                                                                                                             Tie Installation & Climbing of a Tower Crane Checklist
                                                                                                                                                                      HB-HSEQ-F-069-B
                                                                                                                                                                            Version: 4



PROJECT:                                                                                                             DATE:
  ITEM           TASK
                                                             ACCEPTED CRITERIA                                       CHECKED                        NOTES
   NO.       DESCRIPTION
    1        Planning.      •   The tower crane tie has been designed and certified by an engineer.
                            •   The climbing and tie installation is as per the Stage Drawings
                            •   The Building Design Team have signed off on the tie positioning
                            •   Traffic Management Plan completed:
                                     - Who is responsible for it?
                                     - Permits Received
                            •   SWMS submitted for installing ties and climbing of the crane.
                            •   SWMS submitted for using mobile crane including dual crane lifts.
                            •   Harness Register in SWMS
                            •   Rigging Crew Identified and Competencies confirmed.
                                     - Rigging Supervisor
                                     - Electrician/ Diesel Fitter (if required)
                                     - Riggers
                                     - Crane Operator
                            •   Contacted Relevant Stakeholders in advance of Climbing
                                     - Unions
                                     - Site Safety Committee
                                     - Relevant Supervisors and Subcontractors
                            •   Plant pack received for Franna crane (if required)
                            •   Confirmed induction requirements for all rigging crew.
                            •   Confirmed start times for workers onsite.
    2        Climbing Day   •   All rigging crew inducted to site
                            •   Traffic control set up as per Traffic Management Plan
                            •   Exclusion zones have been set up and are suitable.
                            •   Rigging crew have signed into SWMS and signed version given to Site Safety Advisor
                            •   Works are completed as per the sequence in the SWMS
                            •   Works don’t exceed traffic permit
                            •   On completion checks, road and foot path clear of debris, TC signs removed
The following persons confirm that the above Checklist has been implemented:

Foreman:          _________________________        _       Site Safety Advisor:      _______________________________           Crane Supplier: ________________________

Signature:        _________________________        _       Signature:                _______________________________           Signature:     ________________________

                                                                                                                                                                 Page 1 of 1

Used in these records

About this file

File size
16.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

WHSMP.pdf · 16.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.