31. Work Permit Systems
The requirement for, and frequency of, Work Permits at any particular project will be discussed during the
Project Start Up Meeting. The Project Manager will make the final call on which Work Permits are required.
The following table will nominate the work permits required and the frequency the work permits will be
required to be completed:
Frequency
Required
Work Permit Title (Every day, weekly, change of tasks, at the start of works
(Y/N)
etc)
Confined space
Excavation
Hot works
Penetrations – drilling through
walls
Working at heights
Asbestos Management
Respiratory Crystalline Silica
Workers planning to undertake these tasks are required report to Site Management and identify which work
permits will be required. Work Permits are available on a cloud-based software system,
Upon completion of the activity, the worker will report back to the Site Office and sign off on the Work Permit.
All completed documents will be stored electronically.
WHS Management Plan / Page 57
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.