f. Mechanical (or induced) ventilation is to be used if the
ventilation of the space is inadequate to remove fumes or
dust from the work area.
g. Chemicals involved in the work procedures must be
identified and authorised for use in the confined space.
h. Any precautions involving hot work processes (i.e.
welding, oxy-acetylene cutting) shall be identified and
documented
i. Any personal protective equipment (i.e. respirators, gas
monitors, communication devices, safety harness, safety
goggles etc.) needed to perform work safely are to be
identified and supplied to those persons involved.
j. Emergency equipment and stand-by personnel necessary
to rescue workers from the confined space must be
identified and incorporated into the work procedures.
5/ All emergency equipment (i.e. self-contained breathing HSO or Foreman /
6 apparatus, tripods, rescue harnesses etc.) and personnel Subcontractor
protective equipment are appropriate for the specific confined
space, provided, suitably maintained and tested prior to use.
5 At least one stand-by person will be present outside the HSO or Foreman /
confined space when any person is inside the confined space. Subcontractor
The person/s will be:
a. assigned to remain on the outside of, and in close
proximity to, the confined space; and
b. capable of being in continuous communication with and,
if practicable, able to observe persons inside the confined
space; and
c. capable of operating monitoring equipment used to
ensure safety during entry to and work in the confined
space; and
d. Capable of initiating emergency procedures (including
rescue procedures), if necessary.
5 A method of communication is established in the work HSO or Foreman /
procedures to allow constant monitoring of those persons Subcontractor
working in the confined space.
5 If the work environment changes, work is to be suspended HSO or Foreman /
immediately and access to the area restricted, pending Subcontractor
reassessment of the confined space.
5 All persons entering the confined space sign in and out HSO or Foreman /
including recording the dates and times of entry / exit. Subcontractor
WHS Management Plan – Appendix 1 – Project Risk Assessment
Page 10
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
WHSMP.pdfRelated documentApplication case desk ↗
About this file
- File size
- 16.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.