Skip to the record
Noosa's #1 Council Tracker.

Council archive · source document

STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125

of 492

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.

Original PDF page 129, section 1. The text section number identifies this passage in the reader.

OZCARE NOOSA AGED CARE RESIDENCE                                                             Construction Management Plan


         The proposed forms of construction and elements of the project will include but not be limited to the
         following activities;

    Prior to Operational and Site Works commencing onsite, ensure the following is complete and approvals
    and permits have been received.

         •    A completed and distributed Dilapidation report of nearby infrastructure to all stakeholders.
         •    A Vegetation Management Plan and attend a pre-start meeting with council as per DA condition
              requirements.
         •    The Engagement of a licensed fauna spotter catcher (qualified by the relevant QLD state
              government authority) to manage the protection and relocation of any fauna. Submission to
              Development services certification from the licensed Fauna Spotter Catcher that site has been
              fully inspected and necessary protection/relocation measures and procedures are in place. All as
              per DA Conditions.
         •    Natural Assets Local Law (NALL) permit as per DA requirements.
         •    Approved Site Drainage drawings and engineering calculations as per DA requirements.
         •    An approved Erosion and Sediment Control (ESC) Plan(s) and attend a pre-start meeting with
              council as per DA conditions.
         •    Architectural drawings have been submitted for approval to Development Services as per DA
              conditions.
         •    Landscape drawings have been submitted for approval to Development Services as per DA
              conditions.
         •    Attend a Construction Management Plan (CMP) pre-start meeting with Council as per DA
              conditions.
    Enabling Works

               •    Preparation of a construction trafficable surface to the existing fire trail to the rear of the
                    facility.
               •    Client Decant Works.
               •    Installation and erection of site accommodation, hoarding/fencing, environmental controls,
                    temp services.
               •    Tree & Vegetation Removal.
               •    Implement any traffic management requirements as required from CMP meeting.
    Refurbishment Works – Existing Acacia Building

               •    Client Decant Works
               •    Establish stage boundary and setup temporary fencing and hoardings.
               •    Isolate services.
               •    Complete internal and external demolition works.
               •    Complete new structural works internal & external to building.
               •    Installation of new facades and screens.
               •    Internal fit out and finishing works.
               •    Complete landscaping works.
    All Stages - Stage Establishment / Demolition / Bulk Earthworks

               •    Client Decant Works
               •    Establish stage boundary’s and setup temporary fencing and hoardings.
               •    Pothole and survey the location of existing services as required and identified on project
                    drawings.




Woollam Constructions                                                                                                 Page 4 of 17

Used in these records

About this file

File size
58.9 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdf · 58.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.