STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads · OPW24/0125
Very large file (58.9 MB): the whole original can take several minutes to open, especially on a phone. Text is quick to read.
Original PDF page 301, section 1. The text section number identifies this passage in the reader.
Residual
Responsible
Rating
Proposed Controls
Initial
HOC
Risk
Risk
Activity Hazards
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Workers electrocuted / EXTREME 5 All isolations of live electrical circuits will involve placing a physical lock and attachment of a danger tag with relevant Site Management
shocked details associated with the isolation (including the name of the electrician who has undertaken the isolation) to prevent Contract Partner
unauthorised access. Energy circuits under the control of clients/service/asset owners shall have a visual verification of
isolation and lock out.
Full details of the Isolation & Lock out procedure will be detailed within the electrical Contract Partner ’s Safety Plan /
SWMS. Woollam Isolation & Lock Out Permit must be completed prior to commencement of work.
Refer Woollam procedure SP:03 Isolation & Lock Out for other isolation details.
Maintenance of Workers electrocuted / EXTREME 5 All wiring (including switchboards) will be inspected and tested by a licenced electrician after completion of the wiring and Site Management
electrical circuits shocked. prior to connection for normal use and at 6 monthly intervals. Records of all testing and verification to be retained on site Electrical Contract
and provided to Woollam. Partner
Faulty installation
Workers electrocuted / EXTREME 5 Construction wiring will be visually inspected to verify the integrity of the installation every six (6) months, with records of Site Management
shocked. inspections maintained on site. Contract Partner
Faulty installation
Workers electrocuted / EXTREME 5 All inspections, tests and maintenance carried out on electrical installations and plant & equipment will be recorded and Site Management
shocked. kept onsite. Compliant equipment to be fitted with a durable tag with the name of person conducting the test, and the Contract Partner
Faulty installation test and retest dates.
Construction wiring and electrical equipment shall be verified as follows:
- New equipment prior to introduction into service
- Repaired or serviced equipment prior to returning into service after a repair or service.
- Hire equipment inspected prior to each hire and at testing intervals as per Table 6 in AS/NZS 3012
- All equipment as per table 6 in AS/NZS 3012 and in accordance with relevant state/territories legislation.
Workers electrocuted / EXTREME 5 Fixed RCDs will be tested by a licenced electrician every month by the operation of the pushbutton and undergo an Site Management
shocked. operating time at tripping current test using an RCD tester carried out by a licenced electrician every 6 months from the Contract Partner
Faulty wiring time of installation.
References AS/NZ 3012 Electrical Installations – Construction
AS/NZS 3000 Wiring
AS 3010 – Electrical installations – Generating sets
Review / Safety Interactions, Task Observations, SWMS Review, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
9.2Works around overhead and underground electrical installations
Project Hazard/Risk Assessment / Page 59 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads.pdfRelated documentApplication case desk ↗
About this file
- File size
- 58.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.