure. Access points to roofs from ladders will be
free from crossbeams/posts.
Mud or grease must be cleaned off boots before attempting to climb the ladder.
A firm grip must be maintained while climbing up and down the ladder with three-point
contact with the ladder maintained at all times.
All tools and materials should be carried in a suitable pack with shoulder straps or be hoisted
by rope.
Checks must be made to determine if it is permissible to use aluminium ladders on the project
site prior to doing so.
Page 44 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.